Biện pháp tổ chức thi công của Công ty cổ phần xây dựng CTGT 610
Trang 1MANAGEMENT BOARD OF PROJECT 2
PROJECT ON IMPROVEMENT AND UPGRADE OF ROAD 39-2 (Trieu Duong – Diem Dien segment)
nip/cp – 14a(km64+000.00 -:- Km74+432.00) package
Detailed execution proposal
Item: casting culvert head, plate and installing
culvert
Thai binh 2009
MANAGEMENT BOARD OF PROJECT 2 PROJECT ON IMPROVEMENT AND UPGRADE OF ROAD 39-2 (Trieu Duong – Diem Dien segment)
nip/cp – 14a(km64+000.00 -:- Km74+432.00) package
Trang 2-Detailed execution proposal
Item: casting culvert head, plate and installing
culver
Contractor supervising consultant
Thai Binh 2009