S.O.P FINAL AUDIT FLOWCHECK GARMENT FOLDING METHOD CHECK THE APPROVED SHADE BANDS CHECK TICKETS & TAG CHECK P.P.. CHECK UNDER“MACBETH” LIGHT BOX COLOR CONTINUITY ON WHOLE SAMPLE LOT SAME
Trang 1S.O.P Final Inspection Certification
Program (Training Manual)
Prepared By: Technical Service Team
Leo ChanRavi HurPaulStephen ZhouPrashant Pattam
Trang 25/30/2010 2
• Revision History
3/20/2007 PAGE 5,16,62
S.S.C REVISED
5/30/2010 Page 6, add “critical areas” for 2 points
S.S.C Revised
Date Summary Of Changes
Author Issue
Trang 3PART (1) CLASS TRAINING
Trang 45/30/2010 4
1 The Flow of
“S.O.P Final Audit”
Trang 5S.O.P FINAL AUDIT FLOW
CHECK GARMENT FOLDING METHOD
CHECK THE APPROVED SHADE BANDS
CHECK TICKETS
&
TAG
CHECK P.P & TOP SAMPLE CONSTRUCTION IN/OUT SIDE
CHECK P.P SAMPLE
& TOP SAMPLE COMMENTS
LAB TEST REPORT
1 Please clarify with Mast office related Person/department if any information is Not clear, no approval signature,
or does not make sense.
2 Ask your supervisor if the information appears confusing Do not assume.
CHECK
IN LINE REPORT
Trang 6CHECK UNDER
“MACBETH”
LIGHT BOX
COLOR CONTINUITY
ON WHOLE SAMPLE LOT
SAME FABRIC DIRECTION
1 LABEL THE OFF SHADE SAMPLE FOR END RESULT COUNT.
2 CARRY ON THE FOLLOWING PROCESS
TAKE MEASUREMENT
ACROSS COLOR/SIZE
1 LABEL THE “O.O.T.” SAMPLE(S) FOR REVIEW AND FOR END RESULT COUNT.
2 THE SHIPMENT SHOULD BE REJECTED IF “O.O.T”
6% ON KEY POINT.
3 CARRY ON THE PROCESS.
SAMPLE PLAN FOR MEASUREMENT FOLLOW THE S.O.P.
MANUAL REQUIREMENT
FOLLOW THE RIGHT WAY OF MEASURING.
CRITICAL AREAS
- LEARN THE MEASURING METHOD BY MEASURING
THE PP SAMPLE FIRST
-Measure In-line sample & keep record.
BOTTOMS: TWISTING (LEG) HIKING (SEAMS,FRONT/BACK), HIPS LARGER OR SMALLER THAN
STANDARD
TOPS: UNBALANCE, OVER EASING,OVER STRETCHING, SLEEVES,NECKLINES,SHOULDERS, BODICE.
1 LABEL THE DEFFECTIVE SAMPLE(S) AND LOCATION FOR END RESULT.
2 CARRY ON THE PROCESS.
Trang 7END RESULT
NO MATTER THE RESULT “ACCEPT” OR “REJECTED”,MAST QA SHOULD TAKE THE FOLLOW
ACTION:
1 REVIEW ALL DEFECTIVE SAMPLES WITH FACTORY RESPRESENTATIVE
2 MAST Q.A AND FACTORY RESPRESENTATIVE HAVE TO SIGN THE REPORT, TO
ACKNOWLEDGE THE END RESULT.
3 IF THE FACTORY RESPRESENTATIVE DISAGREES WITH THE END RESULT IS “REJECT”, THE
DISAGREEMENT HANDLING BY MAST Q.A SHALL BE:
A TAKE PHOTOS OF THE DEFECTIVE SAMPLES.
B SEND THE REPRESENTATIVE DEFECTIVE SAMPLES TO MAST OFFICE./Q.A.MANAGER AND
AWAIT FOR THE FINAL DECESION.
4 BASED ON THE DECESION ENTER THE FINAL END RESULT INTO THE T.S WEB.
CHECK ALL SEAMS
POCKET BAG IN//OUTSIDE
LINING TURN INSIDE OUT
CHECK ACCESSORIES
BAD SMELL
HAND FEEL
1 LABEL ALL THE DEFECTIVE SAMPLE FOR FINAL REVIEW.
2 IDENTIFY “MIN” & “MAJ” FOR END RESULT COUNT.
3 CARRY ON THE FOLLOWING PROCESSING.
Trang 85/30/2010 8
2 Audit Preparation
Trang 9• Must be a proper audit work room with minimum size of 30 square meters, not a
conference room nor inside of the office.
• All walls covered by white board.
• Floor color must be painted “dark grey” or “black” not light color.
• Well lighted, without window (not being affected by outside daylight or other light
sources).
• ‘MACBETH’ light box should be set in small room (or separate compartment) of the audit area, closed with wooden door (or black opaque curtain) to keep away all light sources.
• Air-conditioned.
the inspection room view (1) the inspection room view (2)
2.1 Audit work area standard.
Trang 105/30/2010 10
2.2 Standard of audit room facilities
PC (Mast standard),
Printer, FAX
Lighting and Temperature Condition
.Range 110-120 candle light
.C.W.F light tubes placement should be under ceiling and 12” away from the edge of
inspection table
C.W.F light tubes model
Brand: PHILIPS Model # TLD 36W/33
.Temperature: Around 18 C – 24 C
.Humidity: Around 40 – 70%
.With A/C and IDD plug for internet connection Or I.Pass Mast specification
The light tubes
Trang 112.2 Standard of audit room facilities
Inspection Table and QC Chair
.Table color in mid-grey with dull surface
.Table size: H34 1-/2” x W48” x L96” x T1-1/2”, with edge surrounded by solid wood and
smooth surface
.4-tables component preferred - big enough to lay bulk samples for testing
.High stand and high back QC chair, removable and adjustable
Trang 125/30/2010 12
2.3 Audit Tool
• 2.3.1 Ball pen.
• 2.3.2 Soft measuring tape
for woven, cut & sew
(ensure the sticker does
not leave any mark on the
garment)
• 2.3.6 Inspection report for
Final Audit.
Trang 133 S.O.P Audit Procedures
Trang 145/30/2010 14
3.1 Selection of samples and cartons (at least8%)
a/ The sample cartons for audit should be randomly selected from different
location & pallet from the storage areas.
b/ The garment samples for audit should be randomly selected from the
different layers of carton.
c/ MAST q.c should escort the selected cartons and samples to the
designated audit area/room.
d/ If the packing list is temporary or not available, the auditor must select carton available randomly and should not just take cartons which are conveniently accessible.
e/ Carton number shall be called out randomly across sizes & colors according
to factory temporary packing list.
f/ Upon the completion of 95% of the goods packed into carton , the order can
be taken for final inspection.
Trang 153.2 Q.C inspection file check.
3.2.1 VPO
Trang 16order to know the type
of defects that were
found
Trang 173.2.3 Accessory Card
Trang 185/30/2010 18
3.2.4.Approved Shade Band
Trang 193.2.5 Lab Test
Trang 20Folding Instructions
Measurement
Trang 225/30/2010 22
3.2.6(c) Tech Pack- PANTS
Style DiagramConstructionConstruction detail
Trim & Color
Labeling PositionLabeling Requirement
Measurement
Folding Instructions
Trang 233.2.6(d) Tech Pack-PANTY
Style Diagram
Construction Details
Folding Instructions
Measurement
Measurement Grading
Trang 253.3 Review the approved P.P sample
(comments, fitting and construction).
Trang 273.4.2 Check shipping mark.
Trang 285/30/2010 28
3.4.3 packing method & units in carton.
Trang 293.5 Check garment presentation ( packed & unpacked).
Trang 305/30/2010 30
3.6 Check color shade.
3.6.1 Color continuity (garment to garment).
Trang 313.6.2 Color shading (within a garment).
Trang 325/30/2010 32
3.7 Check garment measurement and record exactly what you have observed.
Follow the measurement sampling chart.
If over 6% of garments where the key
point(s) are out of tolerance of the total
sample measured, the audit is failed (for
example, 3 pieces out of 50 pieces, result
is “pass”, 4 pieces or more, result is “fail”.
Trang 333.8 Check the fit and balance of garment.
Trang 345/30/2010 34
Fitting-Unbalance
Trang 35Fitting-Over stretching
Trang 365/30/2010 36
Fitting-Twisting
Trang 37Fitting-Hiking at Back
Trang 385/30/2010 38
Fitting-Armhole Bulky
Trang 39Fitting-Wide Neckline
Trang 405/30/2010 40
Fitting-Bodice Edge Curling
Trang 41Fitting-Hem Rise and High Low Vent
Trang 425/30/2010 42
Fitting-Off Shape at Placket
Trang 43Fitting-Low Hip Big Ear (front view)
Trang 445/30/2010 44
Fitting-Low Hip Big Ear (side view)
Trang 453.9 Check workmanship and visual
defects.
(i) For sampling, please follow the brands’ requirement
(ii) For AQL standardized, refer to standardized S.O.P manual (iii) Visual audit definition Which means visible to the eyes.
Examples of defective garments (iiii) For audit regulation, please follow standardized S.O.P
manual.
Trang 465/30/2010 46
3.10 Marking defects properly for.
(i) Color shade garment(s) off standard.
(ii) O.O.T (out of tolerance/measurement) (iii) Visual defects (workmanship /
construction / accessories etc.)
Trang 47Marking Defects
In case you are advised to take digital photo
or send defective garment to your supervisor
or merchandiser for further review during final/in line inspection, the defective sample should be marked properly per following instructions
Trang 485/30/2010 48
Ensure sticker/label size is big enough to write down
Remark: Finally, do not forget to put your signature and
inspection date on sticker/label
Trang 49Example of marking color shade Defect
Trang 505/30/2010 50
II Mark Measurement Defect
Ensure sticker/label size is big enough to write
down information below :
• Description of Measurement Defect
Remark: Finally, do not forget to put your signature and
inspection date on sticker/label
Trang 51Example of marking measurement Defect
Trang 525/30/2010 52
III Mark Visual Defect
• Use arrow sticker to mark defect
• Mark arrow to the direction of defect
• Avoid arrow sticker covering the defect
Proper distance should be maintained
between sticker and defect
Trang 53Workmanship(1) - Mis-matched
Trang 545/30/2010 54
Workmanship(2) – Sewing Defect
Trang 55Construction
Trang 565/30/2010 56
Fabric Defect
Trang 57Accessories
Trang 585/30/2010 58
3.11 Issue Audit Report.
(a) Clear & clean.
(b) Visualable & recognized.
Trang 593.12 Disagreement Handling.
In case of disagreement raised during final inspection, please keep calm
and do not get excited and be influenced by factory personnel You should look for help from your direct supervisor/manager if you are unsure Please followed the instructions below when dealing with this type of situation
1 Report to your supervisor/manager the inspection results with
• The order details
• Which color has problem
• What is the defect
• The rejection details
2 Take the digital photo and send to your supervisor/manager if looking
for help The photo must be clear and visible on the defect.
Trang 605/30/2010 Attached 1:The pattern 60
3 The information must be one pattern (see attached 1)
Trang 614 Do not hesitate to consult your supervisor/manager if in doubt.
5 Marginal Shipment - if final inspection failed due to a minor flaw, you should refer the (ship no ship) decision to the technical manager And all conversation / discussion / decision with merchandising
department or technical manager should be recorded on report.
Trang 625/30/2010 62
3.13 Final Inspection Result
Data Input
Trang 633.13.1 The Website
Trang 645/30/2010 64
3.13.2 enter the “Username” & “Password”
Trang 653.13.3 the Main Window
Trang 665/30/2010 66
(1).Click the “Final Inspection” ,Select the “Final Inspection New”.
3.13.4 Final Inspection