METHOD STATEMENT FOR PLASTERING & SKIM COAT WORK
Trang 1Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Riviera Point Project
METHOD STATEMENT FOR
PLASTERING &
SKIM COAT WORK
Construction Manager Engineering Manager Manager Design Manager QC/QA Manager Safety
C 28-Jan-2013 Issue for Acceptance SC Park M.Tan Bernarrd CM Leong
Trang 2Document Reference and Revision: MS for Plastering & Skim Coat work Rev_A Submission Date: 19-Dec-12
Submission Description: Plastering and Skim Coat
Doc
① What is this (typical)?
② Revise the 5.1 Human Resources (revise No2, No11:why only one?)
③ Revise the 5.2.1 Summary Procedure ( a what is “checking following” b change “brick wall”
c structure clearance? d what is “mixing of cement mortar check time to time inspection”?
④ what is contract specification?(5.3)
⑤ a External mortar admixture? (5.4)
b mix ratio?(5.4)
⑥ Size of Metal mesh? (5.5)
⑦ a How many layer? (5.6) b what kind of nail?
c how to form in-corner bead?(5.6)
⑧ What kind of Sika Latex? (5.7)
⑨ a What is this drawing means?(5.8) b are you sure you want to install surface drainage if necessary? c what is this drawing means at 13page?(5.8)
⑩ a can vinyl sheet last?(5.9), b mixing yard made of timber? c what is this description?
⑪ How you check level in the centre?(5.10)
⑫ a The amount allowed by hand mixing(5.11.1)
b use concrete batching plant?
c how to get uniform color?
① MoS can’t reflect all situations happened on job site, so represent general method, specification, rules when we do the plastering & skim coat
② Please refer to Rev_B 7 th
page (so far, for basement plastering works, we have only one team scheduled According to progress, we submit additional teams for plastering & skim coat)
③ Please refer to Rev_B 9 th
page (a deleted b changed to plastering works” c refer to 27th Page d changed “check mixing of cement mortar”
④ Please refer to Rev_B appendix 5
⑤ a We have no external admixture, Skim coat have functions to resist water
b please refer to Reb_B 10th page
⑥ The size of width is 150, 75mm
⑦ a 2 layers b we submit the sample of nail, not yet approved c we will propose the detailed drawing before we make the mock up unit
⑧ Bonding agent mixed with cement mortar, and use named
“ sika latex Refer to annex6 99th page”
⑨ a The drawing shows transportation method by manpower
⑫ a under 0.036M3 of mortar quantity can use hand mixing
b mostly use mechanical mixer
Trang 3mixing same time to get uniform color
d we will train the workers who control the mechanical mixer
A
① How many layers?, how thick?(5.11.2)
② Leveling peg: cement mortar or brick pat paste?(5.12)
③ Where is corner bead?(5.12)
④ a Render?, two coats, spattering dash coat & finished coat?(5.13)
b To separate internal & external plastering
c rc wall, brick wall?
d greater than 3.2m, shall be provided stiffener colum?
⑤ Is this plastering works description?(5.14,15,16,17, 18,19,20,23,24)
⑥ a Test report?, b tolerance?(5.25)
⑦ a What is all material t?(5.27)
b tolerance ?
① 2layers, internal thk is19mm, external thk is 20mm Skim coat thk is 1~3mm depending on surface condition
② Cement mortar will be used as Leveling peg
③ There is no corner bead
④ a Render mean plastering,
b one trade has combined into one MoS, if separate it has many duplicated pages internal and external plastering difference is only thk
c refer to Rev_B at 19th page
d irrelevant description, deleted
⑤ the description is for brick works deleted
⑥ a please refer to Rev_B’s appendix 4
b please refer to Rev_B 23th page
⑦ a main materials as cement, sand, metal mesh, nail
b moved to 5.25
Reviewer’s suggested status code for this revision only:
ICIC Consultant TYLIN Structural
Review Consultant
JRP MEP Review Consultant
KPK Cost Consultant Other (state)
Oth
er (stat e)
This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document
Trang 4Document Reference and Revision: MS for Plastering & Skim Coat work Rev_A Submission Date: 19-Dec-12
Submission Description: Plastering and Skim Coat
② Based on item 9 of Plastering Specification, there are two coats of plastering with total thickness is 19mm Why is your MOS 15mm (page 11/121)?
③ Page 12/121: The cement bags are stored on slab with 05 bags height, it means that about 500kg/m2 Please check with allowed live load of design whether it is overloaded for slab?
④ Mortar which is used for spatter-dash has to mix with bonding agent Sika Latex
⑤ Item 5.15; 5.16 are belonged to brick work MOS Why does SSY indicate in plastering MOS?
⑥ Item 5.25: Tolerance in plane is 10mm per 3m is not accepted
Since based on TCVN 5674-1992 it only allowed 2mm per 2m
⑦ Metal lath has to be applied before plastering at positions where brick wall is cut for installing concealed conduct Please show the typical detail of this case
⑧ It is not allowed to apply dry mortar on wet mortar which has high slump in order to avoid crack and hollow
⑨ For RC wall without plastering: Please state how to control to plastered layer of brick wall and concrete bare surface of RC wall are in line? And please provide detail of joint between plastered layer of brick wall and concrete bare surface of RC wall?
① Cement : sand= 1:4 is correct according to Specification Clause “plastering & Wall Tiling”
② Internal wall thk is 19mm, external wall thk is 20mm
③ Slab can bear 450kg/m2 according to structure design brief 7 th page, so within 9bags in 1m2 is safe
④ Revised Bonding agent mixed with cement mortar for plastering
Trang 5Document Reference and Revision: Submission Date: 03-Jan-13
Submission Description: MS – Typical Plastering & Skim Coat Work
Doc
1 1 Lim, RPLLC Page 3/127 in item 4.1, provide the actual brand name of the materials for plastering skimming works Material brand is SEAMASTER
1 2 Lim, RPLLC Page 10/127-what is purpose of showing brickwork workforce? It’s the proposal manpower configuratio (Pg.7)
1 3 Lim, RPLLC Please separate the work method for plastering & skimming works We will prepare the separately method
1 4 Lim, RPLLC To describe how to mix the mortar Eg how many bags of cement, bucket of sand and how much water for 1 batch
1 batch of plastering mortar includes:
- 1 Cement bag, to be batched in 2 buckets (the 18liters – bucket)
- Sand: 8 buckets
- Water: 34 litre
1 batch of binder mortar includes:
- 1 Cement bag, to be batched in 2 buckets (the 18liters – bucket)
- Sand: 8 buckets
- Water: 29 litre
1 5 Lim, RPLLC There are groove line for external wall, please include installation of groove line strips in external plastering works Inserted accordingly (Pg 78)
1 8 Tuan/Tan, ICIC Please use sand specification TCVN7570:2006 & TCXD127:1985 for mortar We will comply
1 9 Tuan/Tan, ICIC Please provide treatment tie line between plastered brick wall and bare concrete surface (without plastering) because shrinkage crack will be
1 10 Tuan/Tan, ICIC SSY is required to test mortar (test result of trial mix) before using We will comply
Reviewer’s suggested status code for this revision only:
Trang 6Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Project : Riviera Point Condominium Development
6 Plant & Machinery
7 Communication : Call-up List
8 Power
9 Lighting
10 Access and Egress
11 Emergency Preparedness
12 Risk and Control
Trang 7Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY
Appendix 1 ……….… Risk Assessment & Job Safety Analysis
Appendix 2 ………… ………Organization Chart
Appendix 3 ……… Drawings
Appendix 4 ……… ……… … Check list
Appendix 5 ……… ……… Specification
Appendix 6 ……… ……… Material safety data sheet
Appendix 7 …….…… ……… First Aid Plan
Appendix 8 …….……… Material Specification
Trang 81
Introduction
The project site is located in District 7, HCMC of Vietnam
We recognize that safety, health and environment (SHE) are primary premise in all decisions, being made for successful construction and shall comply with the relavant local authorities of Ho Chi Minh City, Socialist Republic of Vietnam
We will develop the construction method with the focus to avoid any harm to the health and safety of owner’s personnel, contractor employees and the public and also to minimize adverse effect to the natural and around environment
All necessary specifications, inspection and quality control will be complied with the contract documents, specification
If there is any discrepancy in the descriptions below, it will be designated by RPLLC
2
The abbreviations are used for this method statement, as shown below :
Definition & Abbreviation
1) Project Definition
- Project: Riviera Point Project (Phase 1A)
- Main-Contractor: Ssangyong Engineering & Construction Co.Ltd
2) Project Abbreviation
- PD: Project Director, PJC: Project company, KPLS: Keppel Land Safety team
- SHE: Safety Health Environment, RFT: Raft, SAC: Safety Awareness Center
- QA: Quality Assurance, QC: Quality Control, QS: Quality Surveyor
- DWG: Drawing, BSMT: Basement, FDN: Foundation, BLK: Block,
Trang 9[ Site Location of Riviera Point Project ]
3
Scope of work
Trang 104
4.1 Materials for Plastering work
Resources (Materials, Equipments & Human Resources)
4.2 Equipments for Plastering work
Trang 1112 Hacking machine 2010 set 5
4.3 Plan of Vertical supplying material by Hoist
Hoist will be reach 4 levels below from the level that is in progress of RC Work
Hoist
Material
Trang 124.10 Equipment Location & Lifting Loading Chart
4.11 Losistics Plan for Item
Trang 134.12 Losistics Efficiency Chart
4.13 Hoisting time schedule
Trang 145
5.1 Human Resources – Deployment of Manpower
Sequence of work
Trang 15※ For site Organization Chart, please kindly refer to Annex 2
1) Brick work Workforce Configuration (Engineer : 1 shift)
Trang 165.2 Working Flow Chart
5.2.1 Summary Procedure of Plastering working for 1 cycle
PLASTERING WORKS
FINISH
COMPLETE PLASTERING
SAND & OTHER
admixture, mesh, anchor.)
NOTE: Inspection of Debonding
surface should be after totally cured
before application of painting and
or other finishing works
INS : INSPECTION
START
AREA REPARATION
EMBEDDED PIPE OF M&E SERVICES
FIXING OF LEVEL PEG &
Trang 17floor.Clearing of area in any obstruction prior to plastering Spatter dash on
Removing of debris & laitance Removing & clean of all loosed mortar on
concrete surface if necessary
Fixing of internal or external corner bead and other accesoriec
Installation of metal lath Setting out groove line and or knife joint if necessary
5.3 Specific standard
Mortar M1 shall be used to internal( thk 19mm)
Cement Approved Brand ( Fico, Holcim, Nghi Son or
Sand
Rough sand shall be clean, natural, uncrushed or partially crushed sand of a light color, free from organic matter, suitable for use in plastering and approved by the Engineer
Water Shall be clean
Strength Composition Cement / Dry Sand = 1 /4
Trang 185.5 Metal Lath(mesh)
- Local normal metal lath
- Width : 150mm, 75mm
- Supplier : Ly Quoc Phong Co., ltd
5.6 Metal Lath(mesh) position
Trang 205.7 Bonding Agent
- Supplier : Vinkems, Sika Co., LTD
5.8 Material handling, storage and delivery
crane, tower crane, fork lift and/or by manual as appropriate
above ground level and covered by plastic protection in order to prevent water The bagged cement shall be stored in piles not more than 9 bags within 1M2
Trang 21 Skim coat material, local normal metal lath, nails, etc shall be stored in
a dry place
the materials
Trang 225.9 Mixing Yard Preparation
waterproofing, but shall have vinyl sheetI(or plywood) and mortar backing, curb around mixing yard by brick wall 100mm height(or timber have same height), 120mm width and render both side shall be provided
M&E section to install water supply pipe and drain system
5.10 Preparation of works
efflorescence, and any other deleterious substance prior to commencement of rendering
the joint with a strip of expanded metal lath 150 mm wide The expanded metal
and have sufficient depth to permit satisfactory concealment without surface
Trang 23blemish to plastering coat
(external) mortar grout
scaffolds and work platform with enough strong handrails
Trang 245.11 Construction method
5.11.1 Use of Mortar
only for small quantity
plant until attaining uniform color, and the correct amount of water shall be added to achieve workability
within 120 minutes shall be discarded as “Reject”
discarded
( 0.036m3) mixed with 4 gauge box (0.162m3) of sand
Trang 255.11.2 Thickness of plastering
Trang 265.12 Leveling Peg
and also identify the thickness of plastering
paste on to the wall surface at the size of 30 x 30 mm, with its outer most point indicating the wall finish surface
100 mm away from finished wall surface
weight to make another leveling pegs
length of the spatula which is used to spread mortar to its finish surface
Trang 275.13 Application of Plasering to Walls, Ceilings, Parapets, Beams and columns
Plastering works shall be applied two layer of plastering & finished paint
bedded compactly
Trang 28 All frames shall be carefully fixed and stayed in position and shall be anchored into walls, one end securely to frame, and other end built into joints of masonry Anchors shall be spaced as shown on the drawings
Trang 295.14 Mock-up Location:
plastering to demonstrate the proposed quality of materials and workmanship for approval at Site
for all of the plastering works for this project
5.15 Inspection for concrete block:
checking list
arranged well co-ordinate to proceed smoothly
5.16 Inspection for plastering materials:
in plane shall not exceed as below
- 3mm per 2 meter : good plastering
Trang 305.17 Defective recovering works
5.17.1 Check for Defective Works ( by check list )
5.17.2 Remedial Action for Debonding Plaster Area
rectangle with edges under-cut to form a dovetail
manner as specified for the original work
the surrounding work
5.18 Quality control plan
Trang 315.18 Quality control plan
approval prior to use on site
Trang 325.19 Safety Plan
No JOB STEPS
HAZARDS
A Identify List Personnel Required:
- Supervisors, Foreman,
- Workers, Laborers
Personnel that have attended the project HSE induction and are familiar with the task to be performed and JSA that supports the work and addresses the hazards identified in the process
Forman / Supervisor
Personal protective equipment will be issued as
a last defense mechanism in the protection of personnel from hazards identified in the process of the activities All personal protective equipment issued to personnel shall be of a standard, which is fit for purpose, inspected and found to be free from damage, instruction
in its use and fitting has been given to each employee issued with it
Forman / Supervisor / Worker
inspection by the project plant group to ensure the equipment does not expose the personnel or the environment to risk of danger
or contamination
Forman / Supervisor
B
Storage-Moving Handle Moving Ensure workers wear safety gloves, eyes protection etc…
Stack of bricks in tidy
When lifting, keep back straight and lift with legs not back Never twist when lifting
Clear access all times
Forman / Supervisor / Workers
personal
Install sign board at the edge for the warning at height
Forman / Supervisor / Workers
Materials drop down from
Trang 33
Collapse of Wet Wall in Heavy
Wind and Rain
The high of the wet wall is not over 2m for each bricklaying time
The second time bricklaying must be continued next day
The brick wall must be covered by plastic sheet
in heavy rain
Forman / Supervisor / Worker
Defective of Hand Tools,
Materials and Equipments
Inspect hand tools materials at daily prior to starting work
Mark defective hand tools, material and place it out of service
Forman
Lighting Good lighting during time of darkness Forman /
Supervisor / Worker
Electricity Check equipment daily for defects
Always earth ground welding generator sets, the cable do not cause a trip hazard at the work site
Forman / Worker
Cement Dust in Mechanical Mixing
Ensure workers wear safety PPE all times to avoid cement dust and wet mortar Forman / Worker
Completion & Cleaning
Up Always clean the work site of debris andrubbish upon completion.Always roll back cables and
power leads andstore tidy.Ensure the supervisor inspects the jobs site oncompletion
Forman /Supervisor / Worker
T H E S A F E T Y M A N A G E M E N T
Trang 345.20 Datum control
5.30.1 Controling of Line offset & marking
checked
Laser Perpedticuler Instrument
Hole ø100
Trang 35by Laser perpendicular instrument
5.21 Material Lifting
Trang 360989 798928
Site Engineer Pham Cong Hoan
GROUP 1
Supervisor Tran Van Ha
Trang 376.2 Organization chart for Electrical emergency network
Notice.:
Auto Transfer Switch inside
MR Tai0909-919-309
ENGINEER
MR CHUNG98-322-3077SUPERVISOR
012-0301-8041
MR LEEM&E MANAGER
ASSISTANT MANAGER
MR KIM
0913-897-712
MR HoangLocal manager0120-333-2415
Trang 386.3 Configuration for Safety manager
Trang 397
7.1 Temporary Power Supplying Plan
Power
temporary power from the generator, Its specification is shown as below
In case of Black out
Trang 407.2 Power Supplying Circuit & Lighting Circuit
Distributor
Distributor
Main Distributor Distributor