TÀI LIỆU VỀ BỐ TRÍ ĐƯỜNG ỐNG VÀ HỆ THỐNG ĐƯỜNG ỐNG NGẦM 1. Gía đỡ ống: cấu trúc dẫn đường ống đi trong nhà máy Trong một nhà máy hóa học, đường ống dẫn hóa chất chạy từ cụm thiết bị này sang cụm thiết bị khác,và dẫn thẳng đến các cơ sở bên ngoài,... Cấu trúc được sử dụng cho mục đích này được gọi là Piperack. Vì vậy, trong khi chuẩn bị kế hoạch chính cho một nhà máy, một trong những hoạt động quan trọng nhất là lập kế hoạch cho piperack (hệ thống giá đỡ đường ống). 2.Hệ thống đường ống ngầm
PIPING DOCUMENT 1.Piperack: A Structure for Routing Pipes in the Plant In a chemical plant pipes run from one unit to another unit, lines coming from outside facilities etc. The structure which used for these purpose is termed as Piperack. So while preparing the plot plan for a plant one of the most important activity is to plan the piperack through which the piping has to run from one unit to the other Generally it is cheaper to run pipes at grade, but only where resulting hindrance to access is unimportant. The arrangement of pipe rack and structures should be given special attention as savings in structural steel and civil costs can often be greater than increased cost due to extra pipe length. Piperack constructionablity (structural or concrete) needs to be freezed at early stage of project in consultation with client & civil . Piping that needs to be free draining or ‘no pocket’ will often dictate the levels for elevated structures The following types of Pipe racks may be required: • Interconnecting/Main piperack (elevated) • Unit piperack (elevated) • Pipe track or sleeper way (at grade) Pipe rack example 1 Interconnecting piperacks carry process and utility lines to and from process and utility units. They should not run through process or utility units. Unit racks connect to the main rack taking lines into the respective units via a battery limits station. These racks should be at different elevations to the interconnecting rack Unit piperacks are the main arteries carrying the pipes into the units, and as such should be centrally located and are usually elevated. They should be of sufficient height to allow vehicle access beneath. The width of rack will be determined by the number of lines (plus future requirements) it carries, along with any allocation for cable trays In offsite areas or where only a few lines are required to run to an isolated plant area it is more cost effective to run pipes on pipe tracks or sleepers, at grade. Sleeper spacing will depend on limiting pipe spans. Sleeper piping is also preferred in offsite area as pipe runs on elevated structure often acts as hindrance for fire protection Pipe trenches are used mainly in large offplot storage areas where pipes need to run at low level and require to pass under plant roads. However use of unfilled open pipe trenches has to be reviewed considering the draining requirement 2.Underground Piping (U/G) Piping – Part 2 This device is used to collect surface drainage with an outlet liquid seal and sediment trap. The sketch Fig 1 illustrates a typical catch basin feature and Fig 2 illustrates a typical location of catch basins The maximum area coverage of a catch basin is approx 150 sqm. ie. 12m x 12m or15mx10m The area covered by a catch basin should be of square configuration, as far as possible. The catch basin should be located in the middle of the area as far as possible Slope of pavement 1 in 100, e.g. HPP (Ridge of catch basin area = 100.00) and LPP (at catch basin peripheral drain = 99.85) 1. Catch Basin No catch basins or manholes should be located within 15m radius of heaters. No vent pipes should be located within 15m of the heaters Area drainage around heater areas shall be done by pavement sloping towards open ditches. Each catch basin shall be connected to manhole and shall be provided with fire seal Fig 1 Catch basin Fig 2. Plot subdivided into drainage areas 2. Sealed Manholes Sealed manholes shall be provided at a. Unit battery limit and b. Junction of sewers and at change in size of main header These devices are provided so that the unit area is isolated from any fire in offsite area/sewer Within the unit area, sealed manholes in main headers should be provided in such locations so that each subunit within the unit is isolated from the other areas. In case, this demarcation is difficult, one sealed manhole for every 30m length of main sewer in the unit shall be provided Sealed manhole with bent pipes seal type shall be used for carbon steel pipes upto size16 ″ NB and for greater than dia 16″ NB and for all diameters of RCC pipes double compartment type manholes should be used 3. Invert elevation This term, usually associated with any underground line, refers to the elevation of the inside bottom of the line. Because of the wide range of materials used in the underground piping system / drainage system with varying wall thickness, it is the constant that is used to set the elevation on construction drawings The starting invert level of CRWS shall be normally 750mm below HPP (High Point ofPaving) The invert level at outlet point of CRWS and OWS shall be normally 1500mm below FGL 4. Cleanout A cleanout is a piping connection in a sewer system that is located at grade level for inspections or for cleaning the system 5. Vent Pipes Vent pipes shall be located along piperack columns or building columns and should be taken 2m above the building parapet or last layer of pipes on a piperack 6. Valve Pit / Maintenance pit for flanges and instruments When the underground system needs valves for isolation and instruments for control, the normal practice is to enclose these valves and instruments in a RCC pit with cover. These valves and instruments in a pit can be operated as well as maintenance work can be done with ease Piping arrangementUnderground Under piping are generally arranged based on the location of the consumers and the also depends upon the depth for the soil surface. Some of the guidelines for routing of the underground piping are stated below: 1. The overall Plot Plan allocates the space for the major underground services in the beginning of the project The cooling water supply from cooling water pump discharge to the various units as well as the cooling water return from the various units to the top of cooling tower is routed in a simple, straight orientation at a suitable depth avoiding any major road crossings A typical cooling water and potable water system is illustrated in sketch Fig 3. Cooling water cross over piping is illustrated in sketch Fig 4 Cooling water lines to heat exchangers are typically illustrated in sketch Fig 5 Cooling water lines to pumps for various cooling requirements is illustrated in sketchFig 6 2. The potable water system supplies to various units and a branch is taken to the emergency eyewash and safety shower station as illustrated in sketch Fig 7 3. Fire water system protects each piece of equipment by providing water through hydrants, monitors or deluge spray systems Each process unit will have its own underground firewater piping loop system 4. A typical hydrant and monitor installations are illustrated in sketch Fig 9 and a typical fire monitor is shown in sketch Fig 10 5. Normally, chemical process units will have multiple drain systems designed to collect all corrosive or toxic chemical waste as well as surface drainage around the equipment Drain / sewer system in a plant can be categorized as: – Uncontaminated storm water – Contaminated storm water – Oily water sewer – Chemical and process sewer – Sanitary sewer – Blowdown system – Uncontaminated storm water system generally collects all service water from equipment areas, access ways, roadways to equipment. This collection is done through area drains, catch basins, roof rain water downcomers – Contaminated storm water system collects surface drainage from areas containing hydrocarbon processing equipment. This system water must pass through a treatment facility before being discharged into an uncontaminated system or natural body of water viz. river or a stream connected to a river – Oily water sewer system collects waste, drips, leaks from equipment and piping in noncorrosive process equipment area. The designer should identify all the specific drain points in consultation with the process engineer – Chemical and process sewer system recovers acid or chemical drains from equipment / piping as well as surface drainage by providing curbing and drain sump around such equipment – Sketch UGP19 depicts a typical process drains – closed system – Sketch UGP21 illustrates a typical crosssection of a closed or chemical drain system – Sanitary sewer system collects raw waste from lavatories and is either connected to the municipal battery limit or routed to a septic tank – Blowdown system picks up drains around boilers and steam drums and is run as a separate system. It is permissible to connect the blowdown system to a sewer box in oily water sewer system downstream of drainage from a furnace 6. Trench Piping Occasionally, drain piping or process piping should be run below grade but not buried. Sketch Fig 8 illustrates two insulated lines A and B running below grade to a drain tank The top of the trench is covered with grating but could be covered with RCC slab depending on the traffic load estimated in the area The width of trench should allow adequate clearance to valves and drains as required 7. A typical catch basin is illustrated in sketch Fig 11 A typical sewer box or manhole is illustrated in sketch Fig 12. A typical Dyked area drain sump is illustrated in sketch Fig 13 A typical lift station by vertical pump is illustrated in sketch Fig 14 8. A process area for the purpose underground drainage is subdivided into block areas with high point ridge and low point catch basins / pits The low point catch pits are connected to manholes The manholes are interconnected by sloping piping and led to the battery limit valve pit and finally discharged into the treatment pond Sketch Fig 1516, Fig 1718, Fig 19 illustrates the details of the subdivision of the process area into blocks with explanatory notes Sketch Fig 20 illustrates how to handle oily water and storm water system 9.Closed drain system is illustrated by various sketches Fig 2122, Fig 23, Fig 24 10.The underground electrical and instrument cables passing under a road or paved area is takenthrough ducts embedded in lean concrete. Sketch Fig 25 shows a typical arrangement of such underground cabling details Fig 3 Process cooling water and potable water system Fig 4. Cooling water crossover piping Fig 5 Cooling water to exchangers Fig 6. Cooling water to pumps Fig 7 Emergency eyewash and safety shower Fig 8. Trench piping Fig 9 Hydrant and monitor installations Fig 10 Typical grademounted fire monitor Fig 11 Catch basin Fig 12 Typical sewer box or manhole Fig 13 Dyked area drain Fig 14. Lift station Fig 15. Indicative PFD for oily waste sewer & contaminated rain water sewer & process line Fig 16. Notes: Indicative PFD for oily waste sewer & contaminated rain water sewer & process line Fig 17.G.A.for underground piping Fig 18.Notes: G.A.for underground piping Fig 19. Plot subdivided into drainage areas Fig 20. Oily water and storm water system Fig 21.Process drains: Closed system Fig 22. Plan for a closed drain system Fig 24 Closed drain system Sump Fig 23.Closed drain system : Cross section Fig 25 Underground cable duct