I. GENERAL REQUIREMENTS
I.1 Legal requirement
- Normative standard of Vietnam standard 4453: 1955 (concrete structure and concrete blocks), Vietnam standard 4085: 1985 (brick and stone structure) and Vietnam standard 5461: 1991 (reinforced concrete tank).
- Contract for construction of poured reinforced concrete between the Investor and contractor of this work.
- General standard for materials, grading and concrete quality (the contractor must provide the date of manufacture, serial numbers, supplies, materials manufacturers, specifications, check results about information on grading, the link of the use life).
- Profile of architectural designs and textures to when there is a difference between the drawings shall notify to designed unit for timely correction.
V.2 Work requirements:
Poured reinforced concrete (see structural drawings).
V.3 Technical requirements:
1. Form work:
- Install formwork with structural size of the engineering design records, noting all the installation, anchor bolt with a body structure is structural steel, technical tubes and other details according to technical drawings.
- Dismantle formwork when the concrete has gained standard strength.
- Formwork surfaces should be clean, does not warp.
- It is necessary to check the heart axis and the size by elevation measurement machine before construction 24 hours (with photograph).
2. Necklaces track construction method (foundation beam):
a. Form and reinforcement work:
- Get high on momentum Necklaces (foundation beam).
- Installation of formwork and hold the board against the yoke by hand, struts on the outside or use wire tension.
- Check heart beams and adjust the vertical formwork surface.
- Installation of reinforced tripod.
- Align the heart position of anchor bolt (if any).
b. Concreting work:
- Before pouring concrete, need to check formwork and reinforcement last.
- When pouring concrete, must pour concrete focused on the middle, avoiding collisions on formwork and reinforcement can cause them to deform and move out of position.
- During the pouring concrete, must use the concrete compaction.
XII.1 Document Requirements
XIII. MAINTENANCE WORKS
XIII.1 Document Requirement
XIII.2 Work Requirement
XIII.3 Technical Requirements