PLAN OF FORMWORK INSTALL PRIORITY DANGEROUS WORKS・MANUAL & PLAN OF FORMWORK INSTALLATION AND SAFETY WORKS (1) Notification of equipment installation Yes/No (2) Notification of construction plan Project name Yes/No (1) (2)Notification when plan changes Yes/No WORKING PLAN CHECK LIST Content NOTE: ・Heavy equipment(Crane・lift)・Scaffolding(formwork・Single tube・stepladder)・Stockyard( ・Working Procedure・Safety rope/Life line/ Safety net using area・No trepassing area ・Remaining material・Dump truck・Disposal area・neighborhood Structure part Wall Column Beam Internal wall Slab Staircase MS • • • • • • Material CONSTRUCTION DIRECTION (HƯỚNG THI CÔNG) Scaffolding +6.450 2FL DIRECTION OF CONSTRUCTION 2FL +6.450 1FL 1FL - 0.200 - 0.200 Ground beam 1FL RINGLOCK 1FL - 0.200 STEP 4:INSTALL BOTTOM FORMWORK OF BEAM BƯỚC 4: LẮP DỰNG VÁN KHUÔN ĐÁY CỦA DẦM STEP 3: INSTALL RINGLOCK SCAFFOLDING LEVEL BƯỚC 3: LẮP ĐẶT GIÁO RINGLOCK TẦNG DIRECTION OF CONSTRUCTION DIRECTION OF CONSTRUCTION DIRECTION OF CONSTRUCTION SLAB PLYWOOD +6.450 +6.450 2FL STEEL BOX 50X100 Q'ty Tower Crane Application STEEL BOX 50X50 Subcon Supplier ・ ・ ・ ・ ・ ・ ・ ・ Standard segment ( ) 1.Have plan for transportation of formwork material (time, quantity) or diversion plan? Already at site 2.Have plan for assembling formwork of staircase/inclined wall/inclined column/eaves Stair 3.Calculation of formwork structure? (heavy weight part, special part,etc.) Yes 4.Determine the installation procedure Yes 5.Prevention measure for sliding support (Nailing, etc.) No.As Calculation sheet 6.For the height more than 3.5m, there is connection part in every 2.5m height? Yes 7.The connection of more than number of auxiliary support is prohibited Yes 8.Use negarami clamp at the connection between support and horizontal brace? Show on drawing 9.Consideration of overlap allowance of fixed portion of no bracing formwork Nil (Haft PC, Deck, Beam…) 10.Strengthen the connection part when assembling scaffolding/support of beam Show on drawing 11.Have Scaffolding plan when Working on more than 2m height Show on drawing (Stepladder, scaffolding set, mobile framework, aerial working platforms) 12.Have working plan of scaffolding when assembling beam formwork? Show on drawing 13.Subsidence prevention measure for Support of eaves, cantilever, opening hole Nil 14.Determine the organization plan of material (Vertical hanging is prohibited) Yes 15.Using method of stepladder ? (Obtain Using Permit) 2FL +6.450 Nil 16.Secure of safety access? 2FL Life Line 17.Clarification of using area for safety rope/belt when assembling beam, slab Yes 18.Strengthen method for hanging location of rebar Yes 19.Have plan of working platform for staircase assembly and handrail for opening Double handrail 20.Have working platform and handrail arounf opening of Elevator Double handrail Pre-meeting - 0.200 1FL Ground beam ACESS WAY - 0.200 1FL Ground beam STEP 6:ARRANGE STEEL BOX 50X50 AND PLYWOOD FOR SLAB BƯỚC 6: SẮP XẾP THÉP HỘP 50X50 VÀ VÁN GỖ CHO SÀN (TY D17) (THÉP HỘP 50X100) (THÉP D12) (GỖ) DETAIL A MADE BY (CHÂN KÍCH CHỮ U) (CHÂN KÍCH CHỮ U) DETAILDẦM) A DETAIL OF BEAM FORMWORK (CHI TIẾT VÁN KHUÔN STAIR CASE FOR FORMWORK (VÁN KHUÔN CẦU THANG) NGUYEN THANH SON (TY D17) (BIÊN DẦM)) (THÉP HỘP 50X100) FORMWORK QUANTITY WALL & COLUMN: 4058 m2 BEAM & SLAB: 20134 m2 STEEL D12 WOOD 1FL+0.00 ENGINEER SITE MNG CHECKED BY PROJECT MNG Date No need principal safety and health supervisor if overall safety and health controller was assigned J V ) P e rs on i n c h a rg e (THÉP HỘP 50X100) JACK U (CHÂN KÍCH CHỮ U) (GỖ) Month ( Controller STEELBOX 50X100 (GỖ) (THÉP HỘP 50X100) Date Chain of commands (Verify the roles of each Subcon) (Related Subcon) S u p e r v i s o r RING LOCK 2.5M (KHÓA GIÁO 2.5M) (THÉP HỘP 50X50@1000) (THÉP HỘP 50X50@1000) Month - 0.200 STEP 7:INSTALL SIDE FORMWORK FOR EXTERNAL BEAM BƯỚC 7: LẮP DỰNG VÁN KHUÔN THÀNH CHO DẦM BIÊN 1FL+3300 Date JV Ground beam STEP 5: INSTALL SIDE FORMWORK OF BEAM AND EXTERNAL SCAFFOLDING BƯỚC 5: LẮP ĐẶT VÁN KHUÔN THÀNH CHO DẦM VÀ GIÀNG GIÁO BAO NGOÀI Kick-off meeting Month ACESS WAY ACESS WAY 1FL Remarks Lift loading LIFELINE LIFELINE LIFELINE - 0.200 Ground beam Ground beam STEP 2: INSTALL RINGLOCK SCAFFOLDING LEVEL BƯỚC 2: LẮP ĐẶT GIÁO RINGLOCK TẦNG STEP 1: INSTALL STEEL BOX 50X100 AND JACK BASE BƯỚC 1: LẮP ĐẶT THÉP HỘP 50X100 VÀ CHÂN KÍCH Crane /Handrail/Parapet? ACESS WAY STEELBOX 50X100 LEAN CONCRETE 50MM COMPACTED SAND 300MM ACESS WAY STEELBOX 50X100 LEAN CONCRETE 50MM COMPACTED SAND 300MM USE SAFETY ROPES SAFETY BELT ALWAYS DIRECTION OF CONSTRUCTION THÉP HỘP 50X100 BÊ TƠNG LĨT50MM CÁT ĐẦM 300MM THÉP HỘP 50X100 BÊ TƠNG LĨT50MM CÁT ĐẦM 300MM GROUND BEAM +6.450 WORKING PLAN DIRECTION OF CONSTRUCTION Pipe D52 Lift FORMWORK ZONING PLAN (MẶT BẰNG PHÂN CHIA KHU VỰC THI CÔNG) 2FL 50x50x2mm; 50x100x2mm Ringlock Content of ・Safety access( )・Working access( )・Satety ropes(Location: ) working plan ・Lifting equipment(Staircase・Gangplank・Slope・ ) ・Handrail(Staircase・EV shutter・Around opening・ ) ・Off-limit measures (Working area・Slab edge・Operation area of tower crane・Suspended load・ ) TYPICAL SUPPORT LAYOUT PLAN +6.450 Steelbox Heavy equipment Subcon 's duty 2FL 18mm Type ・ Function Safety devices DIRECTION OF CONSTRUCTION Plywood Safety ropes/ Life line/ Safety net ACCESSS LỐI VÀO THI CÔNG ) AREA MNG APPROVED BY QA/QC QC DIRECTOR VO HOANG PHIEM VO THAI BINH (Related Subcon) QUANG MINH Construction YEN PHAT GIA PHAM H.DAI PHAT MEDIA (Obliged measure for specific working area) In case operator use more than 3t mobile crane of other company (Specified company) H.DAI PHAT Installation of Scaffolding, rebar and formwork, dismantle of scaffolding ( S u b c o n t r a c t o