1. Trang chủ
  2. » Kinh Tế - Quản Lý

Lecture Information technology project management - Chapter 5: Project time management

56 90 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Chapter 5 - Project time management. After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management, discuss the process of planning schedule management, define activities as the basis for developing project schedules, describe how project managers use network diagrams and dependencies to assist in activity sequencing,...

Chapter 5: Project Time Management adopted from PMI’s PMBOK 2000 and  Textbook : Information Technology Project Management  (author : Dr. Kathy Schwalbe) Contents of time management • definition: charter and scope statement • sequence: mandatory dependencies, discretionary  dependencies, external dependencies • schedule: ADM, PDM • estimation: actual time + elapsed time. An art  require experience.  • schedule development: Gantt chart, CPM and  PERT • schedule control and change control: perform  checks, allow contingencies, communicate with  stakeholders regularlyChapter 5 Project Time Management • Developing the schedule involves  – – – – define the scope of the work define the activities estimate how long the activities will take define sequence the activities based on its  relationships – estimate associate costs with the activities.  Project Time Management  Processes • Project time management involves the processes  required to ensure timely completion of a  project.   • 5 Processes include: – – – – – Activity definition Activity sequencing Activity duration estimating Schedule development Schedule control planning control Chapter 5 Activity Definition process • 4th planning phase process • It involves identifying and documenting  the specific activities that must be  performed in order to produce the  deliverables and sub­deliverables  identified in the WBS Inputs to Activity Definition  process • WBS – The primary input to Activity Definition. It is scope definition tool that  organizes the work and provides a basis for project estimates • Scope statement – must be considered explicitly during Activity Definition. Project  justification and objectives are especially important • Historical information – activities required on similar projects should be considered in defining  project activities • Constraints – Factors that limit the team’s options • Assumptions – factors that, for planning purposes, will be considered to be true, real, or  certain • Expert judgment – guided by historical information should be used whenever possible.  subject­matter experts can help Tools & techniques for Activity  Definition process • Project schedules grow out of the basic  document that initiate a project – Project charter includes start and end dates and  budget information – Scope statement and WBS help define what  will be done • Activity definition involves developing a  more detailed WBS and supporting  explanations to understand all the work to  be done Chapter 5 Tools & techniques for Activity  Definition process (2) • Decomposition – dividing project elements into smaller, more  manageable components. Decomposition in Activity  Definition and in Scope Definition differ; the final  outputs in Activity Definition are activities (action  steps) and deliverables (tangible items) • Templates – previous project templates help project team to jump­ start the process Outputs from Activity Definition  process • Activity list – includes all activities that will be performed on the project.  Descriptions of each activity should ensure that stakeholders  understand how the work will be done • Supporting details – includes assumptions, constraints, and anything else that is  relevant • WBS update – Missing deliverables, clarifications, or corrections. This output  creates a feedback loop by which you get to tie up loose ends.  – Update the WBS and related documents, such as cost estimates.  These updates are often called refinements Activity Sequencing • 5th planning phase process  • Involves reviewing activities and determining  dependencies – Mandatory dependencies: inherent in the nature of the  work; hard logic – Discretionary dependencies: defined by the project  team; soft logic – External dependencies: involve relationships between  project and non­project activities • You must determine dependencies in order to use  critical path analysis Chapter 5 10 Using Critical Path Analysis to  Make Schedule Trade­offs • Knowing the critical path helps you make schedule  trade­offs • Free slack or free float is the amount of time an  activity can be delayed without delaying the early  start of any immediately following activities • Total slack or total float is the amount of time an  activity may be delayed from its early start without  delaying the planned project finish date Chapter 5 42 Free and Total Float or Slack for  Project X 43 Techniques for Shortening a  Project Schedule • Shortening durations of critical tasks for adding  more resources or changing their scope – Crashing tasks by obtaining the greatest amount of  schedule compression for the least incremental cost – Fast tracking tasks by doing them in parallel or  overlapping them Chapter 5 44 Importance of Updating Critical  Path Data • It is important to update project schedule  information • The critical path may change as you enter  actual start and finish dates • If you know the project completion date  will slip, negotiate with the project sponsor Chapter 5 45 Multitasking Example 46 Program Evaluation and Review  Technique (PERT) • PERT is a network analysis technique – to estimate project duration when there is a high  degree of uncertainty about the individual activity  duration estimates • PERT uses probabilistic time estimates based on  different estimates of activity durations – optimistic estimates (weighting 1) – most likely estimates (weighting 4) – pessimistic estimates (weighting 1) Chapter 5 47 PERT Formula and Example • PERT weighted average formula:  optimistic time + 4x most likely time + pessimistic time • Example: PERT weighted average =  8 workdays + 4 X 10 workdays + 24 workdays = 12 days where 8 = optimistic time, 10 = most likely time,  and 24 = pessimistic time 48 Controlling Changes to the  Project Schedule • 4th of 8 Controlling phase process  • It involves managing changes to the schedule.  The major activities include  – monitor the schedule performance of project activities  – detect variances from the original schedule baseline.  – general steps: • Perform reality checks on schedules – Allow for contingencies – Don’t plan for everyone to work at 100% capacity all  the time – Hold progress meetings with stakeholders and be clear  Chapter 5 and honest in communicating schedule issues 49 Inputs to Schedule control  • Project schedule – As a part of the integrated project plan, the approved schedule is called  schedule baseline.  – Project team/manager re­baseline when the schedule becomes  unrealistic.  – Re­baselining occurs when project team/manager do any major update  in order to have a better control the schedule • Performance reports – provide information on schedule execution – showing if planned dates  have been met. These reports also alert project team on issues that may  cause problem in future • Change requests – any update of schedule, that may require extending or accelerating the  schedule • Scope management plan – describes how changes will be integrated into the project. It is part of the  project plan 50 Tools & techniques for Schedule  control process • Schedule change control system:  – defines the procedures for changing the project schedule. It includes the  paperwork, tracking systems, and approval levels necessary for  authorizing changes • Performance measurement techniques:  – assess the magnitude of any variations that occur in project performance.  An important part of Schedule Control is to decide if the schedule  variation requires corrective action • Additional planning:  – prospective changes may require new or revised activity duration  estimates, modified activity sequences, or analysis of alternative  schedules • Project management software:  – widely used to assist with schedule development and control. In the  context of controlling, it is schedule tracking, and reporting. It helps  levels resources, for schedule alternatives 51 Using Software to Assist in  Time Management • Software for facilitating communications  helps people exchange schedule­related  information • Decision support models help analyze  trade­offs that can be made • Project management software can help in  various time management areas  Chapter 5 52 Outputs from schedule control  process • Schedule updates:  – include any modification to the schedule used to manage the  project. A special category of schedule updates, revisions,  describes changes to start and finish dates in the approval project  schedule • Corrective action:  – encompasses anything that brings your expected future schedule  back in line with the project plan. These actions are outputs from  the other knowledge areas • Lessons learned:  – document causes of variances, the reasoning behind corrective  actions, and other lessons learned from schedule change 53 Working with People Issues • Strong leadership helps projects succeed  more than good PERT charts • Project managers should use – – – – empowerment incentives discipline negotiation Chapter 5 54 Summary • importance of project schedules: IT project  always over­run • Time management process – – – – – definition (planning) sequence (planning) schedule estimation (planning) schedule development (planning) schedule control (control) Chapter 5 55 Summary (2) • definition: charter and scope statement • sequence: mandatory dependencies, discretionary  dependencies, external dependencies • schedule: ADM, PDM • estimation: actual time + elapsed time. An art  require experience.  • schedule development: Gantt chart, CPM and  PERT • schedule control and change control: perform  checks, allow contingencies, communicate with  stakeholders regularly 56 ... estimate associate costs with the activities.  Project Time Management Processes • Project time management involves the processes  required to ensure timely completion of a  project.    • 5 Processes include:... schedule control and change control: perform  checks, allow contingencies, communicate with  stakeholders regularlyChapter 5 Project Time Management • Developing the schedule involves  – – – – define the scope of the work... defined by the project management team. Constraints caused by  discretionary dependencies are called soft logic • External dependencies – involve a relationship between project and non project activities

Ngày đăng: 08/02/2020, 21:48

Xem thêm:

TỪ KHÓA LIÊN QUAN

Mục lục

    Chapter 5: Project Time Management

    Contents of time management

    Project Time Management Processes

    Inputs to Activity Definition process

    Tools & techniques for Activity Definition process

    Tools & techniques for Activity Definition process (2)

    Outputs from Activity Definition process

    Inputs to Activity Sequencing

    Task Dependency Types in PDM

    Sample Precedence Diagramming Method (PDM) Network Diagram for Project X

TÀI LIỆU CÙNG NGƯỜI DÙNG

  • Đang cập nhật ...

TÀI LIỆU LIÊN QUAN