project plan version learn english together

23 0 0
Tài liệu đã được kiểm tra trùng lặp

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Tiêu đề Learn English Together
Tác giả Ha, Le Thanh, Le Xuan Hieu, Ngo Ngoc My, Doan Trung Thong
Người hướng dẫn MSc Huy, Truong Dinh
Trường học International School, Duy Tan University
Chuyên ngành CMU-SE 451 – C2SE.12
Thể loại Capstone Project
Năm xuất bản 2021
Định dạng
Số trang 23
Dung lượng 1,52 MB

Nội dung

Team Organization: 2.1.Scrum Team Information: Table 1: Scrum Team Organization... PROJECT PLANInternational School - Capstone 2 – 2021 2.2.Role and Responsibility: Product OwnerUndersta

Trang 1

International SchoolCapstone Project 2 CMU-SE 451 C2SE.12 –

Project Plan Version 1.1 Date: March 20 , 2021 th

Learn English Together

Submitted by

Ha, Le Thanh Hieu, Le Xuan

My, Ngo Ngoc Thong, Doan Trung

Approved by MSc Huy, Truong Dinh

Proposal Review Panel Representative:

Capstone Project 2- Mentor:

Trang 2

Project acronym LET

Project Title Learn English Together

Lead Institution International School, Duy Tan University

Project Mentor MSc Huy, Truong Dinh

Scrum master /

Project Leader

& contact details

Ha, Le ThanhEmail: lethanhhadtu@gmail.comTel: 0334002818

Ha, Le Thanh lethanhhadtu@gmail.com 0334002818Hieu, Le Xuan xuanhieu.le.1999@gmail.com 0399706614

My, Ngo Ngoc ngongocmy851999@gmail.com 0764497391Thong, Doan Trung doanthong002@gmail.com 0886428208

Trang 3

Thong, Doan Trung

Student ID: 2321124144

Team Member

Trang 4

Title

Project Plan Document

2021

File name: C2SE.12_ProjectPlan_LET_ver1.0.doc

REVISION HISTORY

Version Person(s) Date Description

TABLE OF CONTENTS

1 Introduction: 6

1.1 Purpose: 6

1.2 Project Overview: 6

1.3 Project Deliverable: 6

2 Team Organization: 6

2.1 Scrum Team Information: 6

2.2 Role and Responsibility: 7

2.3 Communication Methodology: 8

2.4 Communication and Report: 8

3 Development Process: 9

4 Schedule and Cost: 10

4.1 Detailed Schedule: 10

4.2 Cost: 16

5 Project Risk: 17

6 Deliverables 18

Trang 6

Introduction:

1.1 Purpose:

This document provides a summary of the project's objectives, division of work,the major milestones, required resources, time and overall schedule and budgetallocation used and based on the document proposal to build a dating websiteapplication on time, at the request and plan

2.1 Scrum Team Information:

Table 1: Scrum Team Organization

MSc Huy, Truong

Hieu, Le Xuan 0399706614 xuanhieu.le.1999@gmail.com Member

My, Ngo Ngoc 0764497391 ngongocmy851999@gmail.com MemberThong, Doan Trung 0886428208 doanthong002@gmail.com Member

Trang 7

PROJECT PLAN International School - Capstone 2 – 2021

2.2 Role and Responsibility:

Product

Owner

Understanding users and customers:

o Research and understand the needs and desires of customers using hotel services

o Market analysis and tourism industry trends

o Identify problems and opportunities to improve customer experience

Collaborate with the development team:

o Clearly communicate feature and functional requirements of hotel-related products and services (for example: online booking system, mobile application for customers, )

o Participate in meetings and give feedback to the development process

o Provide necessary information and answer questions from the development team

Stakeholder management:

o Keep in touch and update information with relevant parties such as management, hotel departments, service providers,

o Resolve issues that arise between relevant parties

Describe user experience and product features:

o Sketch and preliminary design of customer experience when using hotel-related products and services

o Determine required features and prioritize development order

o Provide references and detailed instructions to the development team

Provide detailed user stories:

o Identify actual situations of customers when using products and services

o Describe the customer's actions and goals in each situation

o Provide detailed information to help development teams build products thatbest meet customer needs

Trang 8

Scrum

Master

Coach and support team members:

Scrum and Agile principles

daily work

related to Scrum

Organize Scrum meetings:

o Prepare and lead Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective meetings

o Ensure meetings are effective and on time

o Record and track results of meetings

Monitor project progress:

project progress

o Identify potential risks and problems

o Propose solutions to improve project progress

Promote a spirit of cooperation and communication:

environment for team members

among members

o Resolve conflicts within the group

Secretary Support hotel management work, including:

Schedule and arrange meetings and events

Record and store meeting minutes

Draft and send emails and letters

Manage records and documents

Answer phones and greet guests

Support other administrative tasks

Provide information and support to customers

Maintain professionalism and efficiency in work

Reviewer Rate the quality of hotel services:

o Conduct surveys, collect feedback from customers about hotel services such as reception, rooms, restaurants,spa services,

Trang 9

PROJECT PLAN International School - Capstone 2 – 2021

o Analyze and evaluate customer satisfaction with services

o Identify strengths and weaknesses and make recommendations to improve service quality

Evaluate hotel performance:

o Analyze data related to hotel business activities such as booking rate, revenue, costs,

o Evaluate the performance of hotel departments

o Identify problems and provide solutions to improve operational efficiency

Evaluate employee capabilities:

o Carry out periodic assessments of employee capabilities based on criteria such as knowledge, skills, service attitude,

o Classify and recommend appropriate training programs to improve employee capacity

Developer Developing hotel management

o Integrate necessary APIs and libraries

o Ensure software quality and performance

Software maintenance and updates:

o Fix errors and fix problems that arise

o Update software with new features

o Ensure the software always operates stably and effectively

Technical assistance:

o Support users in using the software

o Answer technical questions and issues

o Provide software usage documentation

Trang 10

Analyzer Collect and analyze data related to hotel

Report analysis results to hotel management and propose appropriate solutions

Support other departments within the hotel

to use data to make more effective decisions

o Perform test cases to check the features of the hotel management system

o Detect errors and record details

o Report errors to the development team and track bug fixing progress

Mentor - Guide on the process

- Monitoring all activities of Team

- Help with anything

MSc Huy, TruongDinh

2.3 Communication Methodology:

Table 3: Communication Methodology

Trang 11

PROJECT PLAN International School - Capstone 2 – 2021

2.4 Communication and Report:

Table 4: Communication and Report

Type of

communication

Methods, tools

Communication among in group

Scrum meeting Face to face

or Hangouts

Every two day

Workprogress:8Membersreport on their workprogress, difficultiesencountered and nextplans

arise:,Discuss and findways to solve problemsthat arise duringimplementation

Update ProductBacklog:,ProductBacklog can bereviewed and updated

if necessary

Project team

Sprint Planning

Meeting

Meet face to

face

together to analyze the

working on the sprint going

to do, planning and designfor the sprint

Project team

Project team and Mentor

Trang 12

o Effectiveinitiatives andimprovements.

o Positive feedbackfrom customers

Challengesencountered:

o Difficulties andobstacles duringoperations

o Weaknesses need

to be overcome

o Unresolvedissues

Learn and improve:

o Lessons learnedfrom successesand failures

o Suggestions andideas to improveoperationalefficiency

o Specific actions

problems andprevent risks

online

Every day A web-based task tracking

system To manage or dividetask, report bugs/issues

Project team

3 Development Process:

Scrum Process

Trang 13

PROJECT PLAN International School - Capstone 2 – 2021

Trang 14

● Scrum is an iterative and incremental agile software development framework formanaging software projects and product or application development

● Scrum focuses on project management institutions where it is difficult to plan

● Mechanisms of empirical process control, where feedback loops that constitute the core management technique are used as opposed to traditional command-andcontrol management

● Its approach to planning and managing projects is by bringing decision-making authority to the level of operation properties and certainties

Benefit of the methodology:

− Project can respond easily to change

− Problems are identified early

− Customers get the most beneficial work first

− Work done will better meet the customer’s needs −

Improved productivity

− Ability to maintain a predictable schedule for delivery

4 Schedule and Cost:

4.1 Detailed Schedule:

1.1.2 Facilities maintenance 27/02 28/02 6 hrs

1.2.1 Promotion and marketing 01/03 02/03 3 hrs

Trang 15

PROJECT PLAN International School - Capstone 2 – 2021

1.2.5 Clean up and prepare 05/03 06/03 5 hrs

2.2.7 Break and Lunch time 14/03 14/03 2 hrs

3.1.1 Trainning employees 15/03 15/03 4 hrs

3.1.3 Clean up and prepare for the evening 16/03 16/03 2 hrs

3.1.4 Food and entertainment services 16/03 16/03 2 hrs

Trang 16

3.1.5.1 End of shift 17/03 18/03 5 hrs

3.1.5.2 Design interface of Register 18/03 18/03 4 hrs

3.1.5.3 Design interface of Login 18/03 18/03 4 hrs

3.1.5.4 Design interface of profile 19/03 19/03 4 hrs

3.1.5.5 Design interface of chat room group 20/03 20/03 4 hrs

3.1.5.6 Design interface of list group 21/03 21/03 4 hrs

3.1.5.7 Design interface of member group 22/03 22/03 4 hrs

3.1.5.8 Design interface of call video group 23/03 23/03 4 hrs

3.1.5.9 Design interface of record group 24/03 24/03 4 hrs

3.1.5.10 Design interface of message 25/03 25/03 4 hrs

3.1.6.1 Code Main Menu for users 26/03 28/03 16 hrs

3.1.6.2 Code Login for users 29/03 30/03 4 hrs

3.1.6.3 Code Register for users 30/03 31/03 4 hrs

3.1.6.4 Code Profile for users 01/04 02/04 10 hrs

3.1.6.5 Code Group for users 03/04 06/04 10 hrs

Trang 17

PROJECT PLAN International School - Capstone 2 – 2021

3.2.1 Sprint Planning Meeting 13/04 13/04 4 hrs

3.2.2 Create Sprint Backlog 13/04 13/04 2 hrs

3.2.3 Create Test Plan document for

Design user interface of

Trang 18

3.2.6.1 Code Find a helper 20/04 21/04 18 hrs

3.2.6.2 Code Support for user 21/04 23/04 18 hrs

3.2.6.4 Code Learn Vocabulary 27/04 02/05 25 hrs

3.2.7.1 Test Find a helper 07/05 07/05 8 hrs

3.2.7.2 Test Support for user 07/05 07/05 5 hrs

3.2.7.3 Test Case for Search 08/05 08/05 5 hrs

3.2.7.4 Test Learn Vocabulary 08/05 08/05 7 hrs

3.3.1 Sprint Planning Meeting 11/05 11/05 4 hrs

3.3.2 Create Sprint Backlog 11/05 11/05 2 hrs

3.3.3 Create Test Plan document forSprint 3 12/05 12/05 2 hrs

3.3.4

Create Database document for

3.3.5.1 Design interface of Dashboard 13/05 14/05 8 hrs

3.3.5.2 Design interface of Manager account 14/05 15/05 5 hrs

3.3.5.3 Design interface of Admin 15/05 16/05 10 hrs

Trang 19

PROJECT PLAN International School - Capstone 2 – 2021

3.3.5.4 Design interface of Event 16/05 17/05 7 hrs

Trang 20

4.2 Cost

4.2.1 Cost Person/Hours

Table 1 Cost person/hours

4.2.2 Total Cost Estimate

3100

Table 2 Total cost estimation

- The explanation for the table: Amount of working hours = 4 o

members * 3 hours * 90 days o Other cost = 4 members * 100

USD

Trang 21

PROJECT PLAN International School - Capstone 2 – 2021

5 Project Risk:

Table 7: Rating for likelihood and seriousness for each risk

RATING FOR LIKELIHOOD AND SERIOUSNESS FOR EACH RISK

(Used forSeriousness only)

Table 8: Project Risk

d

Mitigation Strategy

Estimates of project

planning

The plan may be delayed for the initial estimate of the project

assessment of the scale Reducerequirements

Requirements Internal contradictions that

may exist in the request

Important requirements may be missing from the formal requirements specification

requirements prior to analysis

Estimated project

schedule

created to be updated and evaluated regularly

Programming

experience

Programming Languages and technology

sharing used to reduce the research time

Trang 22

processes

The standard procedure cannot meet the requirements of specific solutions

requirements and processes to ensureThe new process may be

required

The process can be improved and more efficient

appropriate levels

If the new process

is needed, we need to evaluate this response has improved over the old process

Bandwidth

transmission line network

period is too short, so our team cannot complete this project on a short time

During project implementation, our team

to learn and have more work to do, our team cannotfocus all their time to carry out this project

increase individual personal time working in their stay on the 7th day and Sunday

Project

Management

Project management system may not be sufficient to support the requirements of the project

group to offer solutions and consistent accuracy

6 Deliverables

Table 9: Deliverables

1 Proposal Document 16 –Mar – 2021 C2SE.12_Proposal_

LET_ver1.2.docx

2 Project Plan Document 20 –Mar – 2021 C2SE.12_ProjectPlan_LET_ver1

Trang 23

PROJECT PLAN International School - Capstone 2 – 2021

1.docx

Ngày đăng: 24/04/2024, 16:13