KHÓA ĐÀO TẠO TÍNH TOÁN ỔN ĐỊNH VÀ HƯỚNG DẪN SỬ DỤNG PHẦN MỀM PSSE CHO KỸ SƯ HỆ THỐNG ĐIỆN (Kịch bản nghiên cứu theo tiêu chuẩn IEEE trên Phần mềm PSSE): • Saved Case Buildup. • Creating a Single Line Diagram. • Load Flow Analysis. • N1 Contingency Analysis. • ShortCircuit Analysis.
Trang 1Day 12 - Case Study – IEEE 24 Bus Test System
PART 1
July 19, 2013 Prepared by: Frida Ceja-Gomez
Trang 2• Saved Case Build-up
Creating a Single Line Diagram
• Creating a Single Line Diagram
• N-1 Contingency Analysis
• Short-Circuit Analysis
Trang 3IEEE 24 – SAVED CASE
IEEE 24 – SAVED CASE
BUILD-UP
Trang 4• The purpose of this exercise is to build a test case from p p
scratch on PSS®E and then perform all the types of
analysis covered during Part A of this course
Reliability Test System 1996
select Network Case
Trang 5• Leave the MVA Base as 100 and the frequency as 60Hz
• We will input the transformer ratings in MVA units
For non transformer branches the current will be expressed as
• For non-transformer branches the current will be expressed as
MVA
• The heading lines are just to provide some information about g j p
Trang 6• Use the following g
bus data as an
input
of each bus type
Trang 7eBook for You
Trang 8• Our test system has 10 generators y g
generator
Trang 9Enter RTran = 0 015pu and Xtran = 0 125pu for all machines
• Enter RTran = 0.015pu and Xtran = 0.125pu for all machines
• These values are the step-up transformer impedance in pu on Mbase
• Leave Gentap = 1, which is the transformer off-nominal turns ratio in pu on
the system base
• PSS®E assumes the GSU transformer has a delta-wye configuration as PSS®E assumes the GSU transformer has a delta wye configuration, as
Trang 10• Add the following loads to their respective buses g p
Trang 11Th IEEE 24 h h fi 230 138kV
transformers shown below
configuration on both sides
Trang 12• We will add an on-load tap changer to the two-winding
transformers
• The information for the OLTC of our 5 two-winding
transformers is shown below:
• Controlled Bus: LV side
Trang 13• The system only has one fixed shunt
capacitor
Trang 14IEEE 24 – CREATING A SINGLE
IEEE 24 – CREATING A SINGLE
LINE DIAGRAM
Trang 15• Go to the File
menu, click on
New and select
Diagram
Draw option and
Trang 21• Now let us grow g
Trang 23• Finally, grow
Bus 22 one
level
• Now that we
have all the
have all the
Trang 24• In the Diagram In the Diagram
Trang 25• In the Diagram tool In the Diagram tool
menu, use the Title
and Lgnd buttons
to add information
to the diagram
color and size can
Trang 26• Also in the Diagram g
tool menu, the
can add all the bus
can add all the bus
Trang 27• This is how the
Trang 28IEEE 24 – LOAD FLOW
IEEE 24 – LOAD FLOW
ANALYSIS
Trang 29been built, run the load flow analysis
• Verify the output bar to make sure that the simulation
converged
• Why is there a star (*) to the right of the swing bus QGEN?
Trang 30set flags for limit violations in the single line diagram
• Right-click on the diagram and select Diagram Annotation,
where you can enable the option to check line loadings and
voltage limits
Trang 33• Under the Power Flow, Reports, Limit checking reports
menu select the Voltage limits option
Trang 34• Under the Power Flow,
Reports, Limit checking
reports menu select the
reports menu, select the
Branches option
Trang 35• Reliability criteria may vary depending on the utility
contingencies shall typically fulfill the following
conditions
• There shall not be any overloads present
• There shall not be any buses with voltages higher
than 1.05 pu
• There shall not be any buses with voltages lower than
0.95 pu
that the above criteria is satisfied
Trang 36• It will be necessary to modify the transformers
ratings
• Note that it is not necessary to modify the y y
resistance/reactance since these parameters
were input with respect to the winding MVA
base which has not been modified
Trang 37• To address the low voltage at buses 3 and 24, it
will be necessary to add a reactive
Trang 38• To address the low voltage at buses 4, 5, 6, 8, 9,
10, 11 and 14, another reactive compensation
device will be needed
• Place a fixed shunt capacitor of 115 MVAR at
bus 10
• Once these changes have been made, run the
load flow simulation again
Trang 40• Although the overloads and low voltage issues have been g g
resolved, it can be seen that the swing machine is still
running above its reactive power limit
Trang 41• To correct this problem, we need to increase the scheduled voltage at
nearby PV buses to encourage other machines to increase their reactive
power output
• Set the scheduled voltage at bus 23 to 1.03pu and re-run the simulation g p
Trang 43S N 1 t k l it ti t
• Some N-1 cases may take several iterations to converge,
so it is useful to increase the number of allowed iterations
Trang 44• Write a subsystem file defining the whole
system as well a subsystem for each area
Trang 45• Write a monitoring file to monitor
Trang 46• Write a contingency file to trip each of
branches in the system, one at a time
Trang 47• Go to AC contingency solution (ACCC) and
build the distribution factor data file
Trang 48• Verify the output bar for any problems with
the distribution factor file
• Note that one of the contingencies isolates a
bus
Trang 49• Name the contingency solution output file
• Name the contingency solution output file
and solve
Trang 52• How many contingencies cause line
Trang 53• What lines should be upgraded to avoid
major overloads?
• Where should more lines be built to
prevent excessive overloads?
• Is it necessary to add more reactive
power compensation to keep the
voltage within acceptable limits? If so,
where?
Trang 54• When it is not possible to add or
upgrade lines, it is necessary to
develop operational measures to
develop operational measures to
protect lines and other equipment from
high overloads
• What remedial action schemes would
you implement for the safe operation of
this system?
Trang 56• When we built the IEEE 24 Test System,
there was no input data for the zero p
sequence parameters
• Although it is always preferable to input Although it is always preferable to input
true system data, as power system
planners, we can make some
assumptions when the negative and
assumptions when the negative and
zero sequence parameters are not
available
Trang 57• As discussed in the Introduction to PSS®E training and
with the aid of an Excel spreadsheet, generate these
parameters using the following assumptions:
• Negative-sequence impedance is equal to
positive-sequence impedance for all equipment
• Zero-sequence impedance of generators is equal to ¼
of positive-sequence impedance
• Zero-sequence impedance of transformer is equal to
positive-sequence impedance
• Zero-sequence impedance of lines is equal to three
• Zero-sequence impedance of lines is equal to three
times the positive-sequence impedance (B0 = ½ B1)
Trang 58• This activity allows to perform
short-circuit analysis on our test system by y y y
applying a fault at the specified bus(es)
• Before we begin, it will be necessary to Before we begin, it will be necessary to
modify some program settings so that
our short-circuit analysis results are
more meaningful
Trang 59• Go to the Misc menu,
and select Change
Program Settings
• Change the
short-circuit output to
Physical and the
Physical and the
magnitude and angle
Trang 60• Go to the Fault menu
and select the ASCC
and select the ASCC
option
• Set the pre-fault
diti th li conditions as the linear
power flow
• Choose to analyze
three-phase and
line-to-ground faults
• Select the output as Select the output as
Fault current summary
table
• Select all buses and
• Select all buses and
click Go
Trang 62QUESTIONS?
Trang 63WE CARE about the health and safety of our employees, of those who work under our care, and
of the people our projects serve.
WE CARE about our employees, their personal growth, career development and general
well-WE CARE about our employees, their personal growth, career development and general well
being.
WE CARE about the communities where we live and work and their sustainable development, and we commit to
fulfilling our responsibilities as a global citizen.
fulfilling our responsibilities as a global citizen.
WE CARE about the environment and about conducting our business in an environmentally responsible manner.
WE CARE about the quality of our work.