Tính toán thép sàn Bubbledeck .... Thép lớp dưới theo phương X .... Thép lớp trên theo phương X .... Thép lớp dưới theo phương Y .... Thép lớp trên theo phương Y .... Xác định số lượng c
THIẾT KẾ SÀN BUBBLE DECK
THIẾT KẾ SÀN ỨNG LỰC TRƯỚC
Nội lực tính toán bằng phần mền Adapt Builder
Hình 1.4 Vị trí các Support line
Hình 1.5 Moment diagram Support line 1
Hình 1.6 Stress Diagrams Support line 1
Hình 1.7 Design strip reinforcement Support line 1
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.8 Moment Diagrams Support line 2
Hình 1.9 Stress Diagrams Support line 2
Hình 1.10 Design strip reinforcement Support line 2
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.11 Moment Diagrams Support line 3
Hình 1.12 Stress Diagrams Support line 3
Hình 1.13 Design strip reinforcement Support line 3
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14 Span 15
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14 Span 15
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 12 Span 13 Span 14 Span 15
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 2 Span 3 Span 4 Span 5 Span 6 Span 7 Span 8 Span 9 Span 10 Span 11 Span 13 Span 14 Span 15
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.14 Moment Diagrams Support line 4
Hình 1.15 Stress Diagrams Support line 4
Hình 1.16 Design strip reinforcement Support line 4
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.17 Moment Diagrams Support line 5
Hình 1.18 Stress Diagrams Support line 5
Hình 1.19 Design strip reinforcement Support line 5
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Stress Diagrams Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.20 Moment Diagrams Support line 6
Hình 1.21 Stress Diagrams Support line 6
Hình 1.22 Design strip reinforcement Support line 6
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.23 Moment Diagrams Support line 7
Hình 1.24 Stress Diagrams Support line 7
Hình 1.25 Design strip reinforcement Support line 7
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.26 Moment Diagrams Support line 8
Hình 1.27 Stress Diagrams Support line 8
Hình 1.28 Design strip reinforcement Support line 8
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.29 Moment Diagrams Support line 9
Hình 1.30 Stress Diagrams Support line 9
Hình 1.31 Design strip reinforcement Support line 9
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.32 Moment Diagrams Support line 10
Hình 1.33 Stress Diagrams Support line 10
Hình 1.34 Design strip reinforcement Support line 10
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.35 Moment Diagrams Support line 11
Hình 1.36 Stress Diagrams Support line 11
Hình 1.37 Design strip reinforcement Support line 11
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.38 Moment Diagrams Support line 12
Hình 1.39 Stress Diagrams Support line 12
Hình 1.40 Design strip reinforcement Support line 12
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.41 Moment Diagrams Support line 13
Hình 1.42 Stress Diagrams Support line 13
Hình 1.43 Design strip reinforcement Support line 13
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5 Span 6 Span 7
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.44 Moment Diagrams Support line 14
Hình 1.45 Stress Diagrams Support line 14
Hình 1.46 Design strip reinforcement Support line 14
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.47 Moment Diagrams Support line 15
Hình 1.48 Stress Diagrams Support line 15
Hình 1.49 Design strip reinforcement Support line 15
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.50 Moment Diagrams Support line 16
Hình 1.51 Stress Diagrams Support line 16
Hình 1.52 Design strip reinforcement Support line 16
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Span 1 Span 2 Span 3 Span 4 Span 5
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.53 Moment Diagrams Support line 17
Hình 1.54 Stress Diagrams Support line 17
Hình 1.55 Design strip reinforcement Support line 17
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Envelope
Rebar Required Top Rebar Required Bottom
Rebar Provided Top Rebar Provided Bottom
Hình 1.56 Moment Diagrams Support line 18
Hình 1.57 Stress Diagrams Support line 18
Project: CENTRAL COAST / Load Case: Strength 1.35 x Selfweight + 1.35 x Dead load + 1.50 x Live load + 1.00 x Hyperstatic
Moment Drawn on Tension Side
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
Project: CENTRAL COAST / Load Case: Frequent 1.00 x Selfweight + 1.00 x Dead load + 0.50 x Live load + 1.00 x Prestressing
THIẾT KẾ CỘT
Tải trọng gió tác dụng vào công trình
1.1.1 Tải trọng gió tĩnh theo phương X
Bảng 1.5 Giá trị tải trọng gió tĩnh theo phương X
STT TẦNG H j (m) Z j (m) k j L Yj (m) W Xj (kN)
1.1.2 Tải trọng gió tĩnh theo phương Y
Bảng 1.6 Giá trị tải trọng gió tĩnh theo phương Y
STT TẦNG H (m) Z j (m) k j L Xj (m) W Yj (kN)
1.2.1 Chuyển vị ứng với các dạng dao động
❖ Chuyển vị ứng với các dạng dao động theo phương X
Bảng 1.7 Chuyển vị ứng với giao động riêng theo phương X
Hình 1.58 Chuyển vị ứng với các dạng giao động theo phương X
❖ Chuyển vị ứng với giao động theo phương Y
Bảng 1.8 Chuyển vị ứng với các dạng giao động theo phương Y
Hình 1.59 Chuyển vị ứng với các dạng giao động theo phương Y
1.2.2 Tải trọng gió động theo phương X
❖ Tải trọng gió động theo phương X ứng với dạng dao động thứ 1 (Modal 1)
Bảng 1.9 Tải trọng gió động theo phương X ứng với dạng dao động thứ 1
(kN) y ji y ji W Fj y ji 2 M j
❖ Tải trọng gió động theo phương X ứng với dạng dao động thứ 2 (Modal 4)
Bảng 1.10 Tải trọng gió động theo phương X ứng với dạng dao động thứ 2
(kN) y ji y ji W Fj y ji 2 M j
1.2.3 Tải trọng gió động theo phương Y
❖ Tải trọng gió động theo phương Y ứng với dạng dao động thứ 1 (Modal 2)
Bảng 1.11 Tải trọng gió động theo phương Y ứng với dạng dao động thứ 1
(kN) y ji y ji W Fj y ji 2 M j
❖ Tải trọng gió động theo phương Y ứng với dạng dao động thứ 2 (Modal 5)
Bảng 1.12 Tải trọng gió động theo phương Y ứng với dạng dao động thứ 2
(kN) y ji y ji W Fj y ji 2 M j
Giá trị phổ phản ứng đất nền
Bảng 1.13 Giá trị phổ phản ứng đất nền
Chuyển vị công trình
Bảng 1.14 Chuyển vị đỉnh công trình do tải trọng gió
KIỂM TRA CHUYỂN VỊ ĐỈNH CÔNG TRÌNH
DỰ ÁN: TỔ HỢP KHÁCH SẠN VÀ CĂN HỘ CENTRAL COAST
1 Chuyển vị đỉnh công trình phải thỏa mãn Bảng M.4 TCVN 5574:2018
2 Chuyển vị đỉnh công trình không được vượt quá giá trị H/500, với H là chiều cao công trình tính từ mặt móng đến đỉnh công trình
KẾT QUẢ KIỂM TRA CHUYỂN VỊ ĐỈNH
DO TÁC ĐỘNG CỦA: GIÓ
Tầng kiểm tra Tầng Mái
Chuyển vị đỉnh lớn nhất theo phương X (m) 0.108 Chuyển vị đỉnh lớn nhất theo phương Y (m) 0.123 Giới hạn chuyển vị cho phép (H/500) (m) 0.276 Đánh giá ĐẠT
Type Ux Uy Uz Rx Ry Rz m m m rad rad rad
3.2 Chuyển vị đỉnh công trình do động đất
Bảng 1.15 Chuyển vị đỉnh công trình do động đất
KIỂM TRA CHUYỂN VỊ ĐỈNH CÔNG TRÌNH
DỰ ÁN: TỔ HỢP KHÁCH SẠN VÀ CĂN HỘ CENTRAL COAST
1 Chuyển vị đỉnh công trình phải thỏa mãn Bảng M.4 TCVN 5574:2018
2 Chuyển vị đỉnh công trình không được vượt quá giá trị H/500, với H là chiều cao công trình tính từ mặt móng đến đỉnh công trình
KẾT QUẢ KIỂM TRA CHUYỂN VỊ ĐỈNH DO
TÁC ĐỘNG CỦA: ĐỘNG ĐẤT
Tầng kiểm tra Tầng Mái
Chuyển vị đỉnh lớn nhất theo phương X (m) 0.157
Chuyển vị đỉnh lớn nhất theo phương Y (m) 0.076
Giới hạn chuyển vị cho phép (H/500) (m) 0.276 Đánh giá ĐẠT
Type Ux Uy Uz Rx Ry Rz m m m rad rad rad
3.3 Chuyển vị lệch tầng công trình do gió
Bảng 1.16 Chuyển vị lệch tầng do gió
KIỂM TRA CHUYỂN VỊ LỆCH TẦNG CÔNG TRÌNH
DỰ ÁN: TỔ HỢP KHÁCH SẠN VÀ CĂN HỘ CENTRAL COAST
1 Chuyển vị lệch tầng do gió phải thỏa mãn Bảng M.4 TCVN 5574:2018
2 Chuyển vị lệch tầng do động đất phải thỏa mãn Mục 4.4.3.2 TCVN 9386:2012
KIỂM TRA CHUYỂN VỊ LỆCH TẦNG DO TÁC ĐỘNG
Giới hạn chuyển vị cho phép hs/500
Chuyển vị giới hạn được phép tăng 30%
Giá trị giới hạn chuyển vị cho phép (m) 0.00806
Kết quả kiểm tra ĐẠT
Step Type Direction Drift Label X Y Z m m m
The EnvGIOB values for various models were analyzed, with TM EnvGIOB Min Y showing the highest value at 0.00100, while BNM EnvGIOB Max X had the lowest value at 0.00084 BNM EnvGIOB Max Y and BNM EnvGIOB Min X both had values of 0.00088 and 0.00070, respectively, with corresponding counts of 130 T38 EnvGIOB Max X and T38 EnvGIOB Max Y had values of 0.00087 and 0.00091, respectively, with counts of 610 and 568 T37 EnvGIOB Max X, T37 EnvGIOB Max Y, and T37 EnvGIOB Min X all had values ranging from 0.00087 to 0.00074, with T36 EnvGIOB Max X having a value of 0.00089.
The EnvGIOB data reveals a range of values across different temperature levels, with maximum and minimum values observed At T36, the maximum EnvGIOB value is 0.00089, while the minimum is 0.00075 The maximum EnvGIOB value decreases to 0.00087 at T34, and further decreases to 0.00086 at T33 The minimum EnvGIOB value, on the other hand, increases to 0.00317 at T35 and 0.00321 at T34 At T33, the minimum EnvGIOB value is 0.00325, and it continues to increase to 0.00340 at T29 and 0.00343 at T28 The data also shows a consistent pattern of decreasing maximum EnvGIOB values and increasing minimum EnvGIOB values as the temperature level decreases.
The EnvGIOB data shows a gradual decrease in values across different categories, with T27 EnvGIOB Min Y having the highest value at 0.00347, and T17 EnvGIOB Max X having the lowest at 0.00109 The Max X and Max Y values range from 0.00104 to 0.00109 and 0.00132 to 0.00166, respectively, while the Min X and Min Y values range from 0.00093 to 0.00104 and 0.00347 to 0.00352, respectively The data also shows a consistent sample size of 449 for most categories, with a few exceptions having a sample size of 476 The EnvGIOB values also show a consistent decrease in the percentage range, from 86.3 to 54.8.
The EnvGIOB data indicates a gradual decrease in values as the tier level decreases, with the maximum and minimum values for both X and Y coordinates showing a consistent trend The maximum X values range from 0.00109 to 0.00099, while the maximum Y values range from 0.00172 to 0.00150 Conversely, the minimum X values range from 0.00105 to 0.00097, and the minimum Y values range from 0.00339 to 0.00268 The corresponding tier levels, from T17 to T8, show a decrease in values, with the exception of the T17 EnvGIOB Min X and T8 EnvGIOB Min X values, which remain relatively stable at 0.00104 and 0.00097, respectively.
The EnvGIOB data indicates a range of values across different tiers, from T8 to B1 The maximum and minimum values for both X and Y coordinates vary significantly, with the highest maximum value being 0.00252 for T8 EnvGIOB Min Y and the lowest minimum value being 0.00004 for B1 EnvGIOB Max X The corresponding values for the number of observations, percentage change, and EnvGIOB values also show considerable variation, with the highest number of observations being 627 for T4 EnvGIOB Max X and the lowest being 113 for T5 EnvGIOB Max Y The percentage change values range from -6.3 to 85.5, and the EnvGIOB values range from 0.0 to 26.9 Overall, the data suggests a complex and dynamic relationship between the different tiers and variables.
B1 EnvGIOB Max Y 0.00010 168 0.0 -6.3 -3.3 B1 EnvGIOB Min X 0.00005 194 43.3 44.3 -3.3 B1 EnvGIOB Min Y 0.00017 168 0.0 -6.3 -3.3 B2 EnvGIOB Max X 0.00002 180 82.7 -6.3 -6.6 B2 EnvGIOB Max Y 0.00005 168 0.0 -6.3 -6.6 B2 EnvGIOB Min X 0.00002 194 43.3 44.3 -6.6 B2 EnvGIOB Min Y 0.00008 168 0.0 -6.3 -6.6
3.4 Chuyển vị lệch tầng do động đất
Bảng 1.17 Chuyển vị lệch tầng do động đất
KIỂM TRA CHUYỂN VỊ LỆCH TẦNG CÔNG TRÌNH
DỰ ÁN: TỔ HỢP KHÁCH SẠN VÀ CĂN HỘ CENTRAL COAST
1 Chuyển vị lệch tầng do gió phải thỏa mãn Bảng M.4 TCVN 5574:2018
2 Chuyển vị lệch tầng do động đất phải thỏa mãn Mục 4.4.3.2 TCVN 9386:2012
KIỂM TRA CHUYỂN VỊ LỆCH TẦNG DO TÁC ĐỘNG CỦA: ĐỘNG ĐẤT
Giới hạn chuyển vị cho phép dr.v ≤ α.h Với v = 0,4
Chuyển vị giới hạn được phép tăng 0%
Giá trị giới hạn chuyển vị cho phép (m) 0.03875
Kết quả kiểm tra ĐẠT
Step Type Direction Drift Label X Y Z m m m
TM EnvDDB Min Y 0.00062 22 64.9 10.0 128.1 BNM EnvDDB Max X 0.00109 120 53.6 0.0 125.0 BNM EnvDDB Max Y 0.00075 124 82.7 0.0 125.0 BNM EnvDDB Min X 0.00097 130 82.7 39.5 125.0 BNM EnvDDB Min Y 0.00207 89 14.0 12.0 125.0 T38 EnvDDB Max X 0.00113 610 85.5 -1.5 121.1 T38 EnvDDB Max Y 0.00081 568 85.5 41.0 121.1
The EnvDDB values for T38 to T29 were analyzed, with minimum and maximum values recorded for both X and Y axes The minimum X values ranged from 0.00102 to 0.00141, while the maximum X values ranged from 0.00114 to 0.00138 The minimum Y values ranged from 0.00254 to 0.00288, while the maximum Y values remained relatively constant at 0.00082 The corresponding temperatures for these values were also recorded, with T38 having the highest temperature of 121.1 and T29 having the lowest temperature of 92.5.
The EnvDDB data showcases a range of values across different temperatures, with maximum and minimum values recorded for both X and Y axes At T28, the maximum X value is 0.00145, while the maximum Y value is 0.00081, and the minimum X and Y values are 0.00134 and 0.00291, respectively As the temperature decreases, the values fluctuate, with T27 recording maximum X and Y values of 0.00148 and 0.00080, and minimum values of 0.00137 and 0.00292 This trend continues down to T19, where the maximum X and Y values are 0.00161 and 0.00085, respectively Notably, the values for X and Y axes remain relatively consistent across the temperature range, with the maximum and minimum values varying by only a small margin.
The EnvDDB data reveals a consistent pattern across various temperature ranges, with the maximum X values remaining relatively stable between 0.00154 and 0.00162, while the minimum X values fluctuate between 0.00148 and 0.00162 The maximum Y values exhibit a similar trend, ranging from 0.00088 to 0.00095, whereas the minimum Y values vary between 0.00225 and 0.00285 The data points also show a correlation between temperature and EnvDDB values, with the temperature decreasing from 61.0 to 33.1 degrees.
The data presented above outlines the maximum and minimum values of EnvDDB across various tiers, from T9 to TL1 The maximum and minimum values for X and Y coordinates are provided, along with corresponding values for other parameters Notably, the maximum X values range from 0.00150 in T9 to 0.00050 in TL1, while the maximum Y values range from 0.00090 in T9 to 0.00020 in TL1 Conversely, the minimum X values range from 0.00144 in T9 to 0.00085 in TL2, and the minimum Y values range from 0.00213 in T9 to 0.00104 in TL2.
The EnvDDB data reveals various minimum and maximum values across different parameters Notably, TL1 EnvDDB Min X and Y values are 0.00050 and 0.00066, respectively In contrast, T1 EnvDDB Max X and Y values are 0.00011 and 0.00006, respectively The T1 EnvDDB Min X and Y values are 0.00012 and 0.00023, respectively Furthermore, B1 EnvDDB Max X and Y values are 0.00005 and 0.00004, respectively, while B1 EnvDDB Min X and Y values are 0.00006 and 0.00013, respectively Additionally, B2 EnvDDB Max X and Y values are 0.00003 and 0.00003, respectively, and B2 EnvDDB Min X and Y values are 0.00004 and 0.00005, respectively.
4 Kiểm tra tỉ số nén 4.1 Kiểm tra tỉ số nén cột C1 trục 1 (cột C1 trong mô hình etabs)
Bảng 1.18 Tỉ số nén cột C1 trục 1
KIỂM TRA TỈ SỐ NÉN CỘT
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The EnvDDBMax and EnvDDBMin values for T37, T36, and T35 were analyzed, with T37 EnvDDBMax ranging from -1751.88 to -1679.37, and T37 EnvDDBMin ranging from -2370.6 to -2298.08 For T36, EnvDDBMax values ranged from -2374.5 to -2307.16, while EnvDDBMin values ranged from -3097.05 to -3029.71 T35 EnvDDBMax values ranged from -2963.51 to -2896.18, with a consistent value of 0.8 for the first column and 1.2 for the second column across all data points, indicating a reliable and stable pattern.
Dưới đây là kết quả chuyển đổi dữ liệu thành một đoạn văn bản có ý nghĩa, tuân thủ các quy tắc SEO:Các kết quả tính toán cho thấy giá trị EnvDDBMin và EnvDDBMax thay đổi theo từng loại T và C1 Cụ thể, giá trị EnvDDBMin tăng dần từ -3806,86 đến -8155,31, trong khi giá trị EnvDDBMax tăng dần từ -3553,01 đến -6479,31 Tất cả các giá trị này đều có hệ số 0,8 và 1,2, và đều được đảm bảo với giá trị 0,650 Các kết quả này cho thấy sự biến thiên của EnvDDBMin và EnvDDBMax theo từng loại T và C1, và có thể được sử dụng để phân tích và so sánh các giá trị này.
Dữ liệu trên cho thấy các giá trị của EnvDDBMax và EnvDDBMin thay đổi theo các mức độ khác nhau, từ T29 đến T22, với các giá trị tương ứng từ -8121,64 đến -10271,8 và từ -7059,86 đến -9930,51 Các giá trị này được đảm bảo với mức độ tin cậy 0,8 và 1,2, cũng như 0,8 và 1,4, với các giá trị khác nhau của EnvDDBMax và EnvDDBMin Dữ liệu này có thể được sử dụng để phân tích và so sánh các giá trị của EnvDDBMax và EnvDDBMin trong các điều kiện khác nhau.
Dựa trên dữ liệu được cung cấp, có thể thấy rằng các giá trị EnvDDBMax và EnvDDBMin thay đổi tùy theo từng loại T (từ T22 đến T16) và có giá trị đảm bảo (Đảm bảo) là 0.650 Các giá trị này dường như được sử dụng để đo lường hoặc tính toán một số thông số kỹ thuật cụ thể, nhưng không rõ mục đích chính xác của chúng Tuy nhiên, có thể thấy rằng các giá trị này có xu hướng tăng hoặc giảm dần khi loại T thay đổi.
Kết quả tính toán cho thấy giá trị EnvDDBMin và EnvDDBMax thay đổi theo từng cấp độ T từ T16 đến T10 Cụ thể, giá trị EnvDDBMin giảm dần từ -17914,1 xuống -22954,7, trong khi giá trị EnvDDBMax giảm dần từ -14410,2 xuống -17266 Giá trị này cho thấy sự thay đổi đáng kể trong từng cấp độ T, đồng thời cũng cho thấy sự ổn định của các giá trị khác như 0,9, 1,4 và 0,650 Điều này cho thấy rằng kết quả tính toán đảm bảo sự chính xác và ổn định.
THIẾT KẾ VÁCH
Thiết kế vách trục 6-B-C
Bảng 1.23 Bảng tính thép vách trục 6-B-C
BẢNG TÍNH THÉP DỌC VÁCH TRỤC 6
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ
N V M A s A sc A g Số lượng φ A s ch Số lượng φ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 119
Kích thước vách thang máy:
Các vách P17, P18, P19, P20, P21, P22, P23, P24 có độ dày 400 mm Đối với các vách biên P1, P2, P3, P4, P5, P8, P17, P24 có chiều dài nhỏ, chiều dài vùng biên B được chọn là 0L và thép được phân bố đều cho toàn bộ vách Trong khi đó, các vách còn lại sẽ được tính toán như bình thường.
Bảng 1.24 Bảng tính thép vách P1
BẢNG TÍNH THÉP DỌC VÁCH P1
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.6 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 121
Bảng 1.25 Bảng tính thép vách P2
BẢNG TÍNH THÉP DỌC VÁCH P2
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.25 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 123
Bảng 1.26 Bảng tính thép vách P3
BẢNG TÍNH THÉP DỌC VÁCH P3
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.25 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.27 Bảng tính thép vách P4
BẢNG TÍNH THÉP DỌC VÁCH P4
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.3 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 125
Bảng 1.28 Bảng tính thép vách P5
BẢNG TÍNH THÉP DỌC VÁCH P5
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.25 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 127
Bảng 1.29 Bảng tính thép vách P6
BẢNG TÍNH THÉP DỌC VÁCH P6
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 3 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 129
Bảng 1.30 Bảng tính thép vách P7
BẢNG TÍNH THÉP DỌC VÁCH P7
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.5 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.31 Bảng tính thép vách P8
BẢNG TÍNH THÉP DỌC VÁCH P8
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 1.25 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 131
Bảng 1.32 Bảng tính thép vách P9
BẢNG TÍNH THÉP DỌC VÁCH P9
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 133
Bảng 1.33 Bảng tính thép vách P10
BẢNG TÍNH THÉP DỌC VÁCH P10
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.25 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 135
Bảng 1.34 Bảng tính thép vách P11
BẢNG TÍNH THÉP DỌC VÁCH P11
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.25 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.35 Bảng tính thép vách P12
BẢNG TÍNH THÉP DỌC VÁCH P12
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.25 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 137
Bảng 1.36 Bảng tính thép vách P13
BẢNG TÍNH THÉP DỌC VÁCH P13
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 139
Bảng 1.37 Bảng tính thép vách P14
BẢNG TÍNH THÉP DỌC VÁCH P14
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 0.7 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 141
Bảng 1.38 Bảng tính thép vách P15
BẢNG TÍNH THÉP DỌC VÁCH P15
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 0.7 (m) B = 0L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.39 Bảng tính thép vách P16
BẢNG TÍNH THÉP DỌC VÁCH P16
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.35 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 143
Bảng 1.40 Bảng tính thép vách P17
BẢNG TÍNH THÉP DỌC VÁCH P17
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 0.925
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 145
Bảng 1.41 Bảng tính thép vách P18
BẢNG TÍNH THÉP DỌC VÁCH P18
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 147
Bảng 1.42 Bảng tính thép vách P19
BẢNG TÍNH THÉP DỌC VÁCH P19
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 2.55 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.43 Bảng tính thép vách P20
BẢNG TÍNH THÉP DỌC VÁCH P20
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 2.55 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 149
Bảng 1.44 Bảng tính thép vách P21
BẢNG TÍNH THÉP DỌC VÁCH P21
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 2.6 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 151
Bảng 1.45 Bảng tính thép vách P22
BẢNG TÍNH THÉP DỌC VÁCH P22
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 4.35 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 153
Bảng 1.46 Bảng tính thép vách P23
BẢNG TÍNH THÉP DỌC VÁCH P23
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 2.95 (m) B = 0.2L
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Bảng 1.47 Bảng tính thép vách P24
BẢNG TÍNH THÉP DỌC VÁCH P24
Bê tông B45: fc' = Rb = 25 (Mpa) Thép CB-500V: fy = Rs = 435 (MPa) b = 0.4 (m) L = 0.975
Nội lực Tính thép Chọn thép biên Chọn thép giữa μ_all
N V M A s A sc A g Số lượng ∅ A s ch Số lượng ∅ A s ch
(kN) (kN) (kNm) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) (mm 2 ) %
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 155
3 Kiểm tra tỉ số nén
3.1 Kiểm tra tỉ số nén vách trục 6
Bảng 1.48 Tỉ số nén vách trục 6
KIỂM TRA TỈ SỐ NÉN VÁCH TRỤC 6
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The EnvDDBMax and EnvDDBMin values for T37 to T30 PierT6 range from -1898 to -14073, with corresponding coefficients of 0.012 to 0.091, and a constant value of 0.650, ensuring a reliable and consistent performance The data indicates a gradual increase in values as the PierT6 type decreases from T37 to T30, with both EnvDDBMax and EnvDDBMin values showing a consistent pattern.
The EnvDDBMax and EnvDDBMin values for PierT6 range from -14419 to -28073, with a corresponding value of 0.6 for the first column, 6.9 for the second column, and 0.093 to 0.181 for the third column, while maintaining a consistent value of 0.650 for the fourth column, ensuring stability and reliability.
The EnvDDB values for PierT6 range from T20 to T11, with varying maximum and minimum values For T20, the EnvDDBMax values are -28419 and -31017, while the EnvDDBMin values are -31017 and -31364 Moving down to T19, the EnvDDBMax values are -29548 and -29894, and the EnvDDBMin values are -32669 and -33015 Similarly, for T18, the EnvDDBMax values are -31018 and -31364, and the EnvDDBMin values are -34316 and -34663 This pattern continues for T17, T16, T15, T14, T13, T12, and T11, with the EnvDDB values increasing as the tier decreases.
The table above displays the EnvDDBMax and EnvDDBMin values for various Tiers, ranging from T10 to T2, with corresponding values of -42553 to -53364 and -47226 to -57950, respectively, while maintaining a constant 0.6 and 6.9 ratio and 0.650 Đảm bảo across all tiers.
The EnvDDBMin and EnvDDBMax values for various pier structures, including T1, T2, TL1, B1, and B2, have been calculated and compared The results show that the EnvDDBMin values range from -49005 to -59812, while the EnvDDBMax values range from -43130 to -54188 The corresponding frequency values are consistently 0.6, with a damping ratio of 0.650 The calculated values indicate that the structures meet the required safety standards, as indicated by the "Đảm bảo" label, which translates to "ensure" or "guarantee" in English.
3.2 kiểm tra tỉ số nén vách thang máy
Bảng 1.49 Tỉ số nén vách P1
KIỂM TRA TỈ SỐ NÉN VÁCH P1
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The results of the environmental database (EnvDDB) tests for various parameters show that all values are within the acceptable limits Specifically, the maximum and minimum values for BNM P1 EnvDDBMax and EnvDDBMin, as well as T38 P1 EnvDDBMax and EnvDDBMin, are well within the allowed range, with values ranging from -731 to 64 and a corresponding risk assessment of 0.001 to 0.042, indicating a safe and ensured level of 0.650.
The provided data showcases a comprehensive analysis of various temperature points (T37 to T28) and their corresponding EnvDDBMax and EnvDDBMin values The data indicates that each temperature point has multiple EnvDDBMax and EnvDDBMin values, ranging from -62 to -1562, with corresponding values of 0.35, 1.60, and 0.650 The data also reveals a consistent increase in EnvDDBMax and EnvDDBMin values as the temperature points decrease The values of 0.35, 1.60, and 0.650 remain constant throughout the data, suggesting a standardized measurement or threshold Overall, the data suggests a thorough examination of the relationship between temperature points and EnvDDBMax and EnvDDBMin values, ensuring a high level of accuracy and reliability.
The EnvDDBMin and EnvDDBMax values were consistently maintained within the acceptable range, with a maximum of 0.35 and a minimum of 1.60 The corresponding values for T28 to T19 were recorded, with EnvDDBMin ranging from -2316 to -6112 and EnvDDBMax ranging from -973 to -2991 The associated values remained steady, with a consistent value of 0.650 for all readings.
The EnvDDBMax and EnvDDBMin values for T18 to T9 P1 range from -1898 to -4751 and -4054 to -6347 respectively, with a consistent 0.35 and 1.60 ratio and a 0.650 Đảm bảo across all values The EnvDDBMax values for T18 to T9 P1 show a gradual decrease from -1898 to -2935, while the EnvDDBMin values decrease from -4054 to -6347 Similarly, the EnvDDBMax and EnvDDBMin values for T17 to T10 P1 follow a similar pattern, with values ranging from -2015 to -2833 and -4205 to -5202 respectively.
The EnvDDBMin and EnvDDBMax values for various T levels, including T9, T8, T7, T6, T5, T4, T3, TL2, T2, and TL1, were analyzed, with a constant 0.35 and 1.60 ratio, and a 0.650 Đảm bảo The results showed a range of EnvDDBMin values from -5354 to -11080, and EnvDDBMax values from -3032 to -2569, indicating a significant variation in the data.
Bảng 1.50 Tỉ số nén vách P2
KIỂM TRA TỈ SỐ NÉN VÁCH P2
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The EnvDDB database has been tested with various parameters, including TM, BNM, T38, T37, T36, T35, T34, and T33, with both maximum and minimum values The results show that the database ensures compliance with the set parameters, with values ranging from 0.001 to 0.650 for EnvDDBMax and 0.000 to 0.650 for EnvDDBMin The data also indicates that the database maintains a consistent value of 0.35 for the first parameter and 1.25 for the second parameter across all tests Additionally, the results show a range of values for the third and fourth parameters, from 0.000 to 0.117 and 0.650 to 0.650, respectively Overall, the EnvDDB database demonstrates a high level of compliance and consistency in its test results.
The EnvDDBMax and EnvDDBMin values for various temperature ranges, specifically T32 to T23, have been recorded with corresponding values for P2, 0.35, 1.25, and 0.650 The EnvDDBMax values range from -39 to -199, while the EnvDDBMin values range from -169 to -338 The P2 values remain constant at 0.35, and the 1.25 and 0.650 values also remain unchanged throughout the temperature ranges These values are crucial in ensuring the reliability and performance of the system.
The EnvDDBMin and EnvDDBMax values for various T levels, ranging from T23 to T14, have been recorded with corresponding values for P2, 0.35, 1.25, and 0.650 Đảm bảo The EnvDDBMin values for T23, T22, T21, T20, T19, T18, T17, T16, T15, and T14 are -363, -387, -410, -432, -454, -476, -497, -518, -538, and -558, respectively Similarly, the EnvDDBMax values for these T levels are -214, -230, -247, -264, -281, -298, -315, -332, -350, and -363 The corresponding P2 values remain constant at 0.35, while the 1.25 and 0.650 Đảm bảo values also remain consistent throughout the recorded data.
The EnvDDBMax and EnvDDBMin values for T13 to T4 P2 show a consistent pattern, with EnvDDBMax ranging from -368 to -808 and EnvDDBMin ranging from -577 to -1211 The corresponding values for the second set of data also follow a consistent pattern, with EnvDDBMax ranging from -3632 to -4875 and EnvDDBMin ranging from -5537 to -7352 The 0.35 and 1.25 values remain constant across all data points, while the 0.650 value is also consistent, with slight variations in the decimal places.
Kiểm tra tỉ số nén
3.1 Kiểm tra tỉ số nén vách trục 6
Bảng 1.48 Tỉ số nén vách trục 6
KIỂM TRA TỈ SỐ NÉN VÁCH TRỤC 6
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The data presented shows a range of values for different pier types and environmental conditions, with a consistent value of 0.6 for the first column, 6.9 for the second column, and 0.650 for the last column The values for EnvDDBMax and EnvDDBMin vary across different pier types, including T37, T36, T35, T34, T33, T32, T31, and T30 The values range from -1898 to -14073 for EnvDDBMax and -2264 to -14073 for EnvDDBMin, indicating a significant variation in the data.
The data provided indicates a range of values for different pier types, including T30, T29, T28, T27, T26, T25, T24, T23, T22, T21, and T20, with corresponding EnvDDBMin and EnvDDBMax values The values range from -14419 to -28073 for EnvDDBMin and -14251 to -28073 for EnvDDBMax, with a consistent 0.6 and 6.9 value across all entries Additionally, the values for 0.093 to 0.181 and 0.092 to 0.181 are also provided, with a constant 0.650 value Overall, the data suggests a correlation between the pier types and the EnvDDB values, with a general increase in EnvDDB values as the pier type decreases.
The table presents a comprehensive list of T20 to T11 PierT6 EnvDDBMax and EnvDDBMin values, showcasing a consistent pattern of 0.6, 6.9, and 0.650 across all entries The EnvDDBMax values range from -28419 to -41137, while the EnvDDBMin values range from -31017 to -45996, indicating a gradual increase in values as the tier level decreases The corresponding values of 0.183 to 0.296 and 0.200 to 0.296 for EnvDDBMax and EnvDDBMin, respectively, demonstrate a steady increase in these values as well.
The EnvDDBMax and EnvDDBMin values for PierT6 vary across different tiers, including T10, T9, T8, T7, T6, T5, T4, T3, TL2, and T2, with corresponding values ranging from -42553 to -57950 and 0.274 to 0.373, respectively, while maintaining a constant 0.6 and 6.9, and ensuring a consistent 0.650 Đảm bảo.
The data analysis reveals a series of test results for various pier and environmental combinations, with values ranging from -49005 to -45619 The results show a consistent pattern of 0.6 and 6.9 values, with slight variations in the third and fourth decimal places, ranging from 0.263 to 0.385 The "Đảm bảo" label indicates a level of assurance or guarantee, suggesting that these results meet certain standards or requirements.
3.2 kiểm tra tỉ số nén vách thang máy
Bảng 1.49 Tỉ số nén vách P1
KIỂM TRA TỈ SỐ NÉN VÁCH P1
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The test results for EnvDDBMin and EnvDDBMax show compliance with the required standards, with TM P1 EnvDDBMin recording a value of -374, BNM P1 EnvDDBMax at 64, and T38 P1 EnvDDBMax at -16, all within the acceptable range of 0.35 to 1.60 The corresponding p-values for these tests are 0.021, 0.004, and 0.001, respectively, indicating a high level of statistical significance Additionally, the results for BNM P1 EnvDDBMin and T38 P1 EnvDDBMin also demonstrate compliance, with values of -197 and -252, and p-values of 0.011 and 0.014, respectively.
The EnvDDBMax and EnvDDBMin values were analyzed across various temperature points, including T37, T36, T35, T34, T33, T32, T31, T30, T29, and T28, with corresponding values ranging from -62 to -1562 for EnvDDBMax and -498 to -3160 for EnvDDBMin The results showed a consistent pattern of increasing values as the temperature decreased, with all data points meeting the required standard of 0.35 and 1.60, and a maximum value of 0.650.
The EnvDDBMin and EnvDDBMax values for various temperature points, ranging from T28 to T19, have been recorded with corresponding values of 0.35, 1.60, and 0.650 The EnvDDBMin values range from -2316 to -6112, while the EnvDDBMax values range from -973 to -2991 The corresponding percentage values for EnvDDBMin range from 0.132 to 0.349, and for EnvDDBMax range from 0.056 to 0.171 All recorded values are marked as "Đảm bảo" or ensured, indicating a level of reliability in the data.
The EnvDDBMax and EnvDDBMin values vary across different T levels, ranging from T18 to T9, with corresponding values of -1898 to -4751 for EnvDDBMax and -4054 to -6347 for EnvDDBMin The EnvDDBMax values decrease as the T level decreases, with a consistent value of 0.35 for the first column and 1.60 for the second column across all T levels The EnvDDBMin values also decrease as the T level decreases, with a consistent value of 0.35 for the first column and 1.60 for the second column across all T levels The fourth and fifth columns show a gradual increase in values as the T level decreases, with a consistent value of 0.650 for the fifth column across all T levels.
The data presented showcases a comprehensive analysis of various environmental parameters, including EnvDDBMin and EnvDDBMax, across different levels, from T9 to TL1 The results indicate a consistent range of values, with EnvDDBMin ranging from -5354 to -11080 and EnvDDBMax ranging from -2569 to -5204 The corresponding values for the 0.35, 1.60, and 0.650 parameters remain relatively stable across all levels The data suggests a high degree of consistency and reliability, with all results classified as "Đảm bảo," indicating a high level of assurance or guarantee.
Bảng 1.50 Tỉ số nén vách P2
KIỂM TRA TỈ SỐ NÉN VÁCH P2
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
The EnvDDBMin and EnvDDBMax values for various models, including TM, BNM, T38, T37, T36, T35, T34, and T33, were found to be within the acceptable range, with values ranging from -203 to 13 for EnvDDBMax and -1597 to -9 for EnvDDBMin, while maintaining a constant value of 0.35 for the first column and 1.25 for the second column, and a consistent value of 0.650 for the last column, indicating a high level of accuracy and reliability in the data.
The EnvDDBMax and EnvDDBMin values are listed for various temperature levels, ranging from T32 to T23, with corresponding values for P2, 0.35, 1.25, and 0.650 Đảm bảo The EnvDDBMax values range from -39 to -199, while the EnvDDBMin values range from -169 to -338, indicating a significant variation in the data The P2 values remain constant at 0.35, and the 1.25 and 0.650 Đảm bảo values are consistent throughout the data set.
The EnvDDBMin and EnvDDBMax values for T23 to T14 P2 range from -363 to -5372 and -214 to -350 respectively, with a consistent 0.35 and 1.25 value, and a 0.650 Đảm bảo value across all data points The EnvDDBMin values show a gradual increase from 0.027 to 0.393, while the EnvDDBMax values range from 0.016 to 0.255, indicating a consistent pattern in the data.
The data presented shows a series of test results for EnvDDBMax and EnvDDBMin across various temperature levels, ranging from T13 to T4, with consistent values of 0.35 and 1.25 The results indicate a gradual increase in the values of EnvDDBMax and EnvDDBMin as the temperature decreases, with all tests showing a status of "Đảm bảo" or "Ensure." The EnvDDBMax values range from -368 to -808, while the EnvDDBMin values range from -577 to -1211 The corresponding values for the tests also show a consistent increase, ranging from 0.027 to 0.059 for EnvDDBMax and 0.042 to 0.089 for EnvDDBMin.
The EnvDDBMin and EnvDDBMax values for various models, including T4 P2, T3 P2, TL2 P2, T2 P2, and TL1 P2, have been analyzed, showing a range of values from -914 to -4231 for EnvDDBMin and -598 to -438 for EnvDDBMax The results indicate that all models have a consistent value of 0.35 for the first column, 1.25 for the second column, and 0.650 for the last column The third column values vary from 0.032 to 0.586, and the fourth column values range from 0.043 to 0.650 Overall, the data suggests that the models are within the ensured limits, as indicated by the "Đảm bảo" status.
Bảng 1.51 Tỉ số nén vách P3
KIỂM TRA TỈ SỐ NÉN VÁCH P3
Tầng Phần tử Tổ hợp Lực dọc Tiết diện v [v] Kiểm tra
NỀN MÓNG
Nội lực chân cột
Bảng 2.1 Nội lực tiêu chuẩn chân cột trục 6-A
TABLE: Joint Reactions Story Label Output Case Step Type FX FY FZ MX MY kN kN kN kNm kNm
The data set presents various combinations of Base 117, each with its maximum and minimum values AComb2 and AComb3 share the same maximum and minimum values of 20 and -17, respectively, with corresponding values of 75 and 71 AComb4 and AComb5 have maximum values of 5 and minimum values of -3, while AComb6 and AComb7 have maximum values of 20 and minimum values of -14 AComb8 and AComb9 have maximum values of 7 and minimum values of 0, whereas AComb10, AComb11, AComb12, and AComb13 have maximum values of 42 and minimum values of -38 Lastly, AComb14, AComb15, and AComb16 have maximum values of 23 and minimum values of -19, indicating a range of variations across the different combinations.
Base 117 AComb16 Min -19 18 26043 -391 -76 Base 117 AComb17 Max 23 145 29092 142 68 Base 117 AComb17 Min -19 18 26043 -391 -76
Bảng 2.2 Nội lực tính toán chân cột trục 6-A
TABLE: Joint Reactions Story Label Output Case Step Type FX FY FZ MX MY kN kN kN kNm kNm
The Base 117 BComb series showcases a range of maximum and minimum values across various combinations Notably, BComb2 and BComb3 exhibit identical max and min values, with maximums of 27, 83, and 29192, and minimums of -24, 78, and 28894 In contrast, BComb4 and BComb5 display maximums of 7, 182, and 31546, and minimums of -4, -20, and 26540 BComb6 and BComb7 share similar values, with maximums of 27, 113, and 34999, and minimums of -19, 108, and 34730 Furthermore, BComb8 and BComb9 display maximums of 9, 201, and 37118, and minimums of -1, 20, and 32612 The BComb10 to BComb13 combinations exhibit consistent maximums of 43, 113, and 31570, and minimums of -38, 69, and 30397 Lastly, BComb14 and BComb15 show maximums of 23, 154, and 32508, and minimums of -19, 27, and 29459.
Base 117 BComb16 Max 23 154 32508 127 67 Base 117 BComb16 Min -19 27 29459 -406 -77 Base 117 BComb17 Max 23 154 32508 127 67 Base 117 BComb17 Min -19 27 29459 -406 -77
1.2 Cột trục 9-F 1.2.1 Nội lực tiêu chuẩn
Bảng 2.3 Nội lực tiêu chuẩn móng trục 9-F
TABLE: Joint Reactions Story Label Output Case Step Type FX FY FZ MX MY kN kN kN kNm kNm
The results of Base 146 AComb analysis show varying maximum and minimum values for each combination The maximum values range from 0 to 61, with the highest values observed in AComb10 to AComb13, reaching 61 and 90, and a maximum value of 38562 The minimum values range from -6 to -68, with the lowest values observed in AComb10 to AComb13, reaching -68 and 39, and a minimum value of 37209 In contrast, AComb4 and AComb5 show a significant difference, with maximum values of 0 and 130, and minimum values of -6 and -17 AComb8 and AComb9 also display distinct values, with maximum values of -1 and 147, and minimum values of -6 and 14.
Base 146 AComb15 Max 30 136 38561 188 125 Base 146 AComb15 Min -36 -7 37210 -399 -112 Base 146 AComb16 Max 30 136 38561 188 125 Base 146 AComb16 Min -36 -7 37210 -399 -112 Base 146 AComb17 Max 30 136 38561 188 125 Base 146 AComb17 Min -36 -7 37210 -399 -112
Bảng 2.4 Nội lực tính toán móng trục 9-F
TABLE: Joint Reactions Story Label Output Case Step Type FX FY FZ MX MY kN kN kN kNm kNm
The Base 146 BComb series presents varying maximum and minimum values across different combinations BComb2 and BComb3 show maximum values of 41, 64, and 39853, with minimum values of -47, 61, and 39148 In contrast, BComb4 and BComb5 have maximum values of 1, 164, and 40426, with minimum values of -7, -38, and 38575 The BComb6 and BComb7 combinations display maximum values of 35, 92, and 49265, with minimum values of -43, 90, and 48631 Furthermore, BComb8 and BComb9 exhibit maximum values of 0, 182, and 49781, with minimum values of -8, 0, and 48116 The BComb10, BComb11, BComb12, and BComb13 combinations show consistent maximum values of 61, 97, and 43326, with minimum values of -68, 47, and 41973 Lastly, BComb14 presents a maximum value of 30, 143, and 43326, with notable deviations in its minimum values.
Base 146 BComb14 Min -37 1 41974 -411 -111 Base 146 BComb15 Max 30 143 43326 175 126 Base 146 BComb15 Min -37 1 41974 -411 -111 Base 146 BComb16 Max 30 143 43326 175 126 Base 146 BComb16 Min -37 1 41974 -411 -111 Base 146 BComb17 Max 30 143 43326 175 126 Base 146 BComb17 Min -37 1 41974 -411 -111
Thiết kế móng trục 9-F với trường hợp tổ hợp cơ bản và kiểm tra lại với tổ hợp tải trọng gió và tải trọng động đất
- Bê tông cấp bền B40 có 𝑅 𝑏 = 22(𝑀𝑃𝑎), 𝑅 𝑏𝑡 = 1,4(𝑀𝑃𝑎)
- Cốt thép chịu lực nhóm 𝐶𝐵500 − 𝑉: 𝑅 𝑠 = 𝑅 𝑠𝑐 = 435(𝑀𝑃𝑎)
- Từ bảng giá trị nội lực do công trình bên trên truyền vào, phân tích từ mô hình Etabs
Kết hợp giá trị nội lực công trình từ mô hình Etabs và tải trọng giằng móng, sàn tầng hầm 3, chúng ta có thể xác định được các bảng tổng giá trị nội lực chân cột tác dụng lên đài móng, cung cấp thông tin quan trọng cho quá trình thiết kế và xây dựng công trình.
Bảng 2.5 Tổng giá trị nội lực tiêu chuẩn chân cột trục 9-F
(Tĩnh tải + Hoạt tải) 44009 -4 83 -129 8 Comb8
Comb15 (TT + 0,3HT + DDY - 0,3DDX) 38561 30 136 188 125
Bảng 2.6 Tổng giá trị nội lực tính toán chân cột trục 9-F
(Tĩnh tải + Hoạt tải) 49998 -4 94 -146 9 Comb8
Comb15 (TT + 0,3HT + DDY - 0,3DDX) 43326 30 143 175 126
Hình 2.1 Phương tải trọng các dụng nên đài móng móng
2.3 Xác định số lượng cọc và bố trí cọc trên mặt bằng
- Tính theo trường hợp tổ hợp cơ bản
- Áp lực tính toán giả định tác dụng lên đáy đài do phản lực đầu cọc gây ra:
- Diện tích sơ bộ đáy đài:
+ ℎ 𝑡𝑏 = 2,5(𝑚): Chiều sâu đặt đáy đài so với cao độ sàn tầng hầm;
+ 𝑛: Hệ số vượt tải, lấy bằng 1,1;
- Trọng lượng tính toán sơ bộ của đài và đất trên đài:
- Số lượng cọc sơ bộ:
➢ Chọn cọc và đài cọc:
+ Số lượng cọc: 6 + Khoảng cách 2 tim cọc: ≥ 2,5𝑑 = 3000(𝑚𝑚) + Khoảng cách từ mép cọc đến mép đài ≥ 250(𝑚𝑚) chọn: 300(𝑚𝑚) + Chọn kích thước đài: 𝑏 × 𝑙 ×ℎ= 4800 × 7800 × 2500(𝑚𝑚)
Hình 2.2 Bố trí cọc móng trục 9-F
2.4 Kiểm tra điều kiện lực dọc lớn nhất truyền xuống cọc 2.4.1 Xác định tải trọng đáy đài
- Diện tích thực tế của đế đài: 𝐹 𝑑 = 𝑏 𝑙 = 4,8.7,8 = 37,44(𝑚 2 )
- Khoảng cách giữa các cọc phải thỏa mãn 𝑎 ≥ 2,5𝑑 = 3000(𝑚𝑚)
- Khoảng cách bố trí thực tế nhỏ nhất 3000mm
- Trọng lượng tính toán của đài và đất trên đài:
Bảng 2.7 Tải trọng tính toán đáy đài
Tải trọng tính toán Tổ hợp cơ bản
Tổ hợp động đất Comb15 (𝒌𝑵𝒎)
2.4.2 Xác định lực truyền lên các cọc
- Móng chịu tải lệch tâm theo hai phương nên lực truyền xuống cọc được xác định theo công thức:
+ 𝑛 = 6 Số lượng cọc trong móng;
+ 𝑥 𝑖 , 𝑦 𝑖 Khoảng cách từ trục cọc thứ i đến trục Y, X;
Bảng 2.8 Khoảng cách cọc đến trục móng M1
Bảng 2.9 Lực truyền lên các cọc móng M1
2.4.3 Kiểm tra điều kiện lực lớn nhất truyền xuống cọc Điều kiện kiểm tra: 𝑃 = 𝑃 𝑚𝑎𝑥 𝑡𝑡 + 𝑃 𝑐 𝑡𝑡 < 𝑃 𝑠𝑐𝑡 𝑡𝑡
- Trọng lượng tính toán của cọc kể từ đáy đài: 𝑃 𝑐 𝑡𝑡 = 𝑛𝐹 𝑐 𝐿 𝑐 𝛾 𝑐
+ 𝐹 𝑐 = 1,13: Diện tích mặt cắt ngang của cọc
+ 𝛾 𝑐 : Trọng lượng riêng của cọc
- Do một phần cọc nằm dưới mực nước ngầm nên phải tính với trọng lượng riêng đẩy nổi:
+ Chiều dài cọc nằm dưới mực nước ngầm: 𝐿 𝑐𝑁𝑁 = 6(𝑚)
❖ Kiểm tra lực truyền xuống cọc
𝑃 = 9713 < 𝑃 𝑠𝑐𝑡 𝑡𝑡 = 11636(𝑘𝑁) Đồng thời 𝑃 𝑚𝑖𝑛 𝑡𝑡 = 8042(𝑘𝑁) > 0 nên không phải kiểm tra điều kiện chống nhổ
❖ Kiểm tra điều kiện kinh tế:
Bảng 2.10 Kiểm tra điều kiện lực lớn nhất truyền xuống cọc
Tổ hợp 𝑷 = 𝑷 𝒎𝒂𝒙 𝒕𝒕 + 𝑷 𝒄 𝒕𝒕 (𝒌𝑵) 𝑷 𝒔𝒄𝒕 𝒕𝒕 (𝒌𝑵) Điều kiện kinh tế Kết luận
Tải trọng gió 9707 13963 0,99 Thỏa mãn Động đất 8634 10402 1,02 Thỏa mãn
2.5 Kiểm tra nền móng theo trạng thái giới hạn thứ 2 2.5.1 Xác định kích thước khối móng quy ước
- Độ lún của nền móng được tính theo độ lún của nền khối móng quy ước
Bảng 2.11 Độ lún của khối móng quy ước
Lớp đất Chiều dài trong phạm vi cọc 𝜑 𝑖 𝜑 𝑖 ℎ 𝑖
- Góc mở rộng của khối móng quy ước từ mép ngoài cọc tại đáy đài:
- Chiều dài của đáy khối quy ước cạnh 𝐿 𝑀 :
- Bề rộng của đáy khối quy ước𝐵 𝑀 :
- Chiều sâu của khối móng quy ước (kể từ cao độ sàn hầm đến mũi cọc):
- Diện tích đáy đài móng quy ước là:
2.5.2 Tải trọng và áp lực tiêu chuẩn tại đáy móng quy ước
❖ Tải trọng tiêu chuẩn của khối móng quy ước
+ 𝑁 1 𝑡𝑐 Trọng lượng tiêu chuẩn của đài và đất trên đài
𝑁 1 𝑡𝑐 = 𝐹 𝑑 ℎ 𝑑 𝛾 𝑏𝑡 = 37,44.2,5.25 = 2340(𝑘𝑁) + 𝑁 2 𝑡𝑐 Trọng lượng tiêu chuẩn của khối móng quy ước tính từ đáy đài đến mũi cọc, trừ đi trọng lượng đất bị cọc chiếm chỗ:
𝑁 2 𝑡𝑐 = (𝐹 𝑀 − 𝑛 𝑐 𝐹 𝑐 ) 𝑙 𝑐 𝛾 𝐼𝐼 ′ = (156,51 − 6.1,13) 26,9.17,4 = 70083(kN) Với 𝛾 𝐼𝐼 ′ là trọng lương trung bình của các lớp đất từ đáy khối móng quy ước trở lên đến đáy đài
26,9 = 17,4(𝑘𝑁/𝑚 3 ) + 𝑁 3 𝑡𝑐 Trọng lượng cọc trong phạm vi khối móng quy ước:
- Tổng trọng lượng khối móng quy ước:
- Giá trị lực dọc tiêu chuẩn xác định đến đáy khối móng quy ước:
- Mômen tiêu chuẩn tương ứng với trọng tâm đáy khối móng quy ước:
Bảng 2.12 Tải trọng tiêu chuẩn đáy khối móng quy ước
Tải trọng Tổ hợp cơ bản
Tổ hợp động đất Comb15 (𝒌𝑵𝒎)
❖ Áp lực tiêu chuẩn tại đáy móng quy ước
- Độ lệch tâm theo phương trục x:
- Độ lệch tâm theo phương y:
- Áp lực tiêu chuẩn ở đáy khối móng quy ước:
Bảng 2.13 Áp lực tiêu chuẩn tại đáy móng quy ước trục 9-F
2.5.3 Kiểm tra điều kiện áp lực ở dưới đáy móng quy ước
- Cường độ tính toán của đất tại đáy khối quy ước (theo TCVN 9362:2012):
+ 𝑚 1 = 1,2: Đáy khối móng quy ước là cuội sỏi;
+ 𝑚 2 = 1: Công trình không thuộc loại tuyệt đối cứng;
+ 𝑘 𝑡𝑐 = 1: Hệ số tin cậy trường hợp các chỉ tiêu cơ lý của đất lấy theo số liệu thí nghiệm trực tiếp với đất;
+ 𝐴 = 3,66; 𝐵 = 15,64; 𝐷 = 14,64: Tra bảng 14 TCVN 9362-2012 phụ thuộc vào
+ 𝑐 𝐼𝐼 = 0 (𝑘𝑃𝑎): Trị tính toán của lực dính đơn vị của đất nằm trực tiếp dưới đáy móng ( Lớp số 6 là lớp cuội sỏi);
+ ℎ = 39,3 (𝑚): chiều sâu đặt móng so với cốt qui định;
+ 𝛾 𝐼𝐼 = 𝛾 𝑑𝑛 = 11 (𝑘𝑁/𝑚 3 ): Trị tính toán thứ hai của trọng lượng riêng đất dưới đáy khối quy ước;
+ 𝛾 𝐼𝐼 ′ = 17,4(𝑘𝑁/𝑚 3 ): Trị tính toán thứ hai của trọng lượng riêng đất từ chân cọc trở lên
+ ℎ 0 = ℎ − ℎ 𝑡𝑑 = 39,3 − 29,5 = 9,8 là độ sâu tính đổi khi có tầng hầm
- Điều kiện kiểm tra áp lực ở đáy móng quy ước:
Bảng 2.14 Kiểm tra điều kiện áp lực dưới đáy móng quy ước
Gió 782 757 Thỏa mãn Động đất 752 722 Thỏa mãn
2.5.4 Kiểm tra điều kiện biến dạng
- Áp dụng phương pháp cộng lún các lớp phân tố
- Ứng suất bản thân tại đáy khối quy ước:
- Áp lực gây lún ở đáy móng quy ước:
- Chia nền đất dưới móng quy ước thành các lớp phân tố đồng nhất có chiều dày:
- Gọi 𝑧 là độ sâu kể từ đáy móng quy ước thì ứng suất gây lún ở độ sâu 𝑧 𝑖 :
Bảng 2.15 Kết quả tính lún các lớp phân tố
- Độ lún của lớp phân tố thứ i xác định bằng công thức:
- Tại độ sâu 𝑧 𝑖 = 8,88 (𝑚) kể từ đáy khối quy ước có:
- Độ lún của khối quy ước: 𝑆 = ∑ 𝑛 𝑖=1 𝑆 𝑖
➢ Thỏa mãn điều kiện độ lún tuyệt đối
Bảng 2.16 Kiểm tra điều kiện biến dạng
Gió 1,19 Thỏa mãn Động đất 1,01 Thỏa mãn
2.6 Kiểm tra điều kiện chọc thủng
2.6.1 Kiểm tra chọc thủng của cột đối với đài theo phương bất kỳ
❖ Kiểm tra chọc thủng của cột đối với đài theo góc 45 độ
Xác định chiều cao đài cọc theo điều kiện đâm thủng là bước quan trọng trong thiết kế xây dựng Đối với chiều cao đài cọc ℎ 𝑑 2,5𝑚, việc vẽ tháp đâm thủng từ chân vách nghiêng một góc 45° so với phương thẳng đứng cột giúp đánh giá độ ổn định của cấu trúc.
- Theo phương X đáy tháp nằm trùm ra ngoài dãy cọc biên, nên không phải kiểm tra điều kiện chọc thủng
- Theo phương Y đáy tháp đi qua dãy cọc biên, nên phải kiểm tra điều kiện chọc thủng
Hình 2.4 Tháp chọc thủng cột đối mới đài móng trục 9-F
❖ Kiểm tra chọc thủng của cột đối với đài theo phương bất kỳ
Hình 2.5 Kiểm tra chọc thủng cột trục 9-F theo phương bất kỳ
- Khả năng chống chọc thủng:
+ Chiều cao làm việc của đài: h 0 = h d − a = 2,5 − 0,2 = 2,3 (m) c 1 = 1,689 (m) > 0,5h 0 = 0,5 2,3 = 1,15 (m) → c 1 = 1,689 (m) c 2 = 0,638 (m) < 0,5h 0 = 0,5 2,3 = 1,15 (m) → c 2 = 1,15 (m)
➢ Thỏa mãn điều kiện chông chọc thủng của cột theo phương bất kỳ
2.6.2 Kiểm tra chọc thủng của cọc đối với đài
Hình 2.6 Kiểm tra chọc thủng của cọc đối với đài trục 9-F
- Khả năng chống chọc thủng:
+ Chiều cao làm việc của đài: h 0 = h d − a = 2,5 − 0,2 = 2,3 (m)
Bảng 2.17 Kiểm tra điều kiện chọc thủng móng trục 9-F
Khả năng chịu lực Kết luận Của cột với đài theo phương bất kì (𝑘𝑁) 52572 52356 45900 54359 Thỏa mãn
Của cọc ở góc (𝑘𝑁) 8796 8790 7717 21126 Thỏa mãn
2.7 Tính toán và bố trí thép cho đài
Hình 2.7 Sơ đồ mặt ngàm tính thép móng trục 9-F
Bảng 2.18 Giá trị nội lực tính thép cho đài móng trục 9-F
Giá trị nội lực Tổ hợp cơ bản
- Lấy giá trị nội lực của trường hợp tải trọng cơ bản là lớn nhất để tính thép cho đài
❖ Tính giá trị 𝝃 𝑹 , 𝜶 𝑹 theo TCVN 5574-2018
Đối với bê tông nặng có cấp độ bền chịu nén dưới B70, tử số trong công thức được lấy bằng 0,8 Trong khi đó, đối với bê tông có cấp độ bền từ B70 đến B100 hoặc bê tông hạt nhỏ, tử số được lấy bằng 0,7.
+ 𝑥 𝑅 Chiều cao giới hạn vùng bê tông chịu nén;
+ 𝜀 𝑠,𝑒𝑙 Biến dạng tương đối của cốt thép chịu kéo khi ứng suất bằng 𝑅 𝑠 :
(Theo TCVN 5574:2018 mục 6.2.3.3 thì giá trị mô đun đàn hồi cốt thép 𝐸 𝑠 2,0.10 5 (𝑀𝑃𝑎) đối với cốt thép thanh theo TCVN 1561-1:2008, TCVN 1651-
2:2008, TCVN 6284-5:1997 (ISO 6934-5:1991) và đối với dây thép vuốt nguội TCVN 6288:1997 (ISO 10544:1992))
Biến dạng tương đối của bê tông chịu nén khi ứng suất bằng cường độ chịu nén đặc trưng Rb được xác định theo hướng dẫn trong mục 6.1.4.2 khi có tác dụng ngắn hạn của tải trọng Cụ thể, giá trị biến dạng tương đối εb2 đối với bê tông có cấp độ bền từ B60 trở xuống là 0,0035, còn đối với bê tông có cấp độ bền từ B70 đến B100, giá trị này được nội suy với giá trị cụ thể là 0,0033 cho B70 và 0,0030 cho B100.
0,0028) Khi có tác dụng dài hạn của tải trọng lấy theo Bảng 9
Trong phạm vi đồ án này, giá trị biến dạng tương đối của bê tông (𝜀 𝑏2) sẽ được tính toán dựa trên điều kiện tác dụng dài hạn của tải trọng, giúp đánh giá ảnh hưởng của tải trọng lên biến dạng của bê tông theo thời gian.
Theo số liệu từ trang web wikipedia.org, nhiệt độ trung bình cao nhất tại Hà Nội thường rơi vào tháng 7, với mức nhiệt cao nhất là 33,1 độ C và độ ẩm lên tới 82,2%.
Hình 2.9 Dữ liệu khí hậu Hà Nội
Dựa trên các số liệu trên, kết hợp Bảng 9 ta có được giá trị 𝜀 𝑏2 khi chịu nén là 0,0042
❖ Tính thép dọc theo phương X (Mặt ngàm I-I):
- Cọc ngàm vào đài 15 (𝑐𝑚) nên chiều cao hữu ích của đài là:
- Giả thiết cốt thép sử dụng 𝜙25 → Chiều cao làm việc của móng:
- Tính hàm lượng cốt thép:
- Chiều dài một thanh thép:
- Khoảng cách giữa các thanh thép:
❖ Tính thép dọc theo phương Y (Mặt ngàm II-II):
- Cọc ngàm vào đài 15 (𝑐𝑚) nên chiều cao hữu ích của đài là:
- Giả thiết cốt thép sử dụng 𝜙25 → Chiều cao làm việc của móng:
- Tính hàm lượng cốt thép:
- Chiều dài một thanh thép:
- Khoảng cách giữa các thanh thép:
Hình 2.10 Mặt cắt bố trí thép móng trục 9-F
THI CÔNG
Lập tiến độ thi công
Khối lượng công tác thi công được lấy theo mặt bằng của tầng điển hình ĐOÀN ĐỨC TRUNG – 17X+ 291
HIỆU TÊN CÔNG VIỆC ĐƠN
KHỐI LƯỢNG ĐỊNH MỨC NHU CẦU
NC Máy NC Máy CHÚ
3 Công tác chuẩn bị Labour 150 5 30
6 AF.61431 GCLD cốt thép cột, vách Ton 49.26 7.46 367 5 73
7 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
8 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
9 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
10 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
11 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
12 AF.61722 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 12 580 8 73
13 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
14 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730.00 150m3/h 60 0.61 1 60 2 máy
15 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
16 TT Kéo căng cáp ứng lực trước Labour 20 2 10
17 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
20 AK.66110 Lắp trần thạch cao m2 2433.00 0.2 487 8 61
22 TT Công việc khác Labour 450 9 50
24 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
25 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
26 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
27 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
28 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
29 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
30 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
31 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
32 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
33 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
34 TT Kéo căng cáp ứng lực trước Labour 20 2 10
35 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
38 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
39 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
40 TT Công việc khác Labour 450 9 50
42 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
43 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 293
45 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
46 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
47 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
48 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
49 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
50 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
51 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
52 TT Kéo căng cáp ứng lực trước Labour 20 2 10
53 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
56 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
57 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
58 TT Công việc khác Labour 450 9 50
60 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
61 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
62 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
63 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
64 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
65 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
66 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
67 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
69 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
70 TT Kéo căng cáp ứng lực trước Labour 20 2 10
71 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
74 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
75 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
76 TT Công việc khác Labour 450 9 50
78 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
79 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
80 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
81 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
82 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
83 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
84 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
85 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
86 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
87 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
88 TT Kéo căng cáp ứng lực trước Labour 20 2 10
89 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 295
92 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
93 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
94 TT Công việc khác Labour 450 9 50
96 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
97 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
98 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
99 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
100 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
101 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
102 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
103 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
104 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
105 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
106 TT Kéo căng cáp ứng lực trước Labour 20 2 10
107 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
110 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
111 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
112 TT Công việc khác Labour 450 9 50
114 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
115 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
116 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
117 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
118 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
119 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
120 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
121 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
122 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
123 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
124 TT Kéo căng cáp ứng lực trước Labour 20 2 10
125 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
128 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
129 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
130 TT Công việc khác Labour 450 9 50
132 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
133 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
134 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
135 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
136 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 297
138 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
139 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
140 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
141 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
142 TT Kéo căng cáp ứng lực trước Labour 20 2 10
143 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
146 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
147 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
148 TT Công việc khác Labour 450 9 50
150 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
151 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
152 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
153 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
154 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
155 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
156 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
157 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
158 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
159 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
161 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
164 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
165 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
166 TT Công việc khác Labour 450 9 50
168 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
169 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
170 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
171 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
172 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
173 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
174 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
175 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
176 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
177 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
178 TT Kéo căng cáp ứng lực trước Labour 20 2 10
179 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
182 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 299
184 TT Công việc khác Labour 450 9 50
186 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
187 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
188 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
189 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
190 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
191 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
192 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
193 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
194 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
195 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
196 TT Kéo căng cáp ứng lực trước Labour 20 2 10
197 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
200 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
201 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
202 TT Công việc khác Labour 450 9 50
204 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
205 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
207 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
208 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
209 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
210 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
211 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
212 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
213 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
214 TT Kéo căng cáp ứng lực trước Labour 20 2 10
215 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
218 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
219 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
220 TT Công việc khác Labour 450 9 50
222 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
223 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
224 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
225 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
226 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
227 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
228 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
229 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 301
231 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
232 TT Kéo căng cáp ứng lực trước Labour 20 2 10
233 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
236 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
237 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
238 TT Công việc khác Labour 450 9 50
240 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
241 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
242 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
243 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
244 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
245 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
246 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
247 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
248 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
249 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
250 TT Kéo căng cáp ứng lực trước Labour 20 2 10
251 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
254 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
255 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
256 TT Công việc khác Labour 450 9 50
258 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
259 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
260 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
261 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
262 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
263 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
264 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
265 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
266 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
267 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
268 TT Kéo căng cáp ứng lực trước Labour 20 2 10
269 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
272 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
273 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
274 TT Công việc khác Labour 450 9 50
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 303
276 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
277 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
278 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
279 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
280 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
281 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
282 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
283 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
284 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
285 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
286 TT Kéo căng cáp ứng lực trước Labour 20 2 10
287 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
290 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
291 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
292 TT Công việc khác Labour 450 9 50
294 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
295 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
296 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
297 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
298 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
300 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
301 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
302 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
303 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
304 TT Kéo căng cáp ứng lực trước Labour 20 2 10
305 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
308 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
309 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
310 TT Công việc khác Labour 450 9 50
312 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
313 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
314 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
315 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
316 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
317 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
318 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
319 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
320 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
321 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 305
323 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
326 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
327 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
328 TT Công việc khác Labour 450 9 50
330 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
331 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
332 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
333 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
334 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
335 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
336 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
337 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
338 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
339 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
340 TT Kéo căng cáp ứng lực trước Labour 20 2 10
341 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
344 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
346 TT Công việc khác Labour 450 9 50
348 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
349 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
350 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
351 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
352 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
353 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
354 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
355 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
356 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
357 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
358 TT Kéo căng cáp ứng lực trước Labour 20 2 10
359 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
362 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
363 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
364 TT Công việc khác Labour 450 9 50
366 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
367 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 307
369 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
370 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
371 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
372 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
373 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
374 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
375 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
376 TT Kéo căng cáp ứng lực trước Labour 20 2 10
377 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
380 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
381 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
382 TT Công việc khác Labour 450 9 50
384 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
385 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
386 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
387 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
388 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
389 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
390 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
391 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
393 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
394 TT Kéo căng cáp ứng lực trước Labour 20 2 10
395 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
398 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
399 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
400 TT Công việc khác Labour 450 9 50
402 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
403 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
404 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
405 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
406 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
407 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
408 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
409 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
410 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
411 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
412 TT Kéo căng cáp ứng lực trước Labour 20 2 10
413 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 309
416 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
417 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
418 TT Công việc khác Labour 450 9 50
420 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
421 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
422 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
423 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
424 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
425 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
426 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
427 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
428 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
429 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
430 TT Kéo căng cáp ứng lực trước Labour 20 2 10
431 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
434 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
435 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
436 TT Công việc khác Labour 450 9 50
438 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
439 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
440 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
441 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
442 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
443 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
444 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
445 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
446 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
447 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
448 TT Kéo căng cáp ứng lực trước Labour 20 2 10
449 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
452 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
453 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
454 TT Công việc khác Labour 450 9 50
456 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
457 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
458 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
459 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
460 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 311
462 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
463 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
464 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
465 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
466 TT Kéo căng cáp ứng lực trước Labour 20 2 10
467 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
470 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
471 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
472 TT Công việc khác Labour 450 9 50
474 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
475 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
476 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
477 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
478 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
479 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
480 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
481 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
482 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
483 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
485 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
488 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
489 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
490 TT Công việc khác Labour 450 9 50
492 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
493 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
494 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
495 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
496 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
497 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
498 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
499 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
500 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
501 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
502 TT Kéo căng cáp ứng lực trước Labour 20 2 10
503 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
506 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 313
508 TT Công việc khác Labour 450 9 50
510 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
511 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
512 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
513 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
514 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
515 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
516 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
517 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
518 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
519 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
520 TT Kéo căng cáp ứng lực trước Labour 20 2 10
521 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
524 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
525 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
526 TT Công việc khác Labour 450 9 50
528 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
529 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
531 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
532 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
533 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
534 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
535 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
536 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
537 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
538 TT Kéo căng cáp ứng lực trước Labour 20 2 10
539 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
542 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
543 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
544 TT Công việc khác Labour 450 9 50
546 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
547 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
548 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
549 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
550 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
551 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
552 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
553 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 315
555 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
556 TT Kéo căng cáp ứng lực trước Labour 20 2 10
557 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
560 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
561 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
562 TT Công việc khác Labour 450 9 50
564 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
565 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
566 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
567 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
568 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
569 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
570 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
571 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
572 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
573 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
574 TT Kéo căng cáp ứng lực trước Labour 20 2 10
575 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
578 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
579 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
580 TT Công việc khác Labour 450 9 50
582 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
583 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
584 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
585 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
586 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
587 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
588 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
589 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
590 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
591 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
592 TT Kéo căng cáp ứng lực trước Labour 20 2 10
593 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
596 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
597 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
598 TT Công việc khác Labour 450 9 50
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 317
600 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
601 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
602 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
603 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
604 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
605 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
606 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
607 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
608 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
609 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
610 TT Kéo căng cáp ứng lực trước Labour 20 2 10
611 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
614 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
615 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
616 TT Công việc khác Labour 450 9 50
618 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
619 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
620 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
621 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
622 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
624 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
625 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
626 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
627 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
628 TT Kéo căng cáp ứng lực trước Labour 20 2 10
629 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
632 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
633 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
634 TT Công việc khác Labour 450 9 50
636 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
637 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
638 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
639 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
640 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
641 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
642 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
643 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
644 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
645 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 319
647 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
650 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
651 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
652 TT Công việc khác Labour 450 9 50
654 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
655 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
656 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
657 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
658 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
659 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
660 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
661 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
662 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
663 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
664 TT Kéo căng cáp ứng lực trước Labour 20 2 10
665 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
668 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
670 TT Công việc khác Labour 450 9 50
672 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
673 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
674 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
675 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
676 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
677 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
678 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
679 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
680 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
681 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
682 TT Kéo căng cáp ứng lực trước Labour 20 2 10
683 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
686 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
687 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
688 TT Công việc khác Labour 450 9 50
690 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
691 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
Tieu luan ĐOÀN ĐỨC TRUNG – 17X+ 321
693 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
694 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
695 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
696 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
697 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
698 AF.22333 Đổ bê tông dầm, sàn, cầu thang m3 730 150m3/h 60 0.61 1 60 2 máy
699 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
700 TT Kéo căng cáp ứng lực trước Labour 20 2 10
701 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
704 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
705 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
706 TT Công việc khác Labour 450 9 50
708 AF.61431 GCLD cốt thép cột, vách Ton 57.72 7.46 367 5 73
709 AF.83411 GCLD ván khuôn cột, vách 100m2 9.41 16.89 159 3 53
710 AF.22270 Đổ bê tông cột, vách m3 322.52 150m3/h 60 0.27 1 60 2 máy
711 TT Bảo dưỡng bê tông cột, vách Labour 10 5 2
712 AF.83411 Tháo dỡ ván khuôn cột, vách 100m2 9.41 5.63 53 1 53
713 AF.83111 GCLD ván khuôn dầm, sàn, cầu thang 100m2 25.47 14.625 372 6 62
714 AF.61711 GCLD cốt thép dầm, sàn, cầu thang Ton 48.34 13.9 580 8 73
715 TT Lắp đặt cáp ứng lực trước Ton 12.24 100 2 50
717 TT Bảo dưỡng bê tông dầm, sàn, cầu thang Labour 10 5 2
718 TT Kéo căng cáp ứng lực trước Labour 20 2 10
719 AF.83111 Tháo dỡ ván khuôn dầm sàn, cầu thang 100m2 25.47 4.875 124 6 21
722 AK.66110 Lắp trần thạch cao m2 2433 0.2 487 8 61
723 AK.51260 Lát nền bằng gạch ceramic m2 2503 0.15 365 5 73 Gạch
724 TT Công việc khác Labour 450 9 50
726 Xây tường thu hồi Labour 40 2 20
727 AK.54310 Lát gạch lỗ rỗng chống nóng m2 1259 0.17 159 6 27
728 AK.51260 Lát gạch sàn mái m2 1259 0.15 189 5 38
731 Trát ngoài toàn bộ công trình Labour 1200 30 40
732 AK.84221 Lăn sơn toàn bộ công trình Labour 1200 30 40
734 Lắp đặt thiết bị điện, nước Labour 1600 40 40
735 Vệ sinh, dọn dẹp mặt bằng Labour 50 5 10