1. Trang chủ
  2. » Kinh Doanh - Tiếp Thị

Tài liệu Project Management Professional-Chapter 15b (Answer key) doc

7 327 0

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 7
Dung lượng 92,36 KB

Nội dung

Answer: d The expected value of a risk is the probability of the risk times the impact of the risk summed up for all possibilities... If the probability distribution of the scheduled com

Trang 1

1 Answer: c

In a fixed price contract the supplier is obligated to deliver the contracted-for item at a fixed price The supplier is aware of the risk and will put an allowance for the risk in the contracted price This often means that the project team will pay the supplier for the cost of the risk regardless of whether the risk occurs

2 Answer: a

Risk avoidance is eliminating the risk from consideration by doing something that will eliminate it as a possibility Risk acceptance is allowing the risk to happen and dealing with it if it occurs Risk deflection or transfer is transferring the risk to someone other than the project team, such as an insurance company

or outside supplier

3 Answer: c

Risk mitigation is the process of reducing a risk to acceptable levels In risk mitigation the risk has either a reduced impact or probability or both This reduces the risk severity to levels below the risk tolerance

4 Answer: b

Including a contingency budget will set aside money for known, identified risks This will give more control to the project and reduce the problem of known risks using budget that was set aside for the work of the project and causing a cost overrun in the project

5 Answer: d

The expected value of a risk is the probability of the risk times the impact of the risk summed up for all possibilities

7,000

347

Trang 2

Management reserve is funds set aside to manage unidentified risks PMI refers

to these as the ‘‘unknown unknowns.’’ When the management reserve is used,

it is moved from the management reserve to the cost or schedule baseline

7 Answer: a

Risk triggers, sometimes called risk symptoms, are indications that a risk is about to occur In this example there is a risk that the project will be delayed There is a warning that this will occur because several activities are now overdue for completion They do not affect the project schedule yet, but if this trend continues the project will be late

8 Answer: a

Because of risk in most projects the probability distribution is usually skewed This is because there are more things that will adversely affect schedules than there are that will improve them If the probability distribution of the scheduled completion of the project is indeed skewed, then the most likely date for project completion will be earlier than the mean value or the expected value

9 Answer: d

The expected value is found by multiplying the probability of the risk by the

10 Answer: b

This is a matter of applying the probability rule of addition This rule says that the probability of either one of two events is equal to the probability of one event plus the probability of the second event minus the probability of both of the events occurring

11 Answer: c

A buffered schedule is one where float is deliberately created in the schedule Buffers are deliberately created between tasks on the critical path, and the activi-ties are rescheduled to more closely approximate the schedule to the new prom-ise date

Trang 3

12 Answer: d

The client’s outsourcing method has nothing to do with risk management; all the other choices are items that should be included in the risk description

13 Answer: c

The lessons learned document from other similar projects can be a great help

in determining the new risks associated with this project Many times risks repeat themselves from one project to another This makes the lessons learned document very important for all projects

14 Answer: c

The result of the first risk meeting of a project team is to identify as many risks

as possible in the time allowed

15 Answer: b

The Monte Carlo technique is a refinement of PERT In the PERT process the range of values and the probability that they can occur is calculated for the project completion date or parts of the project The Monte Carlo technique allows for shifts that may occur in the critical path during possible values of the durations of the activities of the project It is a simulation technique that pro-duces a value called the criticality index, which is the percent of simulations that a particular activity is on the critical path That is, criticality index is the percent of the number of simulations that an activity is on the critical path

16 Answer: c

The management reserve is time and money used to offset the effect of un-known risks affecting cost and schedule These risks can only be approximated since none of them are specifically identified PMI refers to these risks as the known-unknown risks and the identified risks as the known-known risks

17 Answer: a

The break even point justification technique predicts a point in time where the benefits offset the costs involved It is a simple justification technique that takes into consideration a lot of assumptions Since it predicts the point in time where the benefits exceed the cost, given the choice of an expensive and a cheap machine, the cheap machine will usually have high short term benefits, and the expensive machine will have higher long term benefits

Trang 4

In critical chain theory the feeder chains are activities that are not on the critical path These tasks are scheduled to be done as late as possible and then buffered

so that they start earlier than the late schedule dates Buffer is also added to the critical path of the schedule to improve the probability that the project will finish on time Feeder chain activities as well as critical chain activities are not started as early as possible or as late as possible They are started as late as possible minus their buffer

19 Answer: c

In the normal probability distribution or any symmetric probability distribu-tion, the most likely value of the distribution is the peak of the distribution curve This is the value that has the highest probability of occurring In a sym-metric probability distribution this will be the center of the curve as well There

is a 50% probability that the project will finish past the most likely date and a 50% chance that the project will finish earlier than that date

20 Answer: c

Risks are events that affect a project for better or worse Positive risks increase the positive cash flow or benefits to the project, and negative risks increase the negative cash flow or benefits of the project

21 Answer: a

Fast tracking is changing the project plan to schedule activities that were planned to be done in sequence so that they can be done completely or partially

in parallel This will increase risk, because more work will be done if a problem

is discovered

22 Answer: b

In determining the worst case situation, all of the negative risks are included and none of the positive risks are included in the total This makes the assump-tion of the worst case as being that all of the bad things happen and none of the good things happen

23 Answer: b

Insurance transfers (deflects) the problem of the risk to someone else who takes the responsibility for the loss caused by the risk In this case an insurance com-pany agreed to compensate PMI if this loss occurred

Trang 5

24 Answer: d

During project closeout much of the project work has been completed and many of the risks have passed the time in which they can occur The total risk

of the project is therefore lowest during closeout

25 Answer: c

The Monte Carlo technique is a refinement of PERT In the PERT process the range of values and the probability that they can occur are calculated for the project completion date or parts of the project The Monte Carlo technique allows for shifts that may occur in the critical path during possible values of the durations of the activities of the project It is a simulation technique that pro-duces a value called the criticality index, which is the percent of simulations that a particular activity is on the critical path

26 Answer: b

If any of the activities are late, the entire project of the three activities will be late To state this as three mutually exclusive events we consider the probability

of all three of the events occurring on time This is 9 for each, and the probabil-ity of all three occurring is 9.9.9  73

27 Answer: c

The probability is that at least one of the sellers will deliver the parts on time This is the same as saying either vendor A or B must deliver This is the addition rule in probability The probability that the first seller will deliver is 9 The probability that the second seller will deliver is also 9, but the second seller delivering on time is only of consequence if the first seller fails to deliver on

28 Answer: b

This is the definition of value engineering used in the Guide to the PMBOK

Glossary

29 Answer: b

A workaround is the work that is not planned ahead of time to take care of a threat that occurs

30 Answer: d

In an even distribution any date in the distribution will have the same probabil-ity as any other date in the distribution

Trang 6

352 Preparing for the Project Management Professional Certification Exam

31 Answer: b The Monte Carlo technique is a simulation technique that assigns a value to the duration for each activity in the schedule This assignment can be by user selected probability distributions Depending on the values of the duration for each activity the critical path may change from simulation run to simulation run

32 Answer: a Risk acceptance is doing nothing about the risk until it happens This is done with risks that are below the risk tolerance level

33 Answer: b Risk tolerance is the measure of the client to take risks A client with a low risk tolerance will not be willing to take very many or large risks even though they may produce considerable opportunities to make large profits

34 Answer: b The Monte Carlo technique is a computer simulation method that selects dura-tions for schedule events according to a probability distribution on a random basis For each set of selected durations the simulation is run and the schedule and critical path are calculated The result is a probability distribution showing the probability of project completion dates that are possible The criticality index shows the percent of simulations that any activity is on the critical path

35 Answer: b Simulations such as the Monte Carlo simulation are frequently used in risk management It is far less expensive to model the real world than to actually do things in the real world

36 Answer: b Risk analysis should be done frequently throughout the project

37 Answer: d The risk option of mitigation means that the impact or the probability is re-duced to a level below the risk tolerance level This means that the risk is now acceptable

38 Answer: b Qualitative assessment of risks is often appropriate When there is little impact from a risk or when little is known about the risk parameters it may only be practical to evaluate risks in a qualitative way

Trang 7

39 Answer: c

This is the definition of sensitivity analysis in the Guide to the PMBOK.

40 Answer: a

The expected value of the risk is the probability of the risk multiplied by its cost This is one method of ranking risks Risks can also be ranked qualitatively

by assigning them qualitative values like ‘‘very risky’’ and ‘‘not too risky’’ and ranking them in groups

Ngày đăng: 26/01/2014, 14:20

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN

w