1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

BIỆN PHÁP LẮP ĐẶT THÁP GIẢI NHIỆT

32 1 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 32
Dung lượng 3,64 MB
File đính kèm MOS Cooling Tower.rar (3 MB)

Nội dung

MOS, Biện pháp thi công Tháp giải nhiệt, Method of Statement of Cooling Tower Installation, Tháp lắp Tháp giải nhiệt, Cách lắp Tháp giải nhiệt trong các toàn nhà cao tầng sử dụng hệ thống Chiller có Tháp giải nhiệt nước

PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION METHOD STATEMENT FOR COOLING TOWER ASSEMBLY AND INSTALLATION Prepare by : SUB CONTRACTOR NAME: Hong Soon Min DATE : 23-April-2015 Checked by : POSCO NAME: DATE : POSCO NAME: DATE : Date: 23-April-15 Revision: Rev-00 MVAC Services Submission Ref :PSC-HK-MS-M-0010 Approved by : Consulted by: Page NAME: DATE : HKL PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION Table of Contents INTRODUCTION 1.1 1.2 1.3 Purpose Scope Exclusions .3 GENERAL 2.1 Program 2.2 Location Address 2.3 Approvals 2.4 Labor resources 2.5 Communications 2.6 Site Resources Required 2.7 Temporary material .4 2.8 Protection 2.9 Equipment/Tools 2.10 Hot works 2.11 Confined space works .6 2.12 Emergency & Safety Equipment .6 2.13 Materials required for installation 2.14 Schedule of drawings 2.15 Schedule of inspection 2.16 Attendees 2.17 Safety Briefing 2.18 Mitigation of Risk .9 Actual Works Method Statement 3.1 Delivery and Store .9 3.2 Cooling tower assembly & installation methodology 10 3.3 Setting to work .22 3.4 Testing 22 3.5 T&C Register 23 3.6 Reports 23 Appendix 24 4.1 Certificate of calibration 24 4.2 Instrument catalogue and manual book .25 MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -1 INTRODUCTION 1.1 Purpose The purpose of this Method statement is to bring the requirements from the technical specifications, drawings together in one convenient document for reference by the drafters, factory, site installers, QA/QC and all parties who are concerned with the project And this methodology to be followed for the assembly and installation of Cooling tower 1.2 Scope This is applicable to the assembly and installation of Cooling tower as set out in the project technical brief and the approved drawing 1.3 Exclusions Not application GENERAL 2.1 Program 2.1.1 Ensure that the shop drawing used for the references at site is approved for construction 2.1.2 Ensure that designated manpower to conduct works at site must be properly trained and well oriented by the safety engineer 2.1.3 All equipments, tools and mobile scaffolding to be used must be inspected and approved by authorized safety engineer at site 2.1.4 All staffs associated with the works shall be sufficiently experienced 2.1.5 When the workers climb up the working platform, ladder, his hands must be free 2.1.6 All materials to be used at site must be properly secured and clean 2.1.7 Working period to base on civil work and Cooling tower installation schedule which will be attached after getting approval (Waiting for approval) 2.2 LOCATION – ADDRESS Application for 21st floor 2.3 APPROVALS Materials of submission (Waiting for submission & approval) Shop drawing (Waiting for submission & approval) 2.4 LABOUR RESOURCES MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -The Cooling tower team will coordinate and carry out as below organization chart 2.5 Communications Office mobile phone or walkie-talkie will be used during working time 2.6 SITE RESOURCES REQUIRED Temporary fire protection equipment Site electric panel should be needed as site condition 2.7 TEMPORARY MATERIALS Materials cover needs to be prepared on the floor and cover Cooling tower when needed 2.8 PROTECTION Materials cover needs to be prepared on the floor and cover Cooling tower when needed 2.9 EQUIPMENT/TOOLS MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -Ensure the availability of equipment and tools provision for Cooling tower assembly and installation works as follows: Tape measure or folding rule Cavas sheet Silver ink marker pen Level measure Measure Laser machine Lighting Hand lighting Two-way radios 10 Hand lift 11 Hydraulic toe jack 12 Caution Tape 13 Pipe tube 14 Space roller (Double type) 15 Ropes 16 Traffice control cones 2.10 HOT WORKS MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -Not application 2.11 CONFINED SPACE WORKS Not application 2.12 EMERGENCY & SAFETY EQUIPMENT 1) Safety helmet 2) Safety shoes 3) Safety uniform MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -4) Hand gloves 2.13 MATERIALS REQUIRED FOR INSTALLATION Cooling tower Spring isolator Anchor bolt Frame for Cooling tower Wood Steel plate sheet Shackles Chain block Electric forklift MVAC Services 10 Steel ropes Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -2.14 SCHEDULE OF DRAWINGS Refer to shop drawing layout of floors as below CLMK_MECH_PC_2101 2.15 SCHEDULE OF INSPECTION/T&C FORM Refer to ITP form as the attached file in below 2.16 ATTENDEES 2.16.1 Sub-contractor manager 2.16.2 Sub-contractor site manager 2.16.3 Main contractor MEP coordinator 2.16.4 Main contractor mechanical engineer 2.16.5 HKL M&E manager 2.17 SAFETY BRIEFING 2.17.1 Safety shall be in first priority during construction, safety staff shall be present on site all the time to supervise and to remind workers to observe safety requirement Stop work order shall enforce once its dose not meet the safety requirements 2.17.2 Safety shall conform strictly observed All workers and staff on site shall be oriented of safety requirements All safety equipment such as cloths , shoes, helmet , gloves , safety belt should provide and regularly checked during construction 2.17.3 The engineer shall inspect all subcontractor tools prior to be used on site 2.17.4 Safety Supervisor shall be present for all the safety site inspection 2.17.5 For the safety of worker, grounding wire for the electric ARC process must be provided and wet cloths, protective glasses, long sleeve cloth must be imposed to worker 2.17.6 Fire extinguisher shall be provided at welding area and safety provision must done to ensure usage workability 2.17.7 Safety working with Scaffolding 2.17.7-1 All scaffolds must be erected under the supervision of a competent and experienced person- usually the construction superintendent This includes moving scaffolds from one position to another Each leg of a scaffold must be supported by and adequate footing Loose bards, bricks and other material not provide a safe, adequate base 2.17.7-2 Where the working platform in more than 10 feet off the ground, the scaffold shall have guardrails installed 2.17.7-3 If people are working under the scaffold, toe boards must be used to prevent tools and materials from falling on them MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION 2.17.7-4 Workers are not to climb the metal tubular frame of the scaffold to get the working platform Other, safer means of access must be used – a ladder or access from the building 2.17.8 Safety working with Mobile Scaffold 2.17.9 Mobile scaffolds have restricted reach unless a guy wire secures them They are more susceptible to overturning and require a smooth, level working surface A complete guardrail system must be used at elevations above 10 feet and shall be used at all working levels Scaffold should be moved when unoccupied and only by pushing from the base Wheel brakes must be set when scaffold is in use 2.18 MITIGATION OF RISK Impact damage during pouring of concrete installation to be monitored constancy white concrete is poured Correct connections or materials, ensure the final installation and connections are inspected and signed off with photographic records by MEP coordinator on site M&E staff from contractor, architect and client ACTUAL WORKS METHOD STATEMENT 3.1 Delivery and store Materials arrived to site shall be inspected and stored according to manufacturer recommendations Materials shall be stored in the covered and dry space During the receiving materials of Cooling tower, manpower shall be used to make Cooling tower The Cooling tower and accessories shall be protected and covered with polythene sheets before installing Materials of Cooling tower is as below MVAC Services Page PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION -3.2 COOLING TOWER ASSEMBLY AND INSTALLATION METHODOLOGY a) Safety officers and traffic control officers to station around the cordoned off areas until the crane and transporters for Cooling towers arrive MVAC Services Page 10 PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION - Casing rigging method MVAC Services Page 18 PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION - Alternate discharge hood sealing rigging method MVAC Services Page 19 PROJECT: EXCHANGE SQUARE (STREET 106 SITE) TITLE OF WORK: METHOD STATEMENT MVAC 23 APRIL 2015 FOR COOLING TOWER ASSEMBLY AND INSTALLATION MVAC Services Page 20

Ngày đăng: 19/04/2023, 22:38

w