Cover Abbreviations and Terminology Table of Contents Technical Department Organization Sequence of Works: Technical Department Scope of Works: Technical Department Scope of Civil Design Team Scope of Civil QAQC Team Scope of MEP Design QAQC Team Scope of Document Control Team Scope of Works: Department Positions Technical Department Manager Civil Design Manager Civil Senior Design Engineer Civil Design Engineer Civil Design Assistant Architectural QAQC Manager Architectural QAQC Engineer Office Architectural QAQC Engineer Site MEP Technical Manager MEP Design Engineer MEP QAQC Engineer Document Control Manager Document Controller Design Control Procedures Shop Drawing Submission Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Shop Drawing Submission Cover Sheet Template Shop Drawing For Construction Stamp Template Request For Information Statement of Purpose Sequence of Works Description of Procedure Templates and Forms RFI Template Asbuilt Documentation Handover Statement of Purpose Sequence of Works Description of Procedure Templates and Forms XX Design Calculation Submission Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Design Calculation Submittal Cover Sheet Template Design Modification Control Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Design Control Sheet Template QAQC Control Procedures Material SampleData Submission Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Architectural Material Approval Submittal Template MEP Material Approval Submittal Template Material Sample Label Template Method Statement Submission Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Architectural Method Statement Submittal Template MEP Method Statement Submittal Template Material Delivery and Inspection Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Material Delivery Inspection Request Template Material Delivery Inspection Template Delivery Checklist Form Template AsBuilt Documentation Handover Statement of Purpose Sequence of Works Description of Procedure Templates and Forms ITP Form Handover Register Daily Site Diary Handover Register Material Testing Results Handover Register XX Work Demonstration Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Sequence of Works Format Attendance Signin Template Work Demonstration Report Format Work Demonstration Register Template Agenda for Plastering Work Demonstration Defect Rectification Statement of Purpose Sequence of Works Description of Procedure Templates and Forms NonConformance Report Format Defect List Format MAIN CONTRACTOR Defect Rectification Tracking Template OWNER Defect Rectification Tracking Template Warning Letter Template: Withhold Payment for Outstanding NCRs Testing of Materials Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Testing of Materials Register Template Testing and Commissioning Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Testing and Commissioning Checklist – MEP Works Testing and Commissioning Checklist – XX Works Testing and Commissioning Checklist – XX Works Testing and Commissioning Checklist – XX Works Site Inspections Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Internal ITP Checklist – MEP Works Internal ITP Checklist – XX Works Internal ITP Checklist – XX Works Internal ITP Checklist – XX Works Internal ITP Checklist – XX Works Internal ITP Checklist – XX Works ITP Template Submission Statement of Purpose Sequence of Works Description of Procedure Templates and Forms ITP Template Format FactorySupplier Inspection Statement of Purpose Sequence of Works Description of Procedure Templates and Forms FactorySupplier Inspection Report Format Material Identification Statement of Purpose Sequence of Works Description of Procedure Templates and Forms XX Document Control Procedures Document Identification Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Document Transmittal Template Transmittal Advice Template Request for Information (R.F.I.) Template Material Approval Submittal Template Shop Drawing Approval Submittal Template Method Statement Approval Submittal Template Calculation Sheet Approval Submittal Template Submission of Plan Submittal Template Site Instruction Template Document Registration Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Shop Drawing Submittal Registration Template Material Approval Submittal Registration Template Method Statement Submittal Registration Template Design Calculation Submittal Registration Template RFI Submittal Registration Template ITP Form Submittal Registration Template Document Filing – Soft Copy Version Statement of Purpose Sequence of Works Description of Procedure Templates and Forms FileSharing Server Route Map Document Filing – Hard Copy Version Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Binder Headings Format Correspondence Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Official Letter Template Document Transmittal Template Transmittal Advice Template Email Format Received Document Stamp Template Sent Document Stamp Template Internal Circulation Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Circulation Stamp Template (Document Submission) Circulation Stamp Template (Receiving Documents) Reporting Control Procedures Subcontractor Reporting Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Shop Drawing Weekly Report Template QAQC Weekly Report Template Warning Letter Template: Issue Submission Schedule for Outstanding Documents MAIN CONTRACTOR Reporting Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Engineer Daily Report Format Manager Daily Report Format Manager Weekly Report Format Monthly Report Format Meeting Control Procedures Technical Meeting (with OWNER) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format Technical Meeting (with Subcontractor) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format Internal Technical Meeting (with MAIN CONTRACTOR Staff) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format Board of Directors Meeting (with OWNER) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Meeting Presentation Format General Meeting (with OWNER) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format MEP Design Coordination Meeting (with SubContractor) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format KickOff Meeting (with SubContractor) Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Minutes of Meeting Format Scheduling Control Procedures Shop Drawing Submission Schedule Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Shop Drawing Schedule Format QAQC Submissions Schedule Statement of Purpose Sequence of Works Description of Procedure Templates and Forms QAQC Schedule Format Testing and Commissioning Schedule Statement of Purpose Sequence of Works Description of Procedure Templates and Forms Testing and Commissioning Schedule Format MEP Rooms Submissions Schedule Statement of Purpose Sequence of Works Description of Procedure Templates and Forms MEP Rooms Schedule Format QAQC Site Inspection Schedule Statement of Purpose Sequence of Works Description of Procedure Templates and Forms QAQC Site Inspection Schedule Format
Trang 1PROJECT CONTROL PROCEDURES
Department: Technical Department
Project: Sunrise City, Plot V
Location: Nguyen Huu Tho Street, Tan Hung Ward, District 7, HCMC,
Vietnam Owner: Novaland Investment Joint Stock Company
Main
Contractor: Kumho Engineering and Construction
Contract No: SR-V-6-MC/0701/NVL-KUMHO-
Trang 20.00 ABBREVIATIONS AND TERMINOLOGY
MEP Mechanical, Electrical, Plumbing
QA/QC Quality Assurance and Quality Control
RFI Request For Information
CI Client Instruction
MAS Material Approval Submittal
MSS Method Statement Submittal
ITP Inspection and Test Plan
IITP Internal Inspection and Test Plan
IDP Inspection of material Delivery Plan
SI Site Instruction
PD Project Director
Trang 30.00 TABLE OF CONTENTS
3.00 Design Control Procedures
3.01(d)(i) Shop Drawing Submission Cover Sheet Template Complete 3.01(d)(ii) Shop Drawing For Construction Stamp Template Complete
3.03 As-built Documentation Handover
3.04(d)(i) Design Calculation Submittal Cover Sheet Template Complete 3.05 Design Modification Control
Trang 43.05(a) Statement of Purpose Complete
3.05(c) Description of Procedure
4.01(d)(i) Architectural Material Approval Submittal Template Complete 4.01(d)(ii) MEP Material Approval Submittal Template Complete
4.02(d)(i) Architectural Method Statement Submittal Template Complete 4.02(d)(ii) MEP Method Statement Submittal Template Complete
4.03(d)(i) Material Delivery Inspection Request Template Complete 4.03(d)(ii) Material Delivery Inspection Template Complete
4.04 As-Built Documentation Handover
4.04(c) Description of Procedure
4.04(d)(i) ITP Form Handover Register
4.04(d)(ii) Daily Site Diary Handover Register
4.04(d)(iii) Material Testing Results Handover Register
4.05(c) Description of Procedure
4.05(d)(iv) Work Demonstration Register Template
4.05(d)(v) Agenda for Plastering Work Demonstration Complete
4.06(d)(iii)
MAIN CONTRACTOR Defect Rectification Tracking Template
Trang 54.06(d)(iv) OWNER Defect Rectification Tracking Template
4.06(d)(v)
Warning Letter Template: Withhold Payment for Outstanding NCRs
4.07(d)(i) Testing of Materials Register Template
4.08(c) Description of Procedure
4.08(d)(i) Testing and Commissioning Checklist – MEP Works Complete 4.08(d)(ii) Testing and Commissioning Checklist – XX Works
4.08(d)(iii) Testing and Commissioning Checklist – XX Works
4.08(d)(iv) Testing and Commissioning Checklist – XX Works
4.09(c) Description of Procedure
4.09(d)(ii) Internal ITP Checklist – XX Works
4.09(d)(iii) Internal ITP Checklist – XX Works
4.09(d)(iv) Internal ITP Checklist – XX Works
4.09(d)(v) Internal ITP Checklist – XX Works
4.09(d)(vi) Internal ITP Checklist – XX Works
4.10(c) Description of Procedure
4.11 Factory/Supplier Inspection
4.11(c) Description of Procedure
4.11(d)(i) Factory/Supplier Inspection Report Format Complete 4.12 Material Identification
4.12(c) Description of Procedure
5.01(d)(iii) Request for Information (R.F.I.) Template Complete 5.01(d)(iv) Material Approval Submittal Template Complete
Trang 65.01(d)(v) Shop Drawing Approval Submittal Template Complete 5.01(d)(vi) Method Statement Approval Submittal Template Complete 5.01(d)(vii) Calculation Sheet Approval Submittal Template Complete 5.01(d)(viii) Submission of Plan Submittal Template Complete
5.02(d)(i) Shop Drawing Submittal Registration Template Complete 5.02(d)(ii) Material Approval Submittal Registration Template Complete 5.02(d)(iii) Method Statement Submittal Registration Template Complete 5.02(d)(iv) Design Calculation Submittal Registration Template Complete
5.02(d)(vi) ITP Form Submittal Registration Template Complete
5.06(d)(i) Circulation Stamp Template (Document Submission) Complete 5.06(d)(ii) Circulation Stamp Template (Receiving Documents) Complete
6.00 Reporting Control Procedures
6.01(c) Description of Procedure
6.01(d)(i) Shop Drawing Weekly Report Template
6.01(d)(ii) QA/QC Weekly Report Template
Trang 76.02(a) Statement of Purpose
6.02(c) Description of Procedure
6.02(d)(ii) Manager Daily Report Format
6.02(d)(iii) Manager Weekly Report Format
6.02(d)(iv) Monthly Report Format
7.00 Meeting Control Procedures
7.01 Technical Meeting (with OWNER)
7.01(c) Description of Procedure
7.02 Technical Meeting (with Sub-contractor)
7.02(d)(i) Minutes of Meeting Format
7.03 Internal Technical Meeting (with MAIN CONTRACTOR Staff)
7.03(c) Description of Procedure
7.04 Board of Directors Meeting (with OWNER)
7.04(c) Description of Procedure
7.04(d)(i) Meeting Presentation Format
7.06 MEP Design Coordination Meeting (with Sub-Contractor)
7.06(c) Description of Procedure
7.06(d)(i) Minutes of Meeting Format
7.07 Kick-Off Meeting (with Sub-Contractor)
7.07(c) Description of Procedure
8.00 Scheduling Control Procedures
8.01 Shop Drawing Submission Schedule
8.01(c) Description of Procedure
Trang 88.01(d)(i) Shop Drawing Schedule Format
8.02(c) Description of Procedure
8.02(d)(i) QA/QC Schedule Format
8.03 Testing and Commissioning Schedule
8.03(c) Description of Procedure
8.03(d)(i) Testing and Commissioning Schedule Format
8.04(c) Description of Procedure
8.04(d)(i) MEP Rooms Schedule Format
8.05 QA/QC Site Inspection Schedule
8.05(c) Description of Procedure
8.05(d)(i) QA/QC Site Inspection Schedule Format
Trang 90.00 TECHNICAL DEPARTMENT ORGANIZATION
photo
PROJECT DIRECTOR Name
Email Phone
photo
PROJECT MANAGER Name
Email Phone
TECHNICAL DEPARTMENT
photo
TECHNICAL MANAGER Name
Email Phone
MEP QA/QC AND DESIGN TEAM CIVIL AND ARCH DESIGN TEAM CIVIL AND ARCH QA / QC TEAM DOCUMENT CONTROL TEAM
photo MEP TECHNICAL MANAGER photo CIVIL DESIGN MANAGER photo CIVIL QA/QC MANAGER photo DOCUMENT CONTROL MANAGER Name Name Name Name Email Email Email Email Phone Phone Phone Phone
photo MECHANICAL DESIGN ENGINEER photo ELECTRICAL DESIGN ENGINEER photo SENIOR CIVIL DESIGN ENGINEER photo CIVIL QA/QC ENGINEER - OFFICE photo CIVIL DOCUMENT CONTROLLER Name Name Name Name Name Email Email Email Email Email Phone Phone Phone Phone Phone
photo MECHANICAL QA/QC ENGINEER photo ELECTRICAL QA/QC ENGINEER photo CIVIL DESIGN ENGINEER photo CIVIL QA/QC ENGINEER - SITE photo CIVIL DOCUMENT CONTROLLER Name Name Name Name Name Email Email Email Email Email Phone Phone Phone Phone Phone
photo
MECHANICAL
QA/QC
ENGINEER
photo
ELECTRICAL QA/QC ENGINEER
photo
CIVIL DESIGN ASSISTANT
photo
CIVIL QA/QC ENGINEER - SITE
photo
MEP DOCUMENT CONTROLLER
Trang 100.00 TECHNICAL DEPARTMENT
Trang 11
1.00 SCOPE OF WORKS: TECHNICAL DEPARTMENT
The Technical Department includes the following works: Design, QA/QC and Document Control
1.01 SCOPE OF CIVIL DESIGN TEAM
1 Manage Civil Client Instructions and inform the Sub-Contractors accordingly
2 Manage the register of Civil shop drawings
3 Track the documentation status of Civil shop drawings
4 Reply to Civil RFIs from Sub-Contractors
5 Issue Civil RFIs to OWNER
6 Comment on Civil shop drawings
7 Attend Civil Technical Coordination Meeting with OWNER
8 Coordinate Civil design with subcontractors
9 Comment on Civil design calculations
10 Manage the handover of Civil as-built drawings to OWNER
11 Develop Engineer’s Daily Report and Manager’s Weekly Report, as necessary
12 Develop Monthly Schedule and Weekly Schedule, as necessary
13 Manage the tracking system of Civil design modifications
1.02 SCOPE OF CIVIL QA/QC TEAM
1 Conduct random quality inspections of site works
2 Comment on Civil method statements
3 Comment on Civil material samples and technical data
4 Manage the preparation and implementation of work demonstrations
5 Issue and close Civil Defect Lists and NCRs from MAIN CONTRACTOR, Construction
Team to assure rectification
6 Close Civil NCRs from OWNER, after Construction Team completes rectification
7 Inspect Civil material deliveries: approving for construction or rejecting for removal from site
8 Track quantity of Civil materials delivered and inspected
9 Manage handover of Civil as-built documents to OWNER: ITPs, Daily Site Diaries, Material
Testing, Results, etc
10 Coordinate with Civil sub-contractors for timely submission
11 Develop MAIN CONTRACTOR Monthly Report
12 Develop Engineer’s Daily Report and Manager’s Weekly Report, as necessary
13 Develop Monthly Schedule and Weekly Schedule, as necessary
14 Attend Civil Technical Coordination Meeting with OWNER
Trang 121.03 SCOPE OF MEP DESIGN AND QA/QC TEAM
This section describes the requirement for overall MEP design and QA/QC activities
MEP Design main duties and responsibilities are planning, drawing up, verification, change and interface control for design and construction drawings
Design engineers are an important of a team working on a project because they offer their expertise in technical engineering, review the feasibility of drawings made by the architects, MEP designers and other trade consultants oversee the building designs before they are implemented and also conduct periodic checks to see if the work is being performed according to the original plan Design engineers often make decisions with other team members and are responsible for ensuring that the whole project does not exceed the budget
Quality control and quality assurance are an integral part of every industry Maintaining, designing and controlling quality strategies and quality management systems, that is what forms the basic principles
of total quality management and so forms the foundation stone of QA/QC engineer job description QA/QC engineer job description also consists of providing support to the QA/QC coordinator for ensuring that all risk factors have been scientifically assessed QA/QC engineers are at the helm of project management procedures In the concluding stages of a project and frequently during project execution phase, QA/QC engineers visit working sites to check if all required standards of quality are followed There is a fine line dividing work responsibilities of QA engineer job description and QC engineer job
1 Reply to MEP RFIs from Sub-Contractors
2 Issue MEP RFIs to OWNER
3 Comment on MEP shop drawings
4 Coordinate MEP design with subcontractors
5 Comment on MEP method statements
6 Comment on MEP material samples and technical data
7 Comment on MEP calculations
8 Issue and close MEP Defect Lists and NCRs from MAIN CONTRACTOR, Construction
Team to assure rectification
9 Close MEP NCRs from OWNER, Site Team to confirm rectification
10 Inspect MEP material deliveries: approving for construction or rejecting for removal from site
11 Track quantity of MEP materials delivered and inspected
12 Attend General MEP Meeting with OWNER
13 Attend MEP Technical Coordination Meeting with OWNER
14 Coordinate with MEP subcontractors for timely submission
15 Host the MEP Sub-Contractor Coordination Meeting
16 Hand over MEP as-built documents to OWNER: ITPs, Site Diaries, Material Testing, etc
17 Manage MEP Client Instructions and inform the Sub-Contractors accordingly
Trang 1318 Approve testing and commissioning of MEP installed works, Site Team to confirm proper
function of work
19 Manage the register of MEP shop drawings
20 Develop Engineer’s Daily Report and Manager’s Weekly Report, as necessary
21 Develop Monthly Schedule and Weekly Schedule, as necessary
22 Track the status of MEP shop drawings
1.04 SCOPE OF DOCUMENT CONTROL TEAM
1 Manage the organization system of all hard copy files - MEP and Civil
2 Register the status of all documents incoming and outgoing - MEP and Civil
3 Manage the system of soft copy file-sharing of all documents – MEP and Civil
4 Manage the inter-office circulation of all relevant documents - MEP and Civil
5 Manage the identification system of all documents
6 Manage the templates and formats of standard documentation, including: letters,
transmittals, etc
7 Manage the consolidation of the MAIN CONTRACTOR Weekly Report and Monthly Report
8 Provide as-needed secretarial assistance, including: taking minutes of meetings, copying
documents, support with sending/receiving documents, scanning, etc
Trang 142.00 SCOPE OF WORKS: DEPARTMENT POSITIONS
The Technical Department includes the following positions: Technical Department Manager, Civil Design Manager, Civil Senior Design Engineer, Civil Design Engineer, Civil Design Assistant, Civil QA/QC Manager, Civil QA/QC Engineer – Office, Civil QA/QC Engineer – Site, MEP Technical
Manager, Mechanical Design Engineer, Mechanical QA/QC Engineer – Office, Mechanical QA/QC Engineer – Site, Electrical Design Engineer, Electrical QA/QC Engineer – Office, Electrical QA/QC Engineer – Site
2.01 SCOPE OF TECHNICAL DEPARTMENT MANAGER
deadline
Sub-Contractors and MAIN CONTRACTOR
concerns related to the Technical Department activities
needed
7 Manage the documentation system to assure proper record-keeping of all soft copy and
hard copy files
8 Manage the design control system to accommodate design modifications and communicate
current design with MAIN CONTRACTOR and Sub-Contractor staff
Trang 152.02 to 2.05 SCOPE OF WORKS – ARCHITECTURAL DESIGN DEPARTMENT
Job allocation
engineer
Design engineer Assistant
2.2 - Coordinate between Structural, MEP &
2.2.1 Coordinate between Structural, MEP & Architectural
2.2.2 Internal circulation for each department's review x x
2.3 - Drawings distribution Internal, to subcontractors
2.3.1 Issue to subcontractors (hard copy, soft copy) x x x x
Trang 163.1.2 Make all contractors dwg submission schedule
Tracking progress x x
3.1.3 Request and push sub-contractors for submission x x
3.2 - Review shop drawing received by Subcontractors
3.2.1 Register shop dwg submitted by subcontractors x x 3.2.2 Review and comment x x
3.3 - Circulation of draft internally, submission to NVL (Before Approval)
3.3.1 Filing hardcopy & submit to NVL (2 copies directly) x x 3.3.2 Update soft copy, distribute internally x x x 3.3 Distribute internally x x
3.4 - Track shop drawings submission, approval status
3.4.1 Make weekly status check sheet x
3.4.2 Daily check the status, send to subcontractors for revision x x
3.4.3 Stamp "For Construction" on each page x
3.4.4 Sign on each "For Construction" drawings x
3.5 - Maintain soft copy of approved shop drawings
3.5.1 Soft copy update, receive, internal distribution x
3.5.2 Convert soft copy to PDF file, distribute to each part x
3.6 - Distribute approved shop drawings internally, to each Sub-Contractors
3.6.1 Internally provide to Construction Department x x 3.6.2 Provide to subcontractors x x 3.6.3 Register sent status x x 3.7 - Find The Revision design for down cost confirmation
3.7.1 Find revision design item x x
Trang 173.7.2 Prepare revision design drawing (Before, after) x x
3.7.3 Coordinate and support to Contractor Dept to calculate
4.1 - Receive drawings related RFI from subcontractors x
2.06 SCOPE OF ARCHITECTURAL QA/QC MANAGER
rectification
8 General check & control finishing works quality MS application
List, sample taking …) & report to Technical Manager.
Trang 182.07 SCOPE OF ARCHITECTURAL QA/QC ENGINEER - OFFICE
1 Documentation at MAIN CONTRACTOR site office
2 Coordinate with OWNER & Subcontractor for material samples, document submission &
collection
3 Make records, reports, QA/QC Document register
4 Review & check Subcontractor MS submission, Technical data submission, calculation
sheet AND report to QA/QC Manager prior to submit to OWNER
5 Prepare Monthly Report
6 Summarize & Monitor Test Reports
7 Site Coordination with Civil Section, OWNER and Subcontractors
8 File document into folder, prepare Handover document
2.08 SCOPE OF ARCHITECTURAL QA/QC ENGINEER - SITE
1 Monitor Concreting for remaining items ( monitoring & Controlling concrete supply )
2 Check subcontractor work quality on site & issue Defect List to pass to Civil Section for
rectification
3 Repair Structure works defect, close MAIN CONTRACTOR NCR
4 Inspection with OWNER for Site Material Delivery
5 Close NCR of finishing works with OWNER
6 Taking samples on site for testing & getting test result report
7 Coordinate with Subcontractor for work Demonstration
8 Report to QA/QC any relevant issues to QA/QC matter
Trang 192.09 MEP DESIGN AND QA/QC MANAGER
1 Manage the QA/QC System to effectively maintain quality
2 Engage with subcontractors for timely submission of QA/QC materials and documents
3 Engage with construction team and owner for all required site inspections
4 Manage testing methodology for all materials and completed works
5 Manage site quality control methodology and system of defect rectifications
6
Address all of the owner's QA/QC requests and requirements
7 Review and approve all QA/QC documents and material samples
8 Manage QA/QC schedule
2.10 MEP DESIGN ENGINEER
1 A design engineer needs to understand what the client wants before putting down any ideas
to paper It is important that any design which is finalized is not only pleasing to the eye but meets the clients specifications and is cost-effective too
2 A design engineer needs to inspect the facilities on a site as well as all the mechanical
equipment that is in use They also need to check the equipment for pending repairs and other maintenance issues
3 Preparing and constantly reviewing master plans, construction drawings, cost estimates and
other specifications which have been prepared by the architects The designs need to be feasible before actual construction begins
4 Has to stay in touch with the Construction site managers and other superintendents so that
work can be supervised and changes to the original design made if required
5 The design engineer also has to check the materials used for construction and ensure that
only quality materials are used
6 He also needs to prepare reports on time and ensure that all records are maintained up to
date at all times
7 Most importantly, a design engineer has to ensure that all the drawings are compliant with
the law and state building codes For instance, he is responsible for installing fire alarm systems in the building, marking fire exits, ensuring that the lighting facilities are proper, have facilities for disabled people and general facilities like elevators and escalators
Trang 202.11 MEP QA/QC ENGINEER
1 The QA/QC Engineer has the responsibility of maintaining and following quality strategies
and quality systems within an organization In addition, he or she provides support to the
QA/QC Coordinator in making sure that quality risks are correctly assessed, identified and
managed for all project management procedures that require high quality project delivery and execution
2 The QA/QC Engineer is responsible for the implementation of quality control procedures
and plans for providing the more efficient onsite construction work He or she develops and maintains quality standards that apply to onsite construction work, ensuring proper implementation
3 The QA/QC Engineer reviews and approves inspections, test plans and quality control plans
from contractors He or she identifies, analyzes and resolves problems and issues with quality assurance and control for onshore site construction
4 The QA/QC Engineer plans and coordinates QA/QC activities, making certain of quality
control of the work in accordance to contract requirements
5 It is the responsibility of the QA/QC Engineer to supervise the activities of the quality service
providers and inspectors to ensure diligent performance
6 The QA/QC Engineer reviews and approves the contractors' quality documentation, and
implements contractor audits as well
2.12 SCOPE OF DOCUMENT CONTROL MANAGER
2 Assure proper record-keeping of all soft copy and hard copy files
Trang 212.13 SCOPE OF DOCUMENT CONTROLLER
complete information especially the comment of OWNER if there is a reply already.
Register.
be filed in less than one week)
with complete information (e.g reference number, date, rev no., signature, etc.)
SUB-CONTRACTOR / OWNER on the transmittal.
needs to take action (hard copy) and email to others which needs to be informed.
Trang 223.00 DESIGN CONTROL PROCEDURES
3.01 SHOP DRAWING SUBMISSION
3.01a Statement of Purpose
As per Vietnam standard of practice for large projects, shop drawings must be prepared by the MAIN CONTRACTOR (or Sub-Contractor) and approved by OWNER (or OWNER Representative) prior to commencing the construction/installation works Shop drawings must clearly show the detailed design
of the finished product, including all of the viewpoints necessary: The Vietnam Construction Code which defines the law regarding shop drawings can be found at: TCVN XXX The law clearly specifies that “XXX”
Shop drawings are to show adequate detail for proper construction/installation and must be based upon all relevant approved project design drawings Only shop drawings approved FOR CONSTRUCTION by OWNER, or OWNER Representative, can be used for construction/installation at site
The Sub-Contractor shall, at times specified and well before the relevant work proceeds, prepare and submit for review, detailed, fully co-ordinated shop drawings based on the Working Drawings, taking into account any modification either to the work or to the installation which may have taken place and correctly related to the details of the actual items of plant and equipment to be installed
The Sub-Contractor shall similarly prepare all necessary schedules of equipment, etc., and also all necessary wiring diagrams for items of electrical equipment and diagrams showing the interconnections between different items
To assist the Sub-Contractor in the preparation of his shop drawings, one set of Working Drawings shall be provided after the award of the Sub-Contract The Sub-Contractor shall be fully responsible for updating his shop drawings based on any changes to the Working Drawings which may from time
to time be required
Shop drawings shall be submitted within two months of the award of the Sub-Contract
In particular before beginning fabrication of the equipment, the submission of scaled shop drawings shall be required of all work and equipment showing the equipment working positions, the general arrangement of all plant and tank rooms, electrical equipment and electrical installations
All shop drawings shall be submitted through the Main Contractor and shall contain the Main Contractor’s endorsement that he has coordinated and checked the shop drawings
Trang 233.01b Sequence of Works
Activity: Shop Drawing Submission
Works that MUST/SHOULD be
completed prior to beginning this
3 Nominate a Contractor to carry out the works
4 Approve Structural Calculations for relevant works
5 Identify the shop drawing reference number
Works that MUST/SHOULD be
performed at the same time this
activity is being performed:
1 Approve Method Statement Submittal for relevant works
2 Verify relevant unresolved design discrepancies between shop drawings, approved design and current site condition
Works that CANNOT/SHOULD
NOT begin before this activity is
completed:
1 Carry out relevant construction/installation works
2 Carry out delivery and inspection of relevant materials
Trang 241 Submission A3 2set
4.Return from NVL with comment A3 1set
(2~14 working days)
MAIN CONTRACTOR
SUB
CONTRACTOR
1set for filling
2 & 8 Review and comment
3.Submit to NVL for approval A3 1set
6 & 9 Transmit to subcontractor
2 KH Reviews shop drawing (2~4 days)
IF Reject shop drawing
1 Subcontractor submit to KH (0.5 days)
2 KH Reviews shop drawing (2~4 days)
3.KH Submits to NVL for Approval (0.5 days)
4.Return from NVL with comment ( 2~14 days)
5.KH Transmits to Subcontractor (0.5 days)
TOTAL: 21 days
6 KH Transmits to Subcontractor with comment (0.5 days)
KH Transmits to NVL for information (0.5 days)
8 KH Reviews shop drawing (2
3.KH Submits to NVLfor Approval (0.5 days)
9 KH Transmits to Subcontractor (1 days)
OWNER
4.Return from NVL with comment ( 2~14 days)
Trang 256 KH Reviews shop drawing (2~5 days)
1.Subcontractor submit to KH (0.5 days)
4. KH transmits to Subcontractor with comment (0.5 days)
IF Rejected shop drawing
1.Subcontractor submit to KH (0.5 days)
3.KH approved and transmits to Subcontractor (0.5days) Transmits to NVL for information (0.5 days)
TOTAL: 4 ~11 days
TOTAL: 8.5~21 days
2 KH Reviews shop drawing (3~10 days)
5. Subcontractor re-submits to KH (2~5 days)
3.KH approved and transmits to Subcontractor (0.5 days) Transmits to NVL for information
Civil Shop Drawing Submittal Procedure Excluded Tile Work, external façade work, lift lobby work, cabinet work
Architectural, Structural: A3 2sets
5. Re-submission (Included comment revision)
1.Submission A3 2sets
NVL recommend KH, if have comments within 4 days
OWNER
MAIN CONTRACTOR
1set for filling
2 & 6 Review and comment
3.Transmit to NVL 1 set for information
Re-submission shop DWG procedure Submission shop DWG procedure
2 KH Reviews shop drawing (3~10 days)
4.Transmit to subcontractor 1set for re-submission
3.Transmit to subcontractor 1set for Approval
SUB
CONTRACTOR
Trang 263.KH Reviews shop drawing (1~5
3.KH Reviews shop drawing (1~5
1.Subcontractor submit to KH (0.5 days) Re-submission shop DWG procedure
TOTAL: 18~32 days
7.Subcontractor re-submits to KH (0.5
1.Subcontractor submit to KH (0.5
IF Reject shop drawing
6.KH Transmits to Subcontractor (1 days)
3.KH Reviews shop drawing (1~5 days)
6.KH Transmits to Subcontractor (1 days)
4.KH transmits to NVL KH’s comments and status(1~2
5.NVL transmits KH final shop drawing
status
(1~14 working days)
2.KH transmits to NVL for review (0.5
4.KH transmits to NVL KH’s comments and status(1~2
5.KH transmits to KH shop drawing status(1~14 working
MEP Shop Drawing Submittal Procedure For Main Schematic, Single Line Diagrams, Main Plant Rooms
7.Re-submission, if reject shop drawing
6.Transmit to subcontractor A1 1set
1.Submission A1 4sets or A3 4sets
5.Return from NVL with comment
A1 1set or A3 1set
OWNER
MAIN CONTRACTOR
SUB
CONTRACTOR
1set for filling
3.Review and comment (1~5 working days)
4.Transmit to NVL KH’s comments and status
A1 3sets or A3 3 sets
Submission shop DWG procedure
TOTAL: 16 days
KH Submits to NVL for Approval (0.5 days)
2.Transmit to NVL for review A1 2set or A3 2set
2.KH transmits to NVL for review (0.5
6.KH Transmits to Subcontractor (1 days)
4.KH transmits to NVL KH’s comments and status
(1~2 days)
5.NVL transmits to KH final shop drawing status
Trang 275.Subcontractor re-submits to KH (2~5 days)
OWNER
1.Submission A1 2sets
1set for filling
2 & 6.Review and comment
4.Transmit to subcontractor 1set for re-submission
3.Transmit to subcontractor 1set for approval
MAIN CONTRACTOR
3.Transmit to NVL 1 set for information
TOTAL: 8.5~21 days
4.KH transmits to Subcontractor with comment (0.5 days)
Re-submission shop DWG procedure Submission shop DWG procedure
1.Subcontractor submit to KH (0.5 days)
IF Rejected shop drawing
1 Subcontractor submit to KH (0.5 days)
3.KH approved and transmits to Subcontractor (0.5 days) Transmits to NVL for information (0.5 days)
TOTAL: 4 ~11 days
2.KH Reviews shop drawing (3~10 days) 2.KH Reviews shop drawing (3~10 days)
3.KH approved and transmits to Subcontractor (0.5 days)
Transmits to NVL for information
Trang 28Shop Drawing Submittal Timeline Calendar
1
Sub develops shop drawings
2 3 4 5 6 7 8 9 10 11 12 13 14
16
KH reviews shop dwgs (4 days)
17 18 19
21
NVL reviews shop drawings (14 days)
22 23 24 25 26 27 28 29 30 31 32 33 34
Trang 293.01d Templates and Forms
3.01d(i) Shop Drawing Submission Cover Sheet Template
SUNRISE CITY – PLOT V
SHOP DRAWING APPROVAL SUBMITTAL No
To: Van Viet Son
Contractor’s Comments / Recommendations Final Approval Status
Comments :
Approved As Noted B Revise and Resubmit C
Reviewer Name(s) and Signature(s):
Approved As Noted B Revise and Resubmit C
Trang 303.01d(ii) Shop Drawing for Construction Stamp Template
FOR CONSTRUCTION
This shop drawing is approved by Kumho E&C in principle only
This approval does not alleviate the sub-contractor from their responsibilities under the contract
Note: The sub-contractor is responsible for all details and dimension and that they must conform to the design drawings specification and local authority regulations
Signed:……… Date:………
Trang 313.02 REQUEST FOR INFORMATION
3.02a Statement of Purpose
As per Vietnam standard of practice for large projects, Requests For Information (RFIs) may be issued
as a means of officially confirming details which require clarification An RFI from Sub-Contractor submitted to MAIN CONTRACTOR (or from MAIN CONTRACTOR TO OWNER) must be returned with comment within a reasonable time in order for the project to progress without unnecessary delay RFIs may be used to clarify such things as: design discrepancies; color, supplier, or specification of materials; scope of works of Sub-Contractor or MAIN CONTRACTOR; proposed design or design details; etc However, Official Letters should be used, instead of RFIs, for addressing significant issues related to: contracts, finances, site security, scheduling, etc
The Vietnam Construction Code which defines the law regarding RFIs can be found at: TCVN XXX The law clearly specifies that “XXX”
3.02b Sequence of Works
Trang 332 Legend
Trang 343.02d Templates and Forms
3.02d(i) REQUEST FOR INFORMATION (R.F.I.) TEMPLATE
MAIN CONTRACTOR
Project Date
REQUEST FOR INFORMATION RFI - 0400
TO: OWNER / CONSULTANT ATTENTION:
Trang 353.03 AS-BUILT DOCUMENTATION HANDOVER
3.03a Statement of Purpose
As per Vietnam standard of practice for large projects, design as-built documentation must be handed over from MAIN CONTRACTOR to OWNER at certain stages of project completion The purposes for handing over as-built design drawings include: obtaining Vietnam government approval for proceeding with construction of architectural works after completion of structural works, obtaining Temporary Occupancy Permits prior to use of the building, document record-keeping, etc
The Vietnam Construction Code which defines as-built documentation handover can be found at: TCVN XXX The law clearly specifies that “XXX”
3.03b Sequence of Works
Activity: As-Built Documentation Handover
Works that MUST/SHOULD be
completed prior to beginning this
activity:
1 OWNER and MAIN CONTRACTOR approve of relevant completed construction/installation works by signing the Inspection and Test Plan (ITP)
2 OWNER and MAIN CONTRACTOR approve relevant as-built design drawings
Works that MUST/SHOULD be
performed at the same time this
activity is being performed:
1 File required number of sets of as-built documents for record-keeping
Works that CANNOT/SHOULD
NOT begin before this activity is
completed:
1 Apply for Building Occupancy Permit
Trang 363.03c Description of Procedure
Before the Date of Practical Completion, the Sub-Contractor shall provide “As built” drawings as specified for all equipment and systems for the complete installation, incorporating all amendments made during the course of the Sub-Contract
“As built” drawings shall be developed by competent draftsman throughout the installation program and shall form a continuously updated record of the Sub-Contract Works installed
The Sub-Contractor shall ensure that the “As-built” drawings shall conform in layout to the latest architectural “As-built” plans
The Sub-Contractor shall submit “As-built” drawings of the equipment and systems installed within false ceilings prior to installation of false ceilings
Drawings shall be prepared on the following metric scales: -
Floor plans and sections 1: 100
Plant room layouts and sections 1: 50
Details 1: 20
Three paper prints of all As built drawings together with one CD-ROM in AutoCAD format 2004 of each drawing shall be submitted to the Engineer within two months of the date of issue of the Certificate of Completion As-built drawings shall be bound in hard cover
The Sub-Contractor shall prepare “As Built” Drawings and certify on these drawings that the drawings reflect the actual works installed Two sets of these drawings (2 paper sets) and 1 set of CD-R in AutoCAD format 2007 shall be submitted to the Authorities, through the Engineer, for examination by the Authorities where required
The Sub-Contractor shall ensure that the “As Built” Drawings to be submitted for examination and certification by the Authorities shall conform in layout to the latest Architectural “As-built” Plans
The “As Built” Drawings shall be submitted to the Engineer for checking before submission
The Sub-Contractor shall ensure that this submission of “As Built” Drawings will not delay subsequent inspections and tests of authorities; otherwise he shall be fully responsible for any consequence due
to his delay
Trang 37Inspection
Installation of equipment
Shop Drawing Approved
Rejected
T&C As-built drawings
RFI-24 Hours
Rejected
Review by MAIN CONTRACTOR/
OWNER
Handover to Owner
Trang 383.03d Templates and Forms
Trang 393.04 DESIGN CALCULATION SUBMISSION
3.04a Statement of Purpose
As per Vietnam standard of practice for large projects, design calculations for certain materials/assemblies must be prepared by the MAIN CONTRACTOR (or Sub-Contractor), reviewed by
a qualified third-party checking company, and approved by OWNER (or OWNER Representative) prior
to commencing the construction/installation works Design calculations must clearly show all of the relevant calculations required to prove that the design meets the necessary requirements for: compressive strength, bending strength, wind resistance, pullout capacity, dead load, live load, etc Where design calculations are required, they must comply with the approved design drawings and project specifications for the materials/assemblies being tested
The Vietnam Construction Code which defines the law regarding design calculations can be found at: TCVN XXX The law clearly specifies that “XXX”
3.04b Sequence of Works
Activity: Design Calculation Submission
Works that MUST/SHOULD be
completed prior to beginning this
activity:
1 Identify the Design Calculation reference number
2 Receive review and approval by a qualified third-party checking company
Works that MUST/SHOULD be
performed at the same time this
activity is being performed:
1 Verify relevant unresolved design discrepancies between shop drawings, approved design and current site
Works that CANNOT/SHOULD
NOT begin before this activity is
completed:
1 Carry out relevant construction/installation works
2 Carry out delivery and inspection of relevant materials
Trang 40One approved hard copy sets for KUMHO’s filing
Subcon to prepared Structure Calculation to submit officially to KUMHO in
4 full hardcopy sets with 3 rd party’s verification reports Then KUMHO’s QA/QC section to check the type of submitted materials ( sub or main material )
KUMHO’s QA/QC to check & comment for actual site conditions
&SPEC requirements met
Check & commented Structure Calculation to be submitted to KUMHO’s PD for review & signature to
approve
Checked & commented Structure Calculation to be submitted to KUMHO’s PD for review &
NVL to review & comment ,then to sent back two approved full sets to KUMHO
with approved status
One approved copied set
to be sent back to Subcon
Approved original set for KUMHO’s filing
One signed full hardcopy sets for KUMHO filing
KUMHO ‘s QA/QC to check & comment for actual site conditions & SPEC requirements met ,then to be submitted to KUMHO’s PD for review
& signature
One signed set to be filed
at KUMHO , 3 signed full hardcopy sets to be submitted to NVL for approval
NVL to review & comment , then to send back to KUMHO two approved full hardcopy sets with approved status (A, B,C)
KUMHO to check approved status & sent back 1 approved copied full set to Subcon ,1 approved original set for filing
KUMHO to check the
type of submitted
materials & KUMHO to
review & approve for
sub-materials
KUMHO to check &
approve , then to send
back one approved full
set to Subcon., also send
one approved full set to
NVL for information , one
full set for filing
KUMHO’s QA/QC to check & comment for actual site conditions
&SPEC requirements met