1. Trang chủ
  2. » Ngoại Ngữ

ITS building project progress update 5

11 70 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 11
Dung lượng 5,79 MB

Nội dung

Progress Update (Nr 5) Week ending 20th November Programme Update - ITS For Period : Mon 9th November – Friday 20th November - Completed reduced level dig to to new ground floor slab and pad foundations - Completed concrete pours to perimeter retaining walls and stripped formwork - Commenced ‘making good’ to walls within rooms of existing building - Completed self level screeding and preparatory overboarding to existing sub-floors - Continued internal builders work; including installing required lintels and steelwork - Continued first fix mechanical and electrical works within existing building to all floors Progress Photos – External Basement retaining walls poured and formwork stripped Progress Photos – External Bolt boxes made and cast in preparation for steelwork installation Progress Photos – External Pad foundations excavated and DPM/reinforcement installed prior to concrete pour Progress Photos – Internal First fix mechanical and electrical works continued within the existing building through all floors Progress Photos – Internal Temporary propping system installed to facilitate installation of internal load bearing steelwork Progress Photos – Internal Continued infill of new plasterboard ceilings to rooms throughout floors within existing building Progress Photos – Internal Completed overboarding of existing sub floors to rooms throughout Progress Photos – Internal Commenced ‘making good’ to rooms within existing building including wallpaper strip and localised filling of holes etc Next Few Weeks……… A look ahead to works commencing within the next weeks : - Complete concrete pour to pad foundations - Complete external drainage works including new manhole and channel drainage - Backfill and compact surrounding areas with Type stone - Commence external steelwork installation - Continue overboarding existing ceilings to all floors within existing building - Complete internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors [...]... stone - Commence external steelwork installation - Continue overboarding existing ceilings to all floors within existing building - Complete internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors ... existing building Progress Photos – Internal Completed overboarding of existing sub floors to rooms throughout Progress Photos – Internal Commenced ‘making good’ to rooms within existing building. .. within the existing building through all floors Progress Photos – Internal Temporary propping system installed to facilitate installation of internal load bearing steelwork Progress Photos – Internal... mechanical and electrical works within existing building to all floors Progress Photos – External Basement retaining walls poured and formwork stripped Progress Photos – External Bolt boxes made and

Ngày đăng: 27/11/2015, 12:40

w