Trang 1What is WBS
(Work Breakdown Structure)?
To classify the resources necessary to execute
Project in order to properly control Project
To systematically define the ALL activities(scopes)
of Project
To break down all activities with MECE(mutually
Trang 2What is WBS
(Work Breakdown Structure)?
WBS is the technique of Project control, but not
special and not new
WBS technique is breaking the work
WBS technique is to discrimination and
understanding of all activities
Trang 3What is WBS
(Purpose of WBS technique)?
Effective operation of Project execution/ control
Define each Activity for PJ
Define all required up stream information
Trang 4Type of WBS in JGC
(PLANT Engineering Business)
(Functional WBS)
Definition of Work (Activity)
and Cost by Function
Universal Coding system
within JGC Group
(Project Control WBS)
Geographical Plant Area Breakdown
Project to achieve effective and efficient PJ control.
Trang 5WBS Technique
Discrimination of work
Trang 6WBS :Discrimination of work
PCWBS vs FWBS
Trang 7FWBS CODE in JGC
JGC’s FWBS Code is specified in JGS
To use JGS, you are requested to read and
confirm the SECRECY DECLARATION
Trang 8- SECRECY DECLARATION –
(JGS)
You agree to the following terms and conditions
whenever access and use JGS
1 You shall acknowledge that JGS contain highly confidential
information and intellectual properties.
2 You shall disclose JGS only to personnel who need to know them
to the works instructed and/ or approved by JGC
3 You shall not make any use of JGS for any other purpose than that of execution of the works instructed and/or approved JGC
Trang 9What is FWBS CODE in JGC
CODE Structure
1 2 3 4 5 6 7 8
Supplementary Code
( 2 alphanumeric characters) Sub-code (4 alphanumeric characters) Prime-code (2 alphanumeric characters)
Trang 10FWBS Sample (Level-1)
Trang 11FWBS Sample (Level-2)
<For FWBS 10>
Trang 12FWBS Sample (Level-3)
13X: Detail Engineering
21X: Direct Materials
31X: Direct Labor Work
Where X=
1:Civil General
2:Concrete Structure
3:Steel Structure
4:Buildding
5:Equipment
7:Instrumentation 8:Electrical
9:Insulation A: Painting B: Fireproof & Surface Protection
Trang 13PC-WBS Sample
Plot
Area 32
FURNACE COMPRESSOR
SHELL & TUBE HEAT EXCHANGER
VESSEL
PIPE RACK
PUMP AIR FIN COOLER
VESSEL
VESSEL
Area 10
Area 20
Common: 00
Area 31
Trang 14How to decide PC-WBS?
Control objectives
Type of Project
Type of Plant
Process Unit? Utility?
Control Service
Client
Division
Discipline Lead Engineer
Time
Cost
Trang 15How to decide PC-WBS?
LEVEL 1
LEVEL 2
LEVEL 3
WORK PACKAGE
W.P NO.
SCOPE OF WORK RESPONSIBILITY Work Volume Resource SCHEDULE COST PROGRESS
PLAN FORECAST ACTUAL
Resource
• Time
• COST
• Man Power
• Deliverables
• Materials
• Construction Equipment
PC-WBS
Trang 16Work Framing Example
( P C - W B S ) 0 0
1 0 2 0 3 0 ( F - W B S ) 1 1 1 2 2 0 3 1 3 2
S T R U C T U R E E R E C T I O N 3 1 3 *
E Q U I P M E N T E R E C T I O N 3 1 5
T O W E R E R E C T I O N 3 1 5 1 *
F U R N A C E E R E C T I O N 3 1 5 6 *
C O M P R E S S O R E R E C T I O N 3 1 5 8 *
O T H E R E Q U I P E R E C T I O N 3 1 5 9 * * *
S H O P F A B R I C A T I O N 3 1 6 1 * * * * *
F I E L D I N S T A L L A T I O N 3 1 6 2 * * * * *
Trang 17Concept of Numbering(Coding)
PC - WBS F - WBS Seq.No Type
PC - WBS F - WBS Seq.No.
Type
R
PC - WBS F - WBS Suffix
Schedule Activity No.
PC - WBS F - WBS
WORK PACKAGE NO.
PC - WBS F - WBS
Cost Account No.
Purchase Order No.
BOM/BOQ Data ID