1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant METHOD STATEMENT Erection, Alignment of Tank course shells by jockeying method.. 1500 MTPD Phosphoric Acid plant 4500 MTPD
Trang 11500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Prepared by Reviewed by Safety Release QA/QC
Approval Approved by
Date
Name
Section Engineer Construction Manager Safety manager QA / QC Manager Project Manager
Date
Name
Site Manager
4500 MTPD Sulphuric Acid plant
Method Statement No
CIVIL ELECTRICAL MECHANICAL INSTRUMENTATION
Trang 21 INTRODUCTION
The following is the method statement for the erection of Carbon Steel storage tanks with roof
by Jacking method and covers the following tanks
a) Fulisilic acid storage Tanks-2nos (234-R-01A/B)
b) Sulphuric acid product storage tanks-3nos
c) Potable water tank-1nos (245-R-01)
d) Diesel storage tank-1nos (246-R-01)
e) Molten sulphur tank -1nos
It comes under Sulphuric & Phosphoric acid plant
2 Function and location, General Description, Scope of Work
a) Function and Location
The function of the storage tank is to store the Concentrated acid / Weak acid / Effluent for Maturation/Storage purposes, and it was located in phosphoric acid plant area
Erection of I-Beams on the civil foundation and leveling
Erection, Alignment, Fit up and welding of bottom base plate
Inspecting welding with required NDT procedures like DP Test, Radiography, and Vacuum
box UT etc (refer-ITP)
Trang 31500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Erection, Alignment of Tank course shells by jockeying method
Erection of roof
Erection of Internal Baffle plates, Dip tube etc
Erection of Walk ways, staircase, Agitator support, Hand railing
Erection of Ladders, Flat forms and Hand rails
3 Related Documents
a) Technical specifications
b) Approved construction drawings
c) Weld map
d) Release of material for construction form SNC Lavalin
e) Release certificate starting of erection over civil foundation from MID
f) Vendor’s instruction/manual required
g) I.T.P (Inspection Test Plan)
h) All last revisions of Drawings, WPS, PQR, Welder certificated, etc
4 Required Material Testing, during and before work
Material grade to be confirmed for WPS/PQR/WELD Qualification
Batch number, Heat number punched on the plate to be compared with Mill certificate
5 Environmental and Safety
All the lifting tools gear like slings, belts, D-Shackles etc are of Tested & Certified by the TPI
Cranes involved in Erection are certified by TPI
All the PPE used for the work is of approved quality
All the Workers, Staff, Engineers involved in work are geared with full basic PERSONAL
PROTECTION EQUIPMENT
TOOL BOX TALK will be conducted on daily basis at the starting of the job
When working at height above 1.5mts from the ground every person to be wearing a safety belt When working at height proper scaffolding will be provided for accessing, testing, inspection for the client
Scaffolding work will be done by properly trained and certified workers only under the
supervision of Engineer
Entry Permit system for usage of scaffolding will be practiced
Trang 4While starting of welding, gas cutting, grinding, gouging operations HOT WORK permit system
will be practiced
All the gas cutting torches are installed with approved Flash back arrestors
All the welders are with proper hand gloves, Apron, Face shield and other additional required
safety gears
While working in confined space CONFINED SAPCE ENTRY PERMIT system will be practiced
All the power tools are of certified and tagged properly
All the power, welding cables are of certified and tagged properly
For handling Plates special lifting tools like horizontal and vertical plate lifting tools are used
Good housekeeping will be practices at all the time
Fire extinguishers are kept near the work for any fire incidents
Gas cylinders are stationed during work so that they maintain required distance from the heat source
Best engineering will be practiced to avoid accidents
6 Detail of work supported with sketches and with special highlight for details
• Extension of I Beams to the required length (Refer to QI(QUALITY INTERNATIONAL)
procedures)
• Inspection of welding
• Erection of I-Beams on slab
• Aligning & Leveling of I-Beams
• Anchoring of I-Beams of to the concrete foundation.(Hold)
• Erection of Bottom base Plate on the I-Beams
• Fit-up and Welding of Bottom base plate
• Inspection of welding By Penetration, RT, and Vacuum test
• Erection of Shell-5 plate on the bottom base plate and alignment with fit up
• Vertical welding of shell-5
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding
• Erection of shell-6 on the top of shell-5 and followed by alignment, fit up and welding of vertical
& horizontal welding
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Erection and fabrication of Roof
Trang 51500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
• Installation and fabrication of available Baffle plates
• Erection of Hydraulic jacks inside the tank and distribute symmetrically such that every jack per
3 meter of the circumference
• Installation, erection of walk ways and hand railings if advised
• Lifting of the shell-5 by 2450mm height by hydraulic jacks
• Erection, alignment and fit up of shell-4
• Welding of horizontal and vertical welds
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Lifting of the shell-4 by 2450mm height by hydraulic jacks
• Erection, alignment and fit up of shell-4
• Welding of horizontal and vertical welds
• Installation and fabrication of available Baffle plates
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Lifting of the shell-4 by 2450mm height by hydraulic jacks
• Erection, alignment and fit up of shell-3
• Welding of horizontal and vertical welds
• Installation and fabrication of available Baffle plates
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Lifting of the shell-3 by 2450mm height by hydraulic jacks
• Erection, alignment and fit up of shell-2
• Welding of horizontal and vertical welds
• Installation and fabrication of available Baffle plates
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Lifting of the shell-2 by 2450mm height by hydraulic jacks
• Erection, alignment and fit up of shell-1
• Welding of horizontal and vertical welds
• Installation and fabrication of available Baffle plates
• Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints
• Welding of Bottom shell -1to the Bottom base plate
Trang 6• Installation of Nozzle, pipe supports, flat forms, ladders, agitator supports and handrails
7 Curing and Weather Protection
All the plate will be supplied with sand blasted and primer coated by QI
All the welding edges will be protected by tape while painting
Any additional welding made on painted are will be power brushed and coated again
For locations with scratches, burns on painting etc during erection will be painted again.(rev-1)
8 Show hold points for internal and external required inspection including specified tests on
products
Fit up inspection for levels, weld gaps, etc
Vacuum test of welding of the bottom base plate
While welding Test of root pass with penetration test
Horizontal and vertical welds 10 % of the total length by RT
RT test for the T-Joints by 100%
9 Construction Equipment to be used , including standby Arrangement for breakage
While the shells are erected by Jacking of the top shells with Hydraulic Lifting Jacks which are
activated by a power pack A standby power pack is available for breakage And numbers of
spare hydraulic hoses are available for breakage
10 Lifting equipment, involved (where applicable, crash, tower crane…test and location)
For handling of plates cranes will be used for shifting, lifting, erection and purposes
11 Tools and associated other contractors Apparatus involved in this
The following tools are involved in work
• Welding Rectifiers machine
• Gas cutting torch
• Grinding machines of different sizes (100mm, 125mm and 150mm)
• Owen for baking of electrodes
12 Manpower involved and Trades, who does what and when
Supervisor for Tanks: - He takes care of all the activities associated in erection and fabrication of tanks and he involved in all the activities from staring to the finishing
Riggers: - These will involve in handling the plates for erection, alignment etc
Trang 71500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Fabricator/ Fitter: - He is responsible for fit ups, alignments, verticality and tolerances of the
total tank
Lifting Forman/ Jacking Specialist: - He takes the takes the lead role in alignment and
positioning of Hydraulic lifting Jacks, He takes the leading role in lifting of the tank shells at every step
Pipe Fitter: - He takes the fit up of nozzles and other pipe supports and structural items
Welders: - These will do all the welding operations
Grinders: - These will do grinding operation for the tank
Helpers: - These are the general helpers to skilled workers involving in job
Crane operator: - These will operate the crane
QA/QC Team: - These will guide the job for required QA/QC levels
13 Work Schedule Requirements’ and Timing for This work
For this job the daily regular work hours will be 10 hrs excluding lunch time
From 7-00Am to 6-00PM
On weekly half’s required core skilled workers like welders will be engaged if necessary
14 Training and Orientation for the Team
For all the team members TOOL BOX TALK will be conducted at the beginning of activity on daily
basis
The scaffolding team will be of trained and certified
The crane operator will be of trained and certified
The riggers involved will be of trained and certified
Regular monitor of welders and if necessary training will be given regularly
15 Tests on Systems (QA /QC )
Radiographic Test of all T-Joints by 100%
Vertical & Horizontal welding RT by 10 % of the total length of the welding
Vacuum test for the Base plate
Dye Penetrate Test for all Root pass and Final
In case Repair is needed, extension shots (penalty) to be match with API650
To be advised for any other test is needed
16 Logistics involved if work is expected to extend beyond normal working hours
Lighting while working at night
Shade protection while the wind velocity is very high
Trang 817 Annexes and sketches lists
WEIGHTS OF THE INDIVIDUAL MATERIALS for crane, lifting gear selection purpose
1 IPE 270 TANK BOTTOM BEAMS
2 CS Plate of 2400mm Width X 12000mm Length mm X 16mm Thick = 3.617 Tones
Trang 91500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Trang 111500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Trang 12Isometric view of foundation after erection of I beams
Close up view of foundation, I Beams and bottom plate
Trang 131500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Erection, fit up and welding of bottom plate segments
Erection of 1 st shell plate on bottom plate
Trang 151500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Complete erection, fit up & vertical welding of 5 th shell
Erection of 6 th shell plate on 5 th shell by conventional method
Keeping vertical joints plates adjoining courses a minimum of 600mm apart
Trang 16Complete erection, fit up, vertical & horizontal welds of 6 th shell
Erection, fit up, welding of spiral stair case for the shells completed
Erection, fit up, welding of Baffles and stair case subjected to availability of material for 5 th & 6 th
shells
Trang 171500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Erection fabrication of Tank Roof before jacking
Trang 18Lifting of 5 th & 6 th shells by hydraulic jacks
Trang 191500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
4 th shell 1 st plate erection, alignment on bottom plate
Trang 204 th shell 2 nd plate fit up
Complete erection, fit up and vertical welding of 4 th shell
Jockeying down the 5 th shell to align with the 4 th shell, fit up and completion of horizontal welding
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and
approval for 4 th shell
Trang 211500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Lifting of 4 th shell for 3 rd shell erection
Erection of 3 rd shell first plate
Trang 22Erection fit up of 3 rd shell 2 nd plate
Complete erection, fit up and vertical welding of 3 rd shell plates
Trang 231500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Jockeying down to align top shells with 3 rd shell, horizontal welding of 4 th & 3 rd shells
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and
approval for 3 rd shell
Lifting the 3 rd shell for 2 nd shell erection
Trang 24Erection of 2 nd shell first plate
Complete erection, fit up and vertical welding of 2 nd shell
Trang 251500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Jockeying down for alignment, fit up & horizontal welding between 2 nd shell & 3 rd shell
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and
approval for 2 nd shell
Lifting 2 nd shell for 1shell erection and fit up
Trang 26
1 st shell first plate erection, fit up
1 st shell complete erection, fit up & vertical welding of shell
Trang 271500 MTPD Phosphoric Acid plant
4500 MTPD Sulphuric Acid plant METHOD STATEMENT
Jockeying down 2 nd shell to align, fit up and horizontal welding of 2 nd shell and 1 st shell
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and
approval
Fillet welding of bottom plate to 1 st shell