Progress Update (Nr 5) Week ending 20th November Programme Update - ITS For Period : Mon 9th November – Friday 20th November - Completed reduced level dig to to new ground floor slab and pad foundations - Completed concrete pours to perimeter retaining walls and stripped formwork - Commenced ‘making good’ to walls within rooms of existing building - Completed self level screeding and preparatory overboarding to existing sub-floors - Continued internal builders work; including installing required lintels and steelwork - Continued first fix mechanical and electrical works within existing building to all floors Progress Photos – External Basement retaining walls poured and formwork stripped Progress Photos – External Bolt boxes made and cast in preparation for steelwork installation Progress Photos – External Pad foundations excavated and DPM/reinforcement installed prior to concrete pour Progress Photos – Internal First fix mechanical and electrical works continued within the existing building through all floors Progress Photos – Internal Temporary propping system installed to facilitate installation of internal load bearing steelwork Progress Photos – Internal Continued infill of new plasterboard ceilings to rooms throughout floors within existing building Progress Photos – Internal Completed overboarding of existing sub floors to rooms throughout Progress Photos – Internal Commenced ‘making good’ to rooms within existing building including wallpaper strip and localised filling of holes etc Next Few Weeks……… A look ahead to works commencing within the next weeks : - Complete concrete pour to pad foundations - Complete external drainage works including new manhole and channel drainage - Backfill and compact surrounding areas with Type stone - Commence external steelwork installation - Continue overboarding existing ceilings to all floors within existing building - Complete internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors [...]... stone - Commence external steelwork installation - Continue overboarding existing ceilings to all floors within existing building - Complete internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors ... existing building Progress Photos – Internal Completed overboarding of existing sub floors to rooms throughout Progress Photos – Internal Commenced ‘making good’ to rooms within existing building. .. within the existing building through all floors Progress Photos – Internal Temporary propping system installed to facilitate installation of internal load bearing steelwork Progress Photos – Internal... mechanical and electrical works within existing building to all floors Progress Photos – External Basement retaining walls poured and formwork stripped Progress Photos – External Bolt boxes made and