Progress Update (Nr 4) Week ending 6th November Programme Update - ITS For Period : Mon 26th October – Friday 6th October - Completed excavations, reinforcement and formwork to perimeter retaining walls - Completed installation of reinforcement to basement slab and concrete pour - Commenced installation of holding down bolts in preparation for steelwork - Completed internal damp-proofing works to basement walls - Commenced internal builders work and the removal of remaining load bearing walls: including installing necessary concrete lintels - Continue first fix mechanical and electrical works within existing building to all floors Progress Photos – External Basement floor slab & lift pit concrete pour complete Progress Photos – External Retaining wall steelwork reinforcement installed throughout perimeter walls Progress Photos – External Retaining wall formwork/shuttering installed and also temporary props positioned in preparation for next phase concrete pour Progress Photos – Internal First fix mechanical and electrical works continued within the existing building through all floors Progress Photos – Internal Internal structural builderswork ongoing including installation of load bearing lintels Progress Photos – Internal Commenced infill of new plasterboard ceilings to rooms and corridors throughout floors Next Few Weeks……… A look ahead to works commencing within the next weeks : - Complete excavations to new ground floor slab and pad foundations - Complete concrete pours to perimeter retaining walls - Commence ‘making good’ to walls within rooms of existing building - Commence self level screeding and preparatory overboarding to existing sub-floors - Continue internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors .. .Progress Update (Nr 4) Week ending 6th November Programme Update - ITS For Period : Mon 26th October – Friday 6th October - Completed... mechanical and electrical works within existing building to all floors Progress Photos – External Basement floor slab & lift pit concrete pour complete Progress Photos – External Retaining wall steelwork... continued within the existing building through all floors Progress Photos – Internal Internal structural builderswork ongoing including installation of load bearing lintels Progress Photos – Internal