II.1. CONSTRUCTION OF CABLE JOINT TUNNEL AND CABLE TRENCH
a. Digging cable trench:
b) Placing conduit and backfilling cable trench
3.3. Construction of underground cable signalling pillar:
Together with filling soil, position locations of the underground cable signallin pillars, tighten reinforcement, install formworks for placing concrete of the pillars in place.
c. Treatment of cross intersections of underground works
When excavating and placing the cables are in contact with the underground works, the following treatment measures are used:
3.4. Construction of some cross intersections:
In the cross intersections with the road roads, cross the rivers, large drainage culverts and etc, the contractor shall research, survey and prepare the method of construciton carefully. Specially, for completed road sections, traffic division is made appropriately, construction is made at the night. Renovate the pavement in order to ensure normal circulation issues in the tommorow morning and then renovate the pavement in the original condition at the next nights.
In the case of force majeure, it is impossible to complete at a night, install steel sheets in the locations of trenches to solve temporary circulation for peope and light means for travelling in this area, to avoid the traffic jam for surrounding areas. Excavated soil shall be transported to the suburban area, clean the construction site to ensure temporary circulation in a normal way.
Order of construction and some notes when treating cross intersections in the particular locations:
* Treatment of the cross intersection with the underground culverts in Hoang Cau street,
Make layout of the construction site, appropriate traffic division. Place signs and prohibition signs under the construction requirements.
Excavate soil up to the construction landmark
Place protective concrete layer M200
Place HDPE pipes and position pipes
Place protective concrete M200 for covering HDPE pipes
Fill soil for the excavated pit and return the pavement in the original condition.
*Treatment of cross intersection in the cross intersections:
Make layout of the construction site, appropriate traffic division. Place signs and prohibition signs under the construction requirements.
Cut the existing rod.
Drive Larsen piles for anti – landslide
Excavate soil up to the construction landmark
Place bottom lining concrete and concrete protecting cables
Place HDPE pipes and position pipes
Place protective concrete for covering HDPE pipes
Remove lasen piles
Fill soil for the excavated pit and return the pavement in the original condition.