Thuyết minh biện pháp thi công cọc ván thép trụ cầu đường sắt đô thị thành phố Hà Nội (Tiếng Anh)
Trang 1DAELIM INDUSTRIAL CO., LTD
METHOD STATEMENT FOR SHORED EXCAVATION
Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City
PROJECT IMPLEMENTATION CONSULTANT: SYSTRA S.AJanuary, 2015
Project Reference: DLM-IMP-PPG-WVO-J07-00001-E-1A
Trang 2
PROJECT: HANOI PILOT LIGHT METRO LINE Section Nhon - Hanoi Railway Station
PACKAGE: LINE-ELEVATED SECTIONPACKAGE NUMBER: HPLMLP/CP-01
METHOD STATEMENT FOR SHORED EXCAVATION
Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City
Hanoi, 03 January, 2015
HANOI METROPOLITANRAILWAY MANAGEMENT
BOARD (MRB)
CONSULTANT (SYSTRA S.A.)
Trang 3Contractor Approval / Revision Record Sheet
Contractor specific comments:
Trang 44.1 PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR 22
4.2 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE 23
4.3 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE 24
5 MATERIALS, EQUIPMENT AND MANPOWER 25
5.1 MATERIALS 25
5.2 EQUIPMENT 25
5.3 MANPOWER 26
6 CONSTRUCTION METHOD 27
6.1 CONSTRUCTION FLOW CHART 27
6.2 DETAIL OF CONSTRUCTION METHOD 28
6.2.1 MOBILIZATION AND PREPARATION WORKS 28
6.2.2 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES) 28
6.2.3 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES) 29
6.2.3.1 Excavation Stage 1: About install struts and wales 29
6.2.3.2 Excavation Stage 2: Excavation by machine until design level and hauling out of excavated material 306.2.3.3 Excavation Stage 3: Trimming and leveling work 30
6.2.3.4 Construction for temporary drainage system (Dewatering) 30
6.2.3.5 Cleaning up site 30
7 QUALITY CONTROL 31
8 HEALTH, SAFETY AND ENVIRONMENT CONTROL 31
8.1 HEALTH AND SAFETY CONTROL 31
8.2 ENVIRONMENT CONTROL 32
8.3 HAZARD ANALYSIS 32
9 TRAFFIC CONTROL 33
10 APPENDIX 33
10.1 APPENDIX 1: METHOD DRAWING 34
10.1.1 SHORED EXCAVATION METHOD DRAWING FOR TYPICAL BRIDGE 34
10.1.2 SHORED EXCAVATION METHOD DRAWING FOR SPECIAL BRIDGE 34
10.2 APPENDIX 2: INSPECTION AND TESTING PLAN 35
10.3 APPENDIX 3: TYPICAL SCHEDULE FOR SHORED EXCAVATION OF 01 PILE CAP 36
Trang 5AbbreviationsMRBHanoi Metropolitan Railway Management BoardPICProject Implementation Consultant (SYSTRA S.A.)DLM Daelim Industrial Co., Ltd
Project References
1 DLM-IMP-PPG-WVO-J07-00001-E-1A Method statement for shored excavation
Trang 61 INTRODUCTION OF PROJECT1.1INTRODUCTION
Hanoi Pilot Light Metro Line, section Nhon - Hanoi Railway Station is a major project for Hanoi City.According to the Hanoi Transportation Master Plan till 2020, total length of HPLML (Line 3) shall reach21,5km from Nhon to Hoang Mai.The first phase of this line, and part of this Contract is from Nhon toHanoi Railway Station, with about 8.5 km elevated section and 4.0 km underground section This lineincludes 12 stations (with 8 elevated and 4 underground stations) The Depot is located at Nhon with areaof 150,550m2.
The CP01 Contract’s work scope is Viaduct Line at Elevated Section, including the construction ofviaduct structures which link along the National Road No32, Ho Tung Mau, Xuan Thuy, Cau Giay andinterfaces with underground section at the beginning of Kim Ma Street The contract shall be completedand within 30 months from the date of the Commencement Date.
Both metro and structure alignment follow the current and/or planned median road Viaduct structures aredivided into standard viaducts which cover most of the elevated section and special viaducts where long orspecial spans are required to pass over major constraints (2nd Ring Road, 3rd Ring Road, Nhue River).Other non-typical structure consists in Cross Over (metro line requires switches), ramps to depot andunderground sections and Y-bridge (branches off to depot) The overview of the project is shown in photobelow:
Overview of project
2 SCOPE OF WORK2.1GENERAL
Structure excavation work of Project will be carried out within the narrow area and with the great depth ofexcavated hole Therefore, Shored excavation method will be applied to ensure stability of excavationhole for structure construction.
Shored Excavation shall be undertaken in accordance with clause “3.4 - Shored excavation, Part II,Chapter II-2” of Technical Requirement This method is generally applied to Shored excavation to thedesign bottom elevation for all pile caps using shoring system.
Trang 7This method also includes disposal of unsuitable excavated material, dewatering works and related worksto be free from the accumulation of ground water and artificial runoff water inside excavated area ShoredExcavation shall be done in accordance with the perimeters and slope as indicated on the approvedworking drawing
The Contractor shall set up and submit method of shored excavation The Contractor can adjust methodfor shored excavation in accordance with the actual condition on the site or at the direction of ConsultantEngineer All adjustments will be reviewed and approved by the Consultant Engineer, Employer.
After obtaining consent from the Consultant Engineer, Employer, the Contractor will carry out shoredexcavation.
Shored excavation part including:
Shored excavation for pilecap type I (Standard pile cap). Shored excavation for pilecap type II (Cantilever pile cap). Shored excavation for pilecap type III (Special pile cap).
The Contractor will use method of excavation works of foundation pit by excavator and manpower.
Reference document:
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Section 3 Earthwork.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.4.Shored excavation
-Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.3.Common excavation.- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.5 Preparation and
inspection of foundations.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.8 Grade preparation.- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.9 Water Control.
- Construction Management Plan, document No : DLM – IMP – PPG – ZCO – J00 – 00001 – E
- Quality Plan, document No : DLM – IMP – PPG – ZPQ – J00 – 00001 – E
- Delivery Management Plan, document No: DLM – IMP – PPG – ZPO – J00 – 00001 – E
- Traffic Management Plan, document No: DLM – IMP – PPG – ZPO – J00 – 00004 – E
- H&S Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00003 – E
- Environment Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00002 – E
- Security Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00001 – E
Trang 83.CONSTRUCTION PROCEDURE3.1QUANTITY OF WORK
The estimated quantity is as followings table Below quantity is only reference Final quantity shall becalculated in accordance with approved working drawing Topographic survey of original ground whichhad been approved shall be applied to calculate the quantity for structure excavation.
Trang 9No.Type ofbridgePier
Trang 10Excavation Volume(m3)Length
Width (m)
Trang 11Excavation Volume(m3)Length
Width (m)
Trang 14Excavation Volume(m3)Length
Trang 15Excavation Volume(m3)Length
Width (m)
Trang 173.2REFERENCE TO BORE HOLE
Based on alignment geological borehole, we have reference table of geological boreholes in accordance
Trang 18with pier position Reference table is established for piers of Typical Bridge and Special Bridge.
With dimension, depth and geology of borehole at position of piers, Contractor calculated and proposedall piers in alignment have to use sheet piles cofferdam during excavation process.
Also, at position of pier caps with dimension (10.9x7.4x3.5m và 5.6x4.8x3.0m), Contractor use bracingsystem inside steel piles cofferdam.
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap onTypical Bridge is shown in the attached drawing in section 10.1.1
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap onSpecial Bridge is shown in drawing DLM-IMP-GPV-WVO-JOO-10003-B and DLM-IMP-GNS-WVO-JOO-10018-B (attached in section 10.1.2).
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam withoutwales & struts inside, will be submitted separately
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam and wales &struts inside, will be submitted separately
Trang 19clay,very Stiff /Sét dẻo thấpdẻo cứng
Organic silt, firm/Bụi lẫn hữu cơ,
dẻo mềmLean clay,very Stiff /Sét dẻo thấpdẻo cứngLean
clay,firm/Sét dẻo thấpdẻo mềm
Trụ tham chiếu/Reference to
Typical bridge/Cầu điển
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngOrganic
silt: soft/Sét dẻo thấpdẻo chảy,
Lean clay,firm/Sét
dẻo thấpdẻo mềm
Organic silt, firm/Bụi lẫn hữu cơ,
dẻo mềmLayer 3/Lớp 3
Lean clay with some organic,firm
/Sét dẻo thấp, đôi chỗ lẫn ít hữu cơdẻo mềm
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngLean
clay,very Stiff /Sét dẻo
thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo
thấpdẻo cứngLayer 2/Lớp 2
Lean clay,very Stiff /Sét dẻo
thấpdẻo cứng
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấpMade
ground/Đất lấpMade
ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấpBorehole/Lỗ khoan
ground/Đất lấp
Made ground/Đất lấp
Trang 20Made ground/Đất lấpMade
ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Layer 2/Lớp 2
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấpMade
ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean Clay, Stiff-very
stiff/Sét dẻo thấpnửa cứng
Layer 3/Lớp 3
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo
thấpdẻo cứng
Organic silt: soft-firm/Sét dẻo thấpdẻo chảy,
mềmLean
clay,firm/Sét dẻo thấpdẻo mềm
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Trụ tham chiếu/Reference to
Typical bridge/Cầu điển
Organic silt, firm/Bụi
lẫn hữu cơ,dẻo mềm
Organic silt, firm/Bụi lẫn hữu cơ,dẻo mềm
Organic silt, Stiff/cát lẫn
bụi, xốp- rất xốp
Organic silt, firm/Bụi lẫn hữu cơ,dẻo mềmOrganic
silt: firm/Sét dẻo thấpdẻo chảy,
Cobble,Gravel with sand, very dense/Cuội sỏi, lẫn cát, rất chặt
Organic silt ,firm/Sét dẻo thấpdẻo mềm
Silt sand,medium dense/Cát lẫn bụi,chặt vừa
Organic silt firm/Sét dẻo thấpdẻo mềmOrganic silt
,firm/Sét dẻo thấpdẻo mềm
Silt sand,medium dense/Cát lẫn bụi,chặt vừa
Trang 21chiếu/Reference to
Special bridge/Cầu
đặc biệt
Organic silt, firm/Bụi lẫn hữu cơ,
dẻo mềmLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Silt sand, medium dense/Cát lẫn bụi,chặt
vừaSilt sand,
medium dense/Cát
lẫn bụi,chặt
vừaOrganic
silt, firm/Bụi lẫn hữu cơ, dẻo mềm
Organic silt, firm/Bụi lẫn hữu cơ, dẻo mềmLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay, firm
/Sét dẻo thấpdẻo mềm
Organic silt, firm/Bụi
lẫn hữu cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Organic silt: soft-firm/Sét dẻo chảy,dẻo mềm
Organic silt, firm/Bụi lẫn hữu cơ, dẻo mềmLean clay,very Stiff /Sét dẻo thấpdẻo cứng
Made ground/Đất lấp
Made ground/Đất lấp
Layer 3/Lớp 3
Organic silt: soft/Sét dẻo thấpdẻo chảy
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấp
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay, firm
/Sét dẻo thấpdẻo mềmLean
clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứng
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngLayer 2/Lớp 2
Lean clay,very Stiff /Sét dẻo thấpdẻo cứngBorehole/Lỗ khoan
Layer 1/Lớp 1Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Lean Clay, Stiff-very stiff/Sét dẻo thấpnửa cứng
Organic silt firm/Sét dẻo thấpdẻo mềmMade
ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấp
Made ground/Đất lấpMade
ground/Đất lấp
Made ground/Đất lấp
Trang 234 PERSONNEL ORGANIZATION
4.1PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR
HEAD OFFICE↑SITE OFFICE↓
SITE ENGINEER
QUANTITY SURVEYORCONTRACT M ANAGER(CHOI,JAE-HOON)
PROGRAM M E TEAMCONTRACT TEAM
PLANNING DEPARTM ENTPLANNING M ANAGERDEPUTY PROJECT M ANAGER
COST CONTROL M ANAGER(LEE,CHUNG-HEE)
ADM M ANAGER(KWON,YONG-SHIK)
(DOAN HUU KHOAT)
CLERK(NG T THANH)
CHIEF CIVIL ENGINEER(SƠN TRẦN NGỌC)
SPECIAL BRIDGECHIEF CIVIL
ENGINEER(T T HUY)ACCOUNTING TEAM
LEAD OF GEOTECHNICAL
(ĐẠI TRỊNH XUÂN)(TÚ NGUYỄN M INH)
(NG X HAI)(NG V PHONG)
(HOÀ PHẠM THÁI)(KHIÊM TRẦN ĐĂNG)
CHIEF SURVEYOR(T TRUNG THANH)DESIGN TEAM
(Control Environment)
SAFETY SUPPORTERSH/S ENGINEER
(TOÀN NGUYỄN KHÁNH)
H/S ENGINEER(NGUYỄN VĂN TỚI)
ENVIRONM ENT ENGINEER
SECURITY OFFICESECURITY GUARDS
ENVIRONM ENT M ONITORING TEAMSAFETY OFFICER &
SAFETY SUPPORTERS
(NG K THUAN)DESIGN M ANAGER
PROJECT DIRECTOR
(115 Emergency)
SECURITY LEADER
LABOR CONTROLLERWORK PROGRAM M E
M ANAGER (NG T VU)(Control Security , health and
ADM INISTRATION M ANAGER(HEO,SEON-HAENG)
SUPERVISORCHIEF ACCOUNTANT
(T H ANH)
M ATERIAL PURCHASER
CHIEF OF LABORATORY
QC CHIEF ENGINEER(T M KHANH)
LABORATORY STAFF(TÚ TRẦN ANH)
CONSTRUCTION M ANAGER(OH,SEUNG-JONG)ENV/SUPPORTERS
QA / QC DEPARTM ENTQUALITY ASSURANCE M ANAGER
(G B NGOC)
QUALITY CONTROL TEAMHEALTH & SAFETY M ANAGER
(V V THUY)
(NG NG TRÌNH)
CHIEF STR ENGINEER(D TUNG)(HOANG TIEN TRUNG)
ADM INISTRATION DEPARTM ENT
(PHƯƠNG NGÔ GIA)
(T T TINH)
Trang 244.2PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE
Construction Manager/Chỉ Huy TrưởngMr Lê Thảo TâmPhone: 0987.520.820
Designer/Thiết kếMr Lê Minh TràPhone: 0912-337-176
Mr Bùi Trần HàPhone: 0983-718-345
QA, QC/ Quản lý chất lượngMr Ngô Thế QuỳnhPhone: 0916-042-060
Construction Team/Bộ phận thi côngMr Trần Hữu ThắngPhone: 0983-899-315
Mechanical Team/Bộ phận máy thi công
Mr Cao Tiến SơnPhone: 0985-320-691
Surveyor Team/Đội Trắc đạcMr Khuất Hữu Thuận
Design Team/Tổ Thiết kế
QA, QC Team/Tổ quản lý chất lượng
Mr Cấn Mạnh HùngMr Lê Văn LongPhone: 0947-211-268
ExcavationTeam/Tổ thi công đào
Drainage Team/Tổ thi công thoát
nước tạm
Clinic Team/Tổ Y tế
Safety Team/Tổ An toànMr Phạm Ngọc TiếnPhone: 01686-539-171
Traffic AssuranceTeam/
Tổ Đảm bảo giao thôngPlanning,QS Team/
Bộ phận Kế hoạch, khối lượng Mr Lê Thăng QuânPhone: 01683-636-867
Sheet pile Team/Tổ cọc ván thép
GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁNMr.Lê Lệnh Bắc
Phone: 0913253582
Trang 254.3PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE
GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁNMr.Nguyễn Tuấn Anh
Phone: 0989059379Email: tuananhsd73@gmail.com
PHÓ GIÁM ĐỐC BAN ĐIỀU HÀNHPhụ trách quản lý thi công, ATLĐ, đảm bảo giao
thôngMr: Trần Ngọc QuýPhone: 0979267723Email: ngocquyc14@gmail.comPHÓ GIÁM ĐỐC BAN ĐIỀU HÀNH
Phụ trách kế hoạch, thanh toán, kỹ thuậtMr: Đào Đức Huynh
Phone: 0913060752
BỘ PHẬN KẾ HOẠCH, KHỐI LƯỢNGMr Bùi Quang Vinh
Phone: 0949393492
BỘ PHẬN MÁY THI CÔNG
Mr Đỗ Đường TúPhone: 0974112422THIẾT KẾ
Mr Nguyễn Thắng AnPhone:0989643926
QUẢN LÝ CHẤT LƯỢNGMr Phạm Xuân Nghĩa
Phone: 0912774678 BỘ PHẬN THI CÔNGMr Nguyễn Trung Kiên
Phone: 0979898568
ĐỘI TRẮC ĐẠC Mr Trương Quốc Ninh
Phone: 0904545744
NHÓM AN TOÀN SỨC KHỎE , MÔI TRƯỜNG
Mr Trương Công ThịnhPhone: 0979032579
Mr Lê Văn TuấnPhone:0972405191
Mr Nguyễn Sỹ ThườngPhone:016689912487
Mr Nguyễn An QuangPhone:01689615196Mr Nguyễn Văn Đô
Mr Trần Văn CườngPhone:0972405191Mr Đàm Quang Chiến
Mr Nguyễn Văn HùngPhone:0936672916