Risk Breakdown Structure 8 1.2.2, RBS Coding table: 9 CHAP 2: RISK ASSESSMENT.. Conditions for Impact Scales of a Risk on Major Project Objectives...11 2.1.2.. LIST OF PICTURES, TABLES A
Trang 1TON DUC THANG UNIVERSITY FACULTY OF BUSINESS ADMINISTRATION DIVISION OF DEPARTMENT OF ECONOMICS
ĐẠI HỌC TÔN ĐỨC THẮNG
TON DUC THANG UNIVERSITY PROJECT MANAGEMENT SUPERVISOR: LE PHUOC LUONG TOPIC: LAUNCHING INKWELL'S "CHRISTMAS AND NEW YEAR
WITH INKWELL" PROJECT
Lecturer: Le Phuoc Luong Examiner | (Signature &
Submission date: 13/10/2023 Fullname)
Examiner 2 (Signature &
Trang 2
TON DUC THANG UNIVERSITY FACULTY OF BUSINESS ADMINISTRATION DIVISION OF DEPARTMENT OF ECONOMICS
DAI HOC TON ĐỨC THẮNG TON DUC THANG UNIVERSITY
PROJECT MANAGEMENT TOPIC: LAUNCHING INKWELL'S "CHRISTMAS AND NEW YEAR WITH
INKWELL" PROJECT SUPERVISOR: LE PHUOC LUONG
2 Văn Thị Thùy Trang 721K0394
3 _ | Trần Lê Thanh Tuệ 721K0456
4 | Nguyễn Trần Đông Quân 720K0982
5 | Phan Ngọc Hải Triều 721K0258
Trang 3ACKNOWLEDGMENT First and foremost, our team would like to extend its sincere gratitude and admiration to Mr Le Phuoc Luong He was an ardent advocate and offered detailed advice on the project's development and study direction, as well as advice on the right method, content presentation, direction to take, and analysis of the research presented He made this decision using his very valued skills and research experience This allows us to learn and study in the best way possible
The second thing our team would like to do is thank the Ton Duc Thang University Department of Business Administration for providing us with the opportunity and ideal conditions to research and assess the project We greatly appreciate it
Trang 4LIST OF GROUP MEMBERS AND EVALUATION
Trang 6
TABLE OF CONTENTS
1.1 Risk Management Process 7 1.1.1 Definition of Risk Management Process 7 1.1.2 Benefits of Risk Management Process 7 1.1.3 Risk Management Process 8
1.2 Step 1: Risk Identification 8 1.2.1 Risk Breakdown Structure 8 1.2.2, RBS Coding table: 9 CHAP 2: RISK ASSESSMENT lI 2.1 Step 2: Risk Assessment 11
2.1.1 Conditions for Impact Scales of a Risk on Major Project Objectives 11 2.1.2 Risk Severity Matrix 12 2.2 Risk Assessment Form 13
CHAPTER 3: RISK RESPONSE DEVELOPMENT AND CONTINGENCY
3.5 Step 4: Risk Response Control „ 30 3.5.1 Monitoring, tracking, and reporting risk 30 3.5.2 Fostering an open organizafion enVir0nIM€TIÍ 5 «<< « «ss== 30 3.5.3 Repeating risk identification/Assessment EXer€iS€S - 30
Trang 73.5.4, Assigning and documenting responsibility for managing risk
3.6 Change control management
3.7 Change Log Request CHAP 4: CONCLUSION
38 39
Trang 8LIST OF PICTURES, TABLES AND FIGURES
Table 1: RBS Coding
Table 2: Risk Assessment Form
Table 3: Risk Response Development and Contingency Planning
Table 4: Inkwell’s Contingency Fund Estimate
Table 5: Inkwell’s time buffers for important activities
Table 6: Risk Register
Table 7: Change Log Request
Figure 1: The Risk Breakdown Structure
Pic 1: Change control process 36
Y
CHAP 1: MANAGING RISK 1.1 Risk Management Process
Risk measures the probability and impact of failing to meet a specific project goal Risk affects an individual, organization, or project by an event or circumstance with loss, uncertainty, and negative consequences Risk has two primary components for a given event:
® The probability of occurrence of that event
¢ The impact (or consequence) of the event occurring
Risk increases with threat but decreases with protection This means that good project management should be able to identify hazards and develop a safeguard to get over them A suitable safeguard can reduce the level of risk
1.1.1 Definition of Risk Management Process
Risk management is the process of handling risks It involves preparing for risk, identifying, analyzing, creating plans for responding to risks and tracking and managing risks to see how they have changed The risk management process needs to clarify the following issues:
¢ What risk can occur?
¢ How to decrease the effects of the risk event
¢ What may be done in anticipation of an event
Trang 9® What to do in the case of an occurrence (contingency plans)
The method to create a strong RMP is to include all the details the program team will need to understand the program's objectives, goals, tools, reporting, communication processes, organizational roles, and responsibilities necessary to achieve effective risk management The RMP _ should include suitable risk management definitions, guidelines, and presumptions, as well as potential risk categories, methodologies for identifying and analyzing risks, organizational structures for managing risks, and documentation that is appropriate
1.1.2 Benefits of Risk Management Process
Effective risk management aims to raise the possibility of project success by acting proactive rather than reactive, and positive rather than negative The risk management process allows project managers valuable time to develop contingencies Improve the chances of factors such as cost, performance, and progress meeting the requirements Therefore, proper risk management attempts to reduce the likelihood of
an event occurring and its severity as well as increase the likelihood of project success
1.1.3 Risk Management Process
The Risk Management Process includes 4 steps:
® Identify Risk: Analyzing and examining each important technical process and the program areas to find and record any potential risks
e Risks Assessment: The process of analyzing each risk that has been recognized to determine its likelihood, the severity of its effects on the project, and how to control it
e Risk Response Development: The procedure that discovers, analyzes, and develops one or more solutions to lower risk to a manageable level given program restrictions and objectives and creates contingency plans This covers the details of what has to be done, when it needs to be done, who is responsible, and the costs and timeline involved
¢ Risk Response Control: A process that performs risk management, monitors and evaluates the effectiveness of risk response measures, and provides inputs for adjusting risk management and plans
Trang 101.2 Step 1: Risk Identification
1.2.1 Risk Breakdown Structure
{Txtreme wenther]
Figure 1: The Risk Breakdown Structure The risk breakdown structure started with level 0 - The project name: Inkwell Project Risks This is followed by the categories of risk: Project Management, External, Technical, and Organization Level 2 of the RBS is the risk of the project and level 3 is the actual risk
RBS Level 1 Level 2 Level 3
Trang 11
Poor concept generation 3.1.1 Design
Design product unqualified 3.1.2 Quality Product not meeting standard 3.2.1
Inefficient tool usage 3.3.1 Facilities
Inaccurate tool usage 3.3.2 Technical Hardware 3.4.1
Feasibility Software 3.4.2
Lack of motivati 4.1.1 Staff ack of motivation 1
H
_— turnover 4.1.1 Resource Conflict 2
Manpower shortage 4.1.2
Poor team communication and coordination 4.2.1 Team
Team inexperience 4.2.2 Unsatisfied planning 4.3.1 Process Poor execution 4.3.2
Lost control 4.3.3
lable 1: RBS Coding
Trang 12CHAP 2: RISK ASSESSMENT
2.1 Step 2: Risk Assessment
2.1.1 Conditions for Impact Scales of a Risk on Major Project Objectives Impact scales are used to objectively or qualitatively analyze the probable impact
or consequences of particular risks on important project objectives Project managers and other stakeholders can use these scales to assess possible risks' seriousness and decide on risk management and mitigation measures The impact scale of risk will include:
e The probability that the risk will occur with some notable impact on the project The project manager needs to determine which probability will be given a score from very low to very high
® Project managers must set definitions of impact in terms of very low, low, medium, high, and very high impact levels according to objectives (time, cost, scope, and quality)
The Probability Measurement:
II
Trang 13; Less than 1 1-2
Time Time 2 - 4 months than 4
; month months
increase months Scope Major Scope Project
P Minor Areas 1 Ps 1 ; Decreases Areas of Reduction | End Item is
Scope of Scope
are barely Scope Unacceptable | Effectively
Affected Noticeable Affected | to Customer Useless
Quality Quality Only Very ; Quality Project
Reduction Degradation | Demanding ; Reduction | End Item is Quality , Requires ;
Barely Applications Unacceptable | Effectively Customer
Noticeable | are Affected to Customer Useless
Approval
2.1.2 Risk Severity Matrix
A probability and impact matrix 1s a technique used in qualitative risk analysis to assess the possibility and consequences of identified risks It uses a numerical scale to rank the likelihood and impact of each risk, which may be used to prioritize risks and create plans to reduce or manage them The probability-impact matrix's results can be compared to the performing organization's risk-reaction guidelines The performing organization can categorize the risk according to its risk score to direct its response to risk Based on the risk score, there are three typical categories:
Red zone: These high-risk ratings have a high likelihood and impact Yellow zone: These risks have a somewhat high impact and likelihood Green zone: These risks typically have a low impact, probability, or both
Trang 14¢ Ascore of less than 5 shows a low risk for the given target
® A yellow or moderate risk to the objective is indicated by any score between 5 and 10
e Any score greater than 10 indicates a red or severe risk to the goal
2.2 Risk Assessment Form
Likelihood | Impact When
code difficulty Rating
L111 3 5 1 Project initiation 1.2.1.1 2 5 2 During estimation 1.2.2 2 4 4 Market research 1.2.3 1 3 4 Market research 2.1.1.1 2 4 2 Sourcing 2.1.1.2 3 4 2 Distribution 2.1.1.3 1 5 4 Sourcing 2.1.2 2 4 5 Sourcing
Products are 2.2.1.1 3 2 5
launched
Products are 2.2.1.2 3 3 4
launched 2.2.2 1 3 5 Market trends
Trang 15progress
Launching products During manufacturing Product designing phase Product designing phase Products are launched
Trang 17
CHAPTER 3: RISK RESPONSE DEVELOPMENT AND CONTINGENCY
realistic schedules Key planning ;
Add resources to Project with buffer time for milestones are
LLL critical path ; manager,
uncertainties TS consistently
1 activities to ; Leaders of Closely track missed or
co accelerate work departments progress indicators delayed
contingency funds discounts or will be
available scope reduction exceeded
significantly actions measures
1.2.3 Avoid: Develop Implement cost- Revenue Sale Dept
flexible pricing cutting measures figures strategies that can be | and efficiency consistently
adjusted based on | improvements to | fall short of the
market conditions maintain established
Trang 18profitability sales targets
Promote production of
; ; products and Logistics and ;
1 inventory in advance ; Supply Chain
change Supply Chain communication
plans Order extra
Transfer: Contact
inventory in
multiple suppliers Supplier | 2.1.1 advance and use ; Logistics and and apply penalty ; notifies of ;
2 alternative Supply Chain clauses for late ; delay
transportation
delivery in contracts ;
modes if needed Transfer: Employ a ; Logistics and
; | Activate backup ; ;
variety of suppliers Supplier Supply Chain, 2.1.1 supplier and } ; and have a safety ; notifies of Marketing
; ; ; Supply Chain supplier research suppliers materials
thoroughly quality
Avoid: Hire
designers who Offer Customer
2.2.1 understand and dissatisfied feedback
; ; Sales Dept
1 empathize with target customers indicates
customers and their incentives dissatisfaction
needs
Trang 19Mitigate: Conduct Reduce Market
regular market inventory and | analysis shows
2.2.2 | research and adjust | offer discounts significant R&D Dept
production and or promotions to change in
pricing accordingly clear stock demand
Mitigating: Diversify Activate Detect events
marketing channels alternate that affect Marketing
2.3.1
to mitigate marketing marketing Dept disruption channels campaigns
Deploy compliance team
to identify
required
Mitigate: Create
; operational
flexible plans and ;
; changes and | Notified by the Project 2.3.2 response scenarios
costs government manager for different
Accelerate any regulatory outcomes ;
redesign, process changes needed to comply
2.4.1 Avoid: Schedule Purchase Forecasts of Project
production and insurance to potential manager delivery in advance | cover losses due | severe weather
to avoid peak to weather- conditions that
Trang 20
disruptions operation
Implement Mitigate: Involve Stakeholder
; changes as stakeholders in the requests
; requested by design process and change or
3.1.1 stakeholders and R&D Dept
get their feedback expresses
document the ¬ ; and approval at each | | ; dissatisfaction
impact on time, - - stage with the design
cost, and quality Mitigate: Do Stakeholder prototyping, requests
; ; Revert to the simulations, change or 3.1.2 ; design stage to R&D Dept
analyzing and expresses
¬ ; resolve , ;
piloting to validate dissatisfaction
design with the design Avoid: Implement
robust quality ;
Determine root - assurance procedures ; Notified by ;
cause and adjust Manufacturing 3.2.1 | and inspection points ; quality
production ; Dept
throughout surveillance
; process manufacturing
processes
Mitigate: Provide
comprehensive Additional training programs on | safety training or| Notified by ;
¬ ; Manufacturing 3.3.1 proper tool usage, retraining for | manufacturing D
ept safety procedures, employees manager
and equipment involved
maintenance