The total cost of the process is then averaged over all the units of production.. 2 a Total variance 2,100 F Standard quantity for actual production at standard price 420,000 Direct labo
Trang 1Answers
Trang 3Part 1 Examination – Paper 1.2
Financial Information for Management June 2004 Answers Section A
1 A
2 D
3 C
4 C
5 D
6 C
7 B
8 A
9 D
10 D
11 D
12 A
13 B
14 C
15 B
16 C
17 C
18 C
19 B
20 C
21 C
22 A
23 A
24 B
25 D
3 C Contribution per unit (CPU) £(60 – 15 – 5) £40
4 C CPU (40 x 0·40) £16
––––––––––
––––––––––
800 units of product X uses 1,600 hours and in the remaining 400 hours, 100 units of product Y can be manufactured
6 C £(40,000 – 20,000) ÷ (20,000 – 4,000) units = £1·25 per unit
8 A Closing stock (units) = 200 + 600 – 150 – 200 – 250 = 200
Issues = £5,200 + (600 – 200) x £32·50 = £18,200
9 D
10 D
11 D Total direct labour hours:
Primary (6,000 x 36 ÷ 60) + (7,500 x 48 ÷ 60) 9,600
Finishing (6,000 x 25 ÷ 60) + (7,500 x 35 ÷ 60) 6,875
Absorption rates:
Primary (96,000 ÷ 9,600) £10 per hour
Finishing (82,500 ÷ 6,875) £12 per hour
Fixed cost per unit (Y): (48 ÷ 60) x 10 + (35 ÷ 60) x 12 = £15
(2 x 20 x (4 x 12,500)
0 10 x 15⋅
Trang 412 A £
Absorbed overhead (30,000 ÷ 3·50) 105,000
–––––––-
––––––––
13 B Sales < production by 280 units
Marginal costing profit would be lower by 280 x (48,000 ÷ 12,000) = £1,120
14 C
15 B Adverse price variance (0·04 x 2·50 x 12,000) = £1,200
12,000 litres at £2·50 per litre 30,000
Add Favourable usage variance 11,815
–––––––- Standard cost of actual production 31,815
–––––––- Actual production £31,815 ÷ (10·5 x 2·50) 1,212 units
–––––––-
17 C Let x = budgeted expenditure
1·1x – x = 136,000
1.1x –x = 360,000
1·1 x = 396,000 = actual expenditure (£)
Actual sales at standard selling price 112,500
(9,000 x £12·50) Actual sales at actual selling price 117,000
–––––––-
–––––––-
19 B
20 C
11 x 13,467 – (440 x 330)
b = –––––––––––––––––––––––– = 0·6917
(11 x 17,986) – (440)2
a = (330 ÷ 11) – 0·6917 (440 ÷ 11) = 2·33
Salary costs (54 x 40) + (110 x 25) 4,910
–––––––-
–––––––-
–––––––-
22 A Joint costs apportioned to product H: £
–––––––- Total cost of H production (228,000 units) 296,400
–––––––- Closing stock: 28,000 x (296,400 ÷ 228,000) = £36,400
23 A CPU from existing business (3·70 – 2·50) £1·20
New business CPU (2·95 – 2.50) £0·45
£ Total contribution from new business (6,000 x 0·45) 2,700
Less Lost contribution from existing business
––––––- Overall increase in contribution and profit 1,740
––––––-
Buy in component M
25 D
Trang 5Section B
1 (a) Cost per equivalent unit (EU) calculations for Process I:
(i) Value of closing work in progress =
(300 x 70) + (150 x 50) = £28,500
(ii) Value of transfer of 1,800 units to Process II =
1,600 x (70 + 50) + (120 x 50) + 16,500 = £214,500
Finished production 1,650 288,750
Workings
214,500 + 78,450 Cost per unit = –––––––––––––––––––– = £175
(0·93 x 1,800) Valuations:
Abnormal loss = 24 x 175 = £4,200
Finished production = 1,650 x 175 = £288,750
(c) – In job costing each job is costed separately whereas in process costing it is the process itself which is costed The total
cost of the process is then averaged over all the units of production
– In job costing production is to customer specification and therefore each job is likely to be different In process costing all units are identical in any one process
2 (a)
Total variance
2,100 F Standard quantity for actual production at standard price 420,000
Direct labour
4,620 A Standard hours for actual production at standard rate 945,000
Variable production overheads
1,260 F
19
Trang 6(b) £ Variance (£)
Rate 12,495 A Actual hours at standard rate 937,125
Efficiency 7,875 F Standard hours for actual production at standard rate 945,000
(c) Rate:
– Higher graded workers paid at a higher rate
– Higher than expected wage settlement for the company
Efficiency:
– The higher graded workers being more skilled took less than the standard time
– Highly motivated workers
3 (a) (i) Selling price per unit = £8 ÷ 0·40 = £20
(ii) Weekly contribution = 10,000 + 22,000 = £32,000
Weekly sales = 32,000 ÷ 8 = 4,000 units
Contribution and therefore profit is maximised when Strategy A is adopted
(c) Some costs do not fall clearly into being either variable or fixed They are the costs that are a mix of variable and fixed – sometimes called semi-variable or mixed costs
The following techniques could be used to separate the fixed and variable components of semi-variable or mixed costs: – the high-low method
– linear regression
Many costs are a mix of variable and fixed elements, for example power costs (gas or electricity) The tariffs for power costs often consist of a fixed charge irrespective of the amount of power consumed and a variable charge per unit of consumption
4 (a) (i) Materials
£
K 3,000 kg at (£19,600 ÷ 2,000) x 1·05 30,870
––––––––
£33,070 ––––––––
(ii) Skilled labour
£
Opportunity cost of labour 800 hours at (£40 ÷ 4) 8,000
––––––––
£15,600 ––––––––
(b) Any variable overhead costs associated with the contract would be relevant because they would represent additional or incremental costs caused directly by the contract
Fixed overhead costs would only be relevant if the total fixed overhead costs of the company increased as a direct consequence
of the contract being undertaken In that case the relevant amount would be the specific increase in the total fixed overhead costs caused by the acceptance of the contract
Arbitrary apportionments of existing fixed overhead costs would not be relevant Similarly sunk and committed costs would not be relevant
Trang 7Fixed production overhead costs (finishing section) 241,320
+
Reapportionment of general service centre costs
––––––––
298,920 ––––––––
Lang 7,200 units x (42 ÷ 6 ) 50,400 Dale 10,400 units x (36 ÷ 6) 62,400
––––––––
112,800 ––––––––
Direct labour hour absorption rate for the finishing section:
£298,920 ÷ 112,800 = £2·65
(b) Cost per unit for a Dale:
£ per unit £ per unit Direct material 44·00
Direct labour
– finishing section 36·00
–––––––
Production overhead costs:
– machining department (3 x £3·10) 9·30 – finishing section (6 x £2·65) 15·90
––––––––
––––––––
(c) For both products – Lang and Dale – production is greater than sales for the coming year In other words, stocks of finished products will be increasing In this situation, profits calculated using marginal costing principles will be lower than the profits calculated using absorption costing principles
Fixed production costs are written off as they arise under marginal costing whereas under absorption costing they form part
of the product cost and the inventory valuation Therefore in the coming year with stocks increasing and using absorption costing, a higher amount of fixed production cost will be carried forward at the year end than was brought forward in any opening stocks The effect is that some of the costs that would have been written off and would have reduced the profit under marginal costing are being carried forward under absorption costing to be written off against profits in later years
Trang 9Part 1 Examination – Paper 1.2
Financial Information for Management June 2004 Marking Scheme
Marks
Section A
Each of the 25 questions in this section is worth 2 marks 50
Section B 1 (a) Equivalent units of work done 1
Cost per equivalent unit 1
Value of work in progress 1
Value of transfer 1
––– 4 (b) Transfer in from Process I 1/2 Conversion costs 1/2 Normal loss 1
Abnormal loss 1
Finished production 1
––– 4 (c) Two differences – 1 mark for each 2
–––
10 ––– 2 (a) Three total variances – 1 mark for each 3
(b) Rate and efficiency variances – 11/2 marks for each 3
(c) Four causes (two for each variance in (b)) – 1 mark for each 4
––– 10 ––– 3 (a) Selling price 1
Weekly sales 2
––– 3 (b) Units for each strategy 1 Selling price for each strategy 1
Contribution for each strategy 1
Recommendation (best strategy) 1
––– 4 (c) Mixed or semi-variable costs 1
Example 1
Methods 1
––– 3 –––
10 ––– 4 (a) Material K 2
Material L 2
Skilled labour: – cost 1
Skilled labour:– opportunity cost 2
––– 7 (b) Explanation of relevant cost concept 1
Variable overhead costs 1
Fixed overhead costs 1
––– 3 –––
10
–––
Trang 105 (a) Reapportionment of general service centre costs 11/2
Original cost of finishing section 1/2
Total direct labour hours in finishing section 2
Direct labour hour rate 1
(b) Prime cost 1
Overhead costs (2 x 1/2mark) 1
(c) Production > sales/increasing stocks 1
Marginal costing profit lower than absorption costing profit 1
Explanation 1
–––
10
–––