Purpose: Some practical issues one must know in order to compute the net present value NPV of a project It assumes the social discount rate is given, which is reasonable as the rate is
Trang 1Chapter 6
Discounting Future Benefits and Costs
Applied Welfare Econ & Cost Benefit Analysis
Trang 2Purpose: Some practical issues one must know in order to
compute the net present value (NPV) of a project
It assumes the social discount rate is given, which is reasonable
as the rate is often set by an public agency
The chapter covers: the basics of discounting (two-periods);
compounding and discounting over multiple periods
(years); the timing of benefits and costs; horizon (terminal) values; comparing projects with different time frames;
inflation and the difference between nominal and real
dollars; relative price changes; and sensitivity analysis in discounting
Trang 3Appendix 6A provides shortcut formulas for calculating the present value of
annuities and perpetuities
You are responsible for going through this appendix yourselves
Trang 4BASICS OF DISCOUNTING
Projects with Lives of One Year
Discounting takes place over periods not years However, for simplicity,
assume that each period is a year First we discuss projects that last one year.
There are three possible methods to evaluate potential projects: future
value analysis, present value analysis and net present value analysis Each gives the same answer.
Trang 5BASICS OF DISCOUNTING
Future Value Analysis – Choose the project with the largest future value,
FV, where the future value in one year of an amount X invested at interest rate i is:
FV = X (1 + i) (6.1)
Present Value Analysis – Choose the project with the largest present value,
PV, where the present value of an amount Y received in one year is:
PV = Y/(1 + i) (6.2)
If the PV of a project equals X, and the FV of a project equals Y, both
equations (6.1) and (6.2) imply: PV=FV /(1 + i)
This equation shows that discounting (the process of calculating the
present value of future amounts) is simply the opposite of compounding (the process of calculating future values).
Trang 6BASICS OF DISCOUNTING
Net Present Value Analysis – Choose the project with the largest net
present value, which calculates the sum of the present values of all the benefits and costs of a project (including the initial investment):
NPV = PV(benefits) – PV(costs) (6.3)
Trang 7BASICS OF DISCOUNTING
Usually projects are evaluated relative to the status quo:
If there is only one new potential project and its
impacts are calculated relative to the status quo, it
should be selected if its NPV > 0, and should not be selected if its NPV < 0
If the impacts of multiple, mutually exclusive
alternative projects are calculated relative to the
status quo, one should choose the project with the
highest NPV, as long as this project’s NPV > 0
If the NPV < 0 for all projects, one should maintain
the status quo
Trang 8COMPOUNDING AND DISCOUNTING OVER
MULTIPLE YEARS
Interest is compounded when an amount is invested
for a number of years and the interest earned each period is reinvested
Interest on reinvested interest is called compound
interest
The future value, FV, of an amount X invested for
n years with interest compounded annually at rate i is:
Trang 9Present value again
Present value: the amount a specified money sum received at a
future date is worth today
$1 today can turn into $1(1+r) in a year’s time right?
Therefore, we know that the present value (PV) of $1(1+r) of next
year is $1 of today
This is because $1 is equal to
$ 1+r 1+r
Trang 10Present value vs Future Value
When we translate the future into the present, we discount the
future value (we make it look smaller to get the PV)
When we translate the present into the future, we compound the
present value (we make it look bigger to get the FV)
Trang 11Present value vs Future Value
But we do have a translating device to make values smaller to the
right extent, when calculating the PV of a sum received in the following period
The discount factor 1/(1+r)
which is given by the discount rate r
Trang 12Discount rate
Discount rate: the value placed upon current
consumption, relative to future consumption
It measures how strongly we prefer money now to later given our possibilities to transform money today into money tomorrow
If this rate is high, we will only trade off money now only for lots of money later, since we know how much
we lose by waiting
Trang 13Discount factor
Discount Factor - The factor that translates expected benefits or
costs in any given future year into present value terms
The discount factor is equal to 1/(1 + r) t where r is the interest rate
and t is the number of years from the current year until the future year
Trang 14Discount factor
The discount factor is equal to 1/(1 + r) t where r is the interest rate
and t is the number of years from the current year until the future year
The higher r and or the higher t the smaller the discount factor, so
the bigger the difference between the future value and the present value
Trang 15 So what is the present value of $100 received in 10 years time from
now if the discount rate is 3% (not much higher than the real bank interest rates)? And $10 at a 5%?
$10/(1.05) 10 =$6.14
what about these $10 in 5 years?
$10/(1.05) 5 =$7.84
Trang 16NET PRESENT VALUE
The net present value of an investment is equal to the difference
between benefits received in several periods and costs faced in in several periods
when all expressed in their Present Value
NPV = > 1 t Bt
Ý1+rÞ t ?1 ? Ct
Ý1+rÝ tÝ 1
Trang 17NET PRESENT VALUE
The net present value of an investment is equal to the
difference between benefits received in several periods and costs faced in in several periods
Usually, there is a natural choice for t the “useful” life
of the project, such as when or an asset undergoes a
major refurbishment or the assets are sold.
Sometimes we use variations of the formula with infinite
t
See textbook for alternative ways to calculate horizon
values
Trang 18COMPARING PROJECTS WITH DIFFERENT
TIME FRAMES
Analysts should not choose one project over another solely based
on the NPV of each project if the time spans are different
Such projects are not directly comparable.
So what can the analyst do? Two options…
Trang 19Rolling over the Shorter Project
If project A spans n times the number of years as project B, then
assume that project B is repeated n times and compare the NPV of
n repeated project Bs to the NPV of (one) project A
For example, if project A lasts 30 years and project B lasts 15 years,
compare the NPV of project A to the NPV of 2 back-to-back project B’s, where the latter is computed:
NPV = x + x/(1+i) 15
where, x = NPV of one15-year project B.
Trang 20Equivalent Annual Net Benefits (EANB) Method
The EANB is the amount received each year for the life of
the project that has the same NPV as the project itself
The EANB of a project is computed by dividing the NPV by
the appropriate annuity factor, ai n:
EANB = NPV/ ain
The appropriate annuity factor ain is the present value of an
annuity of $1 for the life of the project (n years), where i = interest rate used to compute the NPV Obviously, one
would choose the project with the highest EANB
Trang 21Other Considerations
Shorter projects also have an additional benefit
(not included in EANB) because one does not necessarily have to roll-over the shorter project when it is finished.
A better option might be available at that time
This additional benefit is called quasi-option value and is discussed further in Chapter 7.
Trang 22NET PRESENT VALUE
If the NPV of a prospective project is positive, it should be accepted,
but if it is negative then the project should be rejected
OK, I will believe it…
but then, what should I do with my savings?
Trang 23NET PRESENT VALUE
what should I do with my savings?
Invest them in any project that promises returns at a rate r
That is the key: your project was not good if you used a discount
rate r
Because you would lose money in PV if the discount rate was to be
r
Trang 24NET PRESENT VALUE
In that case, instead of going for the project, put you money into
something that pays an interest rate r
like a bank account
Trang 25Internal rate of return
Another way to look at it is to find the particular value of the
discount rate that would make the NPV=0 for your project
That is called the internal rate of return of your project
Trang 26Internal rate of return
Trang 27Internal rate of return
Therefore, if you can find an alternative project that pays more
than r*, you should put your money there!!! Not in your original project!
Think about it: if the IRR (r*) is lower than what you can get
anywhere else, then you are not getting a benefit from the project to cover the opportunity cost of your money!
Trang 28Internal rate of return
Think about it in a different way: if the IRR (r*) is lower than the
rate of interest at which you need to repay your loan for the funds for the project, you should not undertake the project!
Trang 29Example of the power of compounding
The Dutch allegedly bought Manhattan in 1626 for about $24
worth of beads and trinkets
if Native Americans had invested in tax-free bonds 7% APR
bonds, it would now be worth over $2.0 trillion > assessed value
Trang 30REAL VERSUS NOMINAL DOLLARS
Conventional private sector financial analysis measures
monetary amounts in nominal dollars (sometimes
called current dollars).
But, due to inflation, one cannot buy as many goods and services with a dollar today as one could one, two or
more years previously It is important to control for
inflation
We control for inflation by converting nominal dollars
to real dollars (sometimes called constant dollars) We
usually use the consumer price index (CPI), but
sometimes use the gross national product (GNP).
Trang 31Estimates of Inflation and Problems with CPI
The CPI is the most commonly used measure of inflation Prior to 1998,
the CPI overstated inflation by about 0.8% to 1.6% per annum Four reasons for the overstatement are:
1) Commodity substitution effect: The CPI did not accurately
reflect changes in consumer purchases, such as switching to priced substitutes;
lower- 2) New goods: The “basket” of goods did not include some
new products, e.g., new (cheaper) generic drugs;
3) Quality improvements: The CPI did not accurately reflect
changes in product quality, e.g more safe or reliable cars;
4) Discount store effect: Consumers are shopping more at
discount stores, which have less expensive products
Trang 32Real rates of interest
In a world with inflation
What is the difference between the real and the nominal interest
rate?
Imagine that prices actually grow at a rate:
We are going to label the real interest rate
Trang 33Real rates of interest
If we want to put next year’s prices in real terms, we want to
discount the inflation
we want to adjust for inflation, dividing by
1+
Using this idea, we can find the real rate of interest
i* is more or less equal to i - for low levels of inflation, like the
ones we normally face
E Ý
Trang 34Real rates of interest
The proof is given in Varian, for example
Check that it makes sense, and then just remember that the results
is a good approximation in most cases
Trang 35Existence Values READ CHAPTER 9