1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

METHOD STATEMENT FOR PRESSURE TEST ( MONG DUONG 1)

21 1,9K 13

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 21
Dung lượng 433,79 KB

Nội dung

Mong Duong1 Thermal Power Plant ProjectPROJECT : TWO(2) x 500 MW MONG DUONG 1 THERMAL POWER PLANTMong Duong1 Thermal Power Plant ProjectPROJECT : TWO(2) x 500 MW MONG DUONG 1 THERMAL POWER PLANT

FOR INFORMATION A Dec 17, 2012 Issue for Information REV DATE DESCRIPTION Y.J.Heo Y.T.Lee J Son DSGN CHKD APPD PROJECT : TWO(2) x 500 MW MONG DUONG THERMAL POWER PLANT EMPLOYER : CONSULTANT : CONTRACTOR : DESIGNED BY Y.J.Heo CHECKED BY Y.T.Lee APPROVED BY J Son DATE Dec 17, 2012 DATE Dec 17, 2012 TITLE : METHOD STATEMENT FOR PRESSURE TEST DATE PROJECT NUMBER DOCUMENT NUMBER REV Dec 17, 2012 ADB/MD1-TPIP/EPC150911 MD1-0-T-054-05-00195 A Doc No.: MD1-0-T-054-05-00195 METHOD STATEMENT FOR PRESSURE TEST Rev A Page of 17 Mong Duong1 Thermal Power Plant Project METHOD STATEMENT FOR PRESSURE TEST REV DATE DESCIPRITON BY CHECKED APPROVED A Dec 17, 2012 ISSUE FOR INFORMATION Y.J.Heo Y.T.Lee J Son METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A - TABLE OF CONTENT Purpose Scope Reference Documents Responsibility Work Sequence Inspection & Testing Safety and First AID Organization For Pressure Test Attachment Page of 17 METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page of 17 Purpose The purpose of this procedure is to provide guidelines for pressure test (hydrostatic, pneumatic) of above ground and underground piping to comply with project specification requirements Scope  This method statement describes the instructions for general requirements of pressure test of piping for the TWO(2) X 500 MW Mong Duong Thermal Power Plant  This method statement shall be read in conjunction with the related specifications, Code and standards to ensure compliance with the project requirements Reference Documents 3.1 Reference Codes and Standards  ASME B31.1 :Power Piping  ASME Sec I :Boiler and Pressure Vessel Code  ASME B31.3 :Process Piping  MD1-0-T-030-05-00072 :ITP for aboveground piping  MD1-0-T-030-05-00073 :ITP for underground piping  ERQ SEC 4.6 :Inspection and test Responsibility 4.1 Piping Manager The Piping Manager shall ensure that competent persons effectively implement this procedure 4.2 QA/QC Manager The QA/QC is responsible to ensure the quality of above scope of works 4.3 Design Manager Design Manager shall be responsible for the issuance of isometric drawings which is approved for constructions and other relevant documents necessary for installing work METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page of 17 4.4 Piping Engineer The Piping Engineer shall perform installation of piping and field work for pressure test as per this method statement Work Sequence 5.1 General execution  The test section of the line has been installed in accordance with approved drawings  The welded joints of the test section shall be completed the visual inspection, applicable NDT, PWHT and properly documented  Location marking of test blind, gauge, isolation valves or temporary spools on the DWG  Approval of test packages shall be secured before final pressure testing of the line  Partial test of the line can be done in accordance with the approved drawing  Vendor OEM and vendor recommendation shall be included in relevant test package  Approved test packages shall be submitted for “walk down” inspections Furthermore, if the lines are cleared and ready for test, a written “Inspection Request” indicating the proposed date and time shall be submitted to owner one day before the execution of pressure test  The results of test shall be recorded on “Pressure Test Report” attached to the test package  Ensure all the above ground piping spools, valves & other components installed as specified in the given approved piping drawings  Works shall be carried out in accordance with this method statement and project specifications  All Equipments / Instruments shall have a valid calibration certificate and shall be recalibrated before due date, Method statement shall be followed for calibration of Equipments / Instruments  All piping systems to be hydrostatically tested shall be vented at the high points to remove air from the system before applying pressure to the system  All through valves shall be in fully opened position during pressure test  All joints welded of flanged shall be uncovered for inspection during the test  Pressure gauges used in testing shall be installed as close as possible to the lowest & highest METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page of 17 point in the piping system to be tested  All pipe supports and anchors, including any temporary supports required due to weight of test medium shall be installed prior to pressure testing All spring-loaded pipe supports shall be locked during hydrostatic testing If any temporary supports need to be installed for pressure testing, sketch or drawing of temporary supports approved by Engineering shall be attached in the test package with isometric drawings  An adequate Pressure Relief valve shall be provided on the test manifold to protect the piping from overpressure The pop test of pressure relief valve with 110% set pressure of test pressure prior to hydro test shall be performed to ensure proper operation  Prior to commencing pressure test, it shall be confirmed that any commitments of on-destructive examinations, line check, etc have been completed and equipment such as vessels, pumps and instruments are isolated or removed from the piping by use of blinds or other suitable means  Any manifold employed for pressure testing of piping shall be separately calculated and pressure tested to the specified system test pressure before use All manifold shall meet all requirements as per Design code of the Permanent Piping and approved by engineering An isolation valve & Drain valve shall be provided between the manifold and the system being tested METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A  Page of 17 Piping Walk-down Check List included in the Test Package shall be available for walk-down prior to testing Consolidated punch items will be categorized / classified as A, B and C items in accordance with the following definitions  ‘A’ Items to be completed/corrected prior to the hydrostatic test Examples: Not welded on pressure part such as butt joint, branch joint, shoe or anchor support Not yet perform the NDE, if necessary Not yet treat PWHT, if necessary To be installed manual valves and proper supports which are born up the loading of water Non-pressure part welding such as structure steel to support, support to support Certificate of pressure gauge, water analysis Hydrotest PRV Calibration Certificate  ‘B’ Items that can be completed after hydrostatic test Examples: Reinstatement point In-line instrument item such as Relief valve, control valve, inline mixer, transmittal, etc Interface with structural steel, cable tray, etc  ‘C’ Items that can be completed/corrected during or after Initial Start-up Examples: Touch up paint Insulation work METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page of 17  Any punch items shall be recorded on the punch list in the pressure test package and designated to the action discipline which is responsible to clear the punch item  The classification of Punch list items should be agreed between HDEC and EVN as necessary The classification can depend on the future work-plans for the individual items of equipment and system affected  All weld joints which are to be taken NDE shall be confirmed by Contractor’s IPCS and attached the Preheating/PWHT/NDE Summary in the hydro test package METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A  Flow chart of pipe installation and pressure test Fabricated spools at shop Delivery to the laydown area Inspection of spools as per Isometric drawings Painting Delivery to the site Site erection Fit-up Visual inspection for fit-up Re-welding YES Preheating (If required) Welding NO NDE (If required) Post Weld Heat Treatment (If required) Pressure Test NO Page of 17 METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 10 of 17 5.2 Preparation  Pressure Water Pump  Pressure Gauge  Manifold with relief valves and temporary piping or hoses  Manifold test certificate shall be provided in test package  Verification of safety valve on line before test by HDEC Field Engineer  Blind flanges with bolts/nuts and temporary gaskets  Test Packages 5.3 Hydro Testing for GRP Pipeline Before hydro testing, pipeline should meet the following conditions:  Construction is completed according to the design requirements  System restraints such as thrust restraints, other supports and anchors are in place and properly cured with the no deflects  Pipe deflection within requirement limits  It is suggested that the length of pipeline for hydro testing not more than km however considering the system restraints and efficiency, the length can be longer  Pressure gauge and thermometer for hydro testing should be calibrated and qualified for use  Prior to testing, ensure no other foreign materials are found in the pipe For larger diameter pipe, workers can enter the pipe through inspection manhole to carry out the inspection and cleaning Wash the pipe with water if necessary  Use suitable water source close to the testing site and ensure appropriate discharge locaton, take note of the safety  Testing plan is approved METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 11 of 17 During Hydro testing:  Fill GRP pipeline with sea water or fresh water, open valves and vents to have the air removed from the line during filling  Pressurize the line slowly Ensure the gauge location will be able to read the highest pipeline pressure or make adjustment accordingly Lower point will have higher pressure Ensure the pressure at the lower point does not exceed the bearing capability of pipe, meter and valve  When the pressure reaches the testing pressure (1.5 times operating pressure), stop the pump Hold for 10minutes without any pressure drop Then release the pressure to operating pressure and hold for 20-30 minutes Inspect the pipeline, if no leakages is noticed, the test is considered successful During pressurizing process, if there are any leakages noticed, stop further pressurizing, mark the leakage locations and carry out inspection Ensure pipeline strength reliability before continue pressurizing slowly to expose all the problems till reaching the testing pressure Inspect whether the leakages increase and any other new leakages found, mark all the leakage points, record leakage patterns in order to analyze the causes and prepare for the repair proposal 5.4 Hydrostatic Test for above ground piping  The HDEC Field Engineer will record all the activities such as elevating pressure, holding time, decreasing time in order  Hydrostatic testing of the line shall be using the potable or demi water (Hydrostatic testing of the stainless steel pipe line shall be using the demi water)  The testing pressure shall be 1.5 times for hydrostatic on the design pressure of the system  Vent lines on the highest location of the test sections, are in open position during water filling to allow elimination of air within the line  The line is completely full if the water flows out from the vent lines Let the water flow for a few minutes to ensure that the air is completely eliminated within the line  At the end of hour holding time, verify the values of the pressure and transcribe these final values in the minutes of testing  In any case pipe insulation shall be carried out before hydrostatic test provided that all welded joints shall be exposed for inspection during the test METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 12 of 17 5.5 Pneumatic Test  The HDEC Field Engineer will record all activities in chart such as elevating pressure, holding time, decreasing, etc  Instrument and service air piping etc shall be subjected to air pressure test  The testing pressure shall be 1.2 times the design pressure of the system  The test medium shall be dry air or Nitrogen gas  Flange connections and all threaded joints shall be checked for leaks using a soap solution test  Compile a minute of testing and reporting the values of pressure from the beginning of the testing  At the end of hour holding time, verify the values of the pressure and record the final values in the minutes of testing 5.6 Visual Test  Piping which is normally open to the atmosphere such as drains, vents, sewers piping, the last shutoff valve etc shall not be subjected to field pressure testing Therefore, these lines are subjected to visual inspection for acceptance 5.7 Testing Medium  In general, test medium shall be potable water, which is free from all silt and non corrosive Stainless steel shall be tested using de-mineralized water, Test reports collected from HDEC shall be attached with Hydro test record Both test mediums and certificates which are applicable to testing shall be provided by Company in accordance with Project specification The test medium temperature shall be 5℃ to avoid the possibility of brittle fracture METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 13 of 17 5.8 Test Pressure  The hydrostatic test pressure which is calculated and approved by engineering shall be indicated in the line list/test package  The pressure difference between high and low positions of the test section shall be bar per 10m  Conversion of Hydrostatic head to Pressure P=r X g X (h1-h2) Where: P: Water head difference (N/m2 = Pascal)/ 105 = Bar ρ: Water density (kg/m3) g: Gravitational acceleration (9.8m/s2) h: Static head (m) * The Pressure of test section on the highest location will be decreased by bar for every 10 m from the lowest location of the test section 5.9 Test Pressure Gauges  All gauges used for field testing shall have scale range of 1.5 to times of the test pressure with 100mm dial  All pressure gauge dials shall be in kgf/cm2  All pressure gauges shall be duly calibrated every six month as per Manufacturer's recommendation using a standard dead weight gauge tester METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 14 of 17 5.10 Preparation of Test package  Test package shall include the following documents: Test report (Certificate), Line list with test pressure, Certificates of Test gauge calibration and Water analysis, Mark-up P&ID and isometric drawings as built, Welding inspection / Pre-heating / PWHT-NDT summary report, Piping Walkdown check list, Punch list, etc  The IPCS will be used to determine the completion status of welds per isometrics in a test pack  Test package has to be approved by HDEC prior to submitting to EVN to review 5.11 Filling  Ensure suitable pumps are available for filling of the system and its pressurization The specification of pumps to be used shall be provided before testing  Liquid testing medium shall be filled from the lowest point in the system to minimize the risk of trapped air pockets  After water filling and before pressurizing the line, supports shall be inspected for abnormal movement, if any is found it shall be corrected before pressurizing 5.12 Testing / Pressurizing  A minimum of two pressure gauges are required for the test system, one gauge shall be on the test pump or test manifold and a minimum of one on the system being tested  In line instruments such as control valves, orifice plate, flow meter, safety valve shall not be included in the test system  A pressure gauge shall be provided at the test manifold for guidance in bringing the system to the required pressure  Pressure shall be applied only after the system / line is ready and approved by company  Pressure shall be applied by means of a pressurizing pump, which shall be disconnected from the system and isolated by blind as soon as the test pressure is reached and the system is stabilized  Piping systems shall not be pressurized at a rate exceeding bars per minute  After all punches are cleared and walk down is completed totally, the line shall be filled with water, and shall be pressurized After the pressure is built up to the required test pressure and preliminary inspection by HDEC is completed, Company Inspectors shall be notified for final inspection of the test section METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 15 of 17  Pressure relief valves shall be set up adequately to avoid increase in pressure  PRV discharge shall be to safe location  Care shall be taken to avoid increase in pressure due to temperature variation during the test by monitoring the test pressure and releasing the same so as to maintain required pressure  Test pressure and duration shall be maintained for at least 10 minutes after the pressure is raised to the required test pressure and become stable to permit / allow for inspection of all joints for leakage or signs of failure  Any leakage found at the time of testing shall be marked, empty the line as the sequence of draining fully or partially if necessary and make the repair Then, the hydrostatic test shall be repeated 5.13 Draining  After successful completion of the test, the system shall be depressurized gradually and then drain completely  After the hydro-test has been completed, pressure shall be released in a manner and at a rate so as not to endanger personnel or damage equipments  De-pressurize the system through vent or flange “called vent.” Open manifold valves before commencement of water draining to avoid negative pressure near the pump till gauge zero, then open the vent valve  When draining the systems after testing, vent valves at high point shall be opened before opening drain valves to obviate vacuum arising in the system and possible resultant damage to vessel, etc  All vent and drains shall be opened before the system is to be drained and shall remain open till all draining is complete so as to prevent formation of vacuum in the system  Testing/draining of the system is completed, all temporary blanks and test blinds shall be removed All inline instruments, expansion joints, strainers, filter elements, and other components removed or restrained for the test shall be reinstated when pre-commissioning activities are completed  Flanged connections, which are adjacent to temporary spool pieces, shall be reinstated with new gaskets And all temporary gaskets which are used in flange connection for hydrotest shall be replaced with new ones New bolts and nuts shall be provided as per bolting and torquing procedure by qualified fitters if test bolting is not of correct grade for the service METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 16 of 17 5.14 Acceptance criteria  The values of pressure shall be kept during the period of hydro test after the pressure is raised to the required test pressure and becomes stable No leakages are visible in any point of piping system and no pressure decreases are occurred Inspection & Testing  Field Engineer shall notify QC Engineer for performing required inspection to assure that all requirements are met  All Inspection and Testing shall be performed in accordance with the Approved inspection and test plan  The last welding joint can be alternated 100% RT or UT in case of connecting each system (equipment, pipe, valve etc.) which is completed pressure test  Discipline Engineer shall notify QC Engineer for performing required inspection to assure that all requirements are met  All inspection and testing shall be performed in accordance with the approved inspection and test plan (MD1-0-T-030-05-00072, MD1-0-T-030-05-00073) Safety and First AID 7.1 Safety Instructions  Do not smoke or use free flames anywhere close the jointing areas, under any circumstances  Safety glasses and safety mask must be worn while grinding  Closed areas, such as the inside of the pipe, or protected areas should be ventilated to avoid an excessive inhalation of gas  During the time when the pressure test is in progress, the area around the circuit under pressure shall be cleared by authorized personnel and warning sign shall be installed before hydro test Patrols will also be provided to keep exclusion zone free of any unauthorized persons  Any use of airline to blow off particles from pipe interiors, operator must wear groves, goggles and a reducing nozzle must be pitted to the air hose  PTW required – all other PTWs suspended METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 17 of 17 7.2 First Aid  Excessive inhalation of vapor Go out in the open air  Ingestion Induce vomiting and call for a doctor  In case of fire use CO2, foam or powder extinguishers Extinguishers must be within reach in the working area in every moment  Emergency contact during pressure test shall be arranged such as portable walkie talkie, and mobile phone Organization for Pressure Test Prior to test, organization chart shall be checked and verified by HDEC field Engineer The chart shall be attached to test plan for verification and be checked by any HDEC field Engineer before filling the water for test Organization chart shall be revised for each package if relevant peoples are changed Attachment  Attachment #1: Check list before welding  Attachment #2: Welding inspection record  Attachment #3: Walk down inspection report before pressure test  Attachment #4: Pressure test report Attachment HYUNDAI ENG & CONST CO., LTD CHECK LIST BEFORE WELDING TWO(2) X 500MW MONG DUONG THERMAL POWER PLANT ISO DWG NO.: SYSTEM: P&I NO.: LINE NO: NO CHECK ITEM Material Verification Verifying WPS Verifying Welder’s ID Visual / Dimensional Check Edge Preparation Inspection Preheating(If required) Heat Treatment(If required) Others RESULT REMARK REMARKS : SIGNATURE SUBCONTRACTOR : CONTRACTOR : EMPLOYER : DATE FORM NO ITP-P-100-01 Attachment HYUNDAI ENG & CONST CO., LTD WELDING INSPECTION RECORD TWO(2) X 500MW MONG DUONG THERMAL POWER PLANT ISO Drawing No : Rev No : P&ID No : Line No : Joint No System : Dia (㎜) Welding Sch Visual NDE(RT/UT/MT/PT) Welder No PWHT Date Fit-up Final Kind Report No REMARK Result No SUBCONTRACTOR CONTRACTOR EMPLOYER SIGN DATE FORM NO ITP-P-100-02 Attachment HYUNDAI ENG & CONST CO., LTD WALK DOWN INSPECTION REPORT BEFORE PRESSURE TEST TWO(2) X 500MW MONG DUONG THERMAL POWER PLANT TEST PACKAGE NO.: ISO DWG NO.: P&ID NO.: LINE NO.: SYSTEM : NO CHECK ITEM RESULT Material Verification Correct Dimension, Location and Orientation Welding Completed NDE Completed PWHT Completed Valve, In-Line Item and Equipment Completed Support and Hanger Installation Others REMARK REMARKS : SIGNATURE SUBCONTRACTOR : CONTRACTOR : EMPLOYER : DATE FORM NO ITP-P-100-03 Attachment HYUNDAI ENG & CONST CO., LTD PRESSURE TEST REPORT TWO(2) X 500MW MONG DUONG THERMAL POWER PLANT TEST PACKAGE NO.: ISO DWG NO.: P&ID NO.: LINE NO.: SYSTEM : DATE OF TEST: TYPE OF TEST : DESIGN PRESSURE / TEMP : □ HYDROSTATIC □ PNEUMATIC □ OTHERS REQUIRED TEST PRESSURE : TEST MEDIUM / TEMP : ACTUAL TEST PRESSURE : PRESSURE GAUGE SERIAL NO.: PRESURE HOLDING TIME : MIN., START : FINISH : SKETCH OF TEST BOUNDARIES : RESULT : ACCEPT REJECT REMARK : SIGNATURE SUBCONTRACTOR : CONTRACTOR : EMPLOYER : DATE FORM NO ITP-P-100-04 [...]... CONTRACTOR : EMPLOYER : DATE FORM NO ITP-P-100-03 Attachment 4 HYUNDAI ENG & CONST CO., LTD PRESSURE TEST REPORT TWO(2) X 500MW MONG DUONG 1 THERMAL POWER PLANT TEST PACKAGE NO.: ISO DWG NO.: P&ID NO.: LINE NO.: SYSTEM : DATE OF TEST: TYPE OF TEST : DESIGN PRESSURE / TEMP : □ HYDROSTATIC □ PNEUMATIC □ OTHERS REQUIRED TEST PRESSURE : TEST MEDIUM / TEMP : ACTUAL TEST PRESSURE : PRESSURE GAUGE SERIAL NO.:... Hydrostatic head to Pressure P=r X g X (h1-h2) Where: P: Water head difference (N/m2 = Pascal)/ 105 = Bar ρ: Water density (kg/m3) g: Gravitational acceleration (9 .8m/s2) h: Static head (m) * The Pressure of test section on the highest location will be decreased by 1 bar for every 10 m from the lowest location of the test section 5.9 Test Pressure Gauges  All gauges used for field testing shall have... of the test pressure with 100mm dial  All pressure gauge dials shall be in kgf/cm2  All pressure gauges shall be duly calibrated every six month as per Manufacturer's recommendation using a standard dead weight gauge tester METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 14 of 17 5.10 Preparation of Test package  Test package shall include the following documents: Test. .. be taken to avoid increase in pressure due to temperature variation during the test by monitoring the test pressure and releasing the same so as to maintain required pressure  Test pressure and duration shall be maintained for at least 10 minutes after the pressure is raised to the required test pressure and become stable to permit / allow for inspection of all joints for leakage or signs of failure... specification The test medium temperature shall be 5℃ to avoid the possibility of brittle fracture METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 13 of 17 5.8 Test Pressure  The hydrostatic test pressure which is calculated and approved by engineering shall be indicated in the line list /test package  The pressure difference between high and low positions of the test section... and shall be pressurized After the pressure is built up to the required test pressure and preliminary inspection by HDEC is completed, Company Inspectors shall be notified for final inspection of the test section METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 15 of 17  Pressure relief valves shall be set up adequately to avoid increase in pressure  PRV discharge shall be... flow for a few minutes to ensure that the air is completely eliminated within the line  At the end of 1 hour holding time, verify the values of the pressure and transcribe these final values in the minutes of testing  In any case pipe insulation shall be carried out before hydrostatic test provided that all welded joints shall be exposed for inspection during the test METHOD STATEMENT FOR PRESSURE TEST. .. connection for hydrotest shall be replaced with new ones New bolts and nuts shall be provided as per bolting and torquing procedure by qualified fitters if test bolting is not of correct grade for the service METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page 16 of 17 5.14 Acceptance criteria  The values of pressure shall be kept during the period of hydro test after the pressure. .. pressure Ensure the pressure at the lower point does not exceed the bearing capability of pipe, meter and valve  When the pressure reaches the testing pressure (1 .5 times operating pressure) , stop the pump Hold for 10minutes without any pressure drop Then release the pressure to operating pressure and hold for 20-30 minutes Inspect the pipeline, if no leakages is noticed, the test is considered successful... phone 8 Organization for Pressure Test Prior to test, organization chart shall be checked and verified by HDEC field Engineer The chart shall be attached to test plan for verification and be checked by any HDEC field Engineer before filling the water for test Organization chart shall be revised for each package if relevant peoples are changed 9 Attachment  Attachment #1: Check list before welding  Attachment ...Doc No.: MD1-0-T-054-05-00195 METHOD STATEMENT FOR PRESSURE TEST Rev A Page of 17 Mong Duong1 Thermal Power Plant Project METHOD STATEMENT FOR PRESSURE TEST REV DATE DESCIPRITON... Responsibility Work Sequence Inspection & Testing Safety and First AID Organization For Pressure Test Attachment Page of 17 METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195 Rev A Page of... responsible for the issuance of isometric drawings which is approved for constructions and other relevant documents necessary for installing work METHOD STATEMENT FOR PRESSURE TEST Doc No.: MD1-0-T-054-05-00195

Ngày đăng: 15/01/2016, 20:46

TỪ KHÓA LIÊN QUAN

w