1. KINGPOST 2. Cừ LARSEN 3. Cọc khoan nhồi 4. giếng hạ mực nước ngầm 5. Biện pháp xốp pha 6. Biện pháp xử lý 7. Biện pháp cắt đục bê tông 8. Biện pháp chống thấm
Trang 110/2020 CÔNG TÁC PHỤ
BẢN VẼ BIỆN PHÁP THI CÔNG PHẦN HẦM
Trang 21 0
2
0
01 - MD - 01
BIỆN PHÁP HẠ KINGPOST VÀO CỌC NHỒI/ BARRETTE (1)
6
DANH MỤC BẢN VẼ
3
4
5
0 0
DANH MỤC BẢN VẼ
9
10
11
0
XỬ LÝ BÊ TÔNG BỊ RỖ 7
0
0
0
0
0
12
13
0 15
16
17
18
19
20
0
0 0
22
23
24
25
26
0
0
0 0
BIỆN PHÁP THI CÔNG KHOAN CẤY THÉP BIỆN PHÁP CHỐNG GỈ THÉP
BIỆN PHÁP XỬ LÝ LỖ TI CHẾT
0
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
01 - MD - 02
01 - MD - 03
01 - MD - 04
01 - MD - 05
01 - MD - 06
01 - MD - 07
01 - MD - 08
01 - MD - 09
0
0
0
0
0
0
0
0
0
0 0 0
0 0 0 0
0
0
0
0
0
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MƠ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
01 - MD - 10
01 - MD - 11
01 - MD - 12
01 - MD - 13
01 - MD - 14
01 - MD - 15
01 - MD - 16
01 - MD - 17
01 - MD - 18
01 - MD - 19
01 - MD - 20
01 - MD - 21
21
42
01 - MD - 22
01 - MD - 23
01 - MD - 24
01 - MD - 25
01 - MD - 26
01 - MD - 27
01 - MD - 28
01 - MD - 29
01 - MD - 30
01 - MD - 31
01 - MD - 32
01 - MD - 33
01 - MD - 34
01 - MD - 35
01 - MD - 36
01 - MD - 37
01 - MD - 38
01 - MD - 39
01 - MD - 40
01 - MD - 41
01 - MD - 42
43
44
01 - MD - 43
01 - MD - 44
0
0
ĐỤC BÊ TÔNG CỌC NHỒI/ BARRETTE
BIỆN PHÁP CHỐNG THẤM TƯỜNG VÂY - SÀN HẦM
BIỆN PHÁP CỐP PHA CỘT TOPDOWN BIỆN PHÁP CỐP PHA VÁCH TOPDOWN
BIỆN PHÁP BƠM VỮA MỐI NỐI CỘT VÁCH TOPDOWN
BIỆN PHÁP CHỐNG THẤM BỂ NƯỚC SINH HOẠT, PCCC BIỆN PHÁP CHỐNG THẤM BỂ XỬ LÝ, BỂ TỰ HOẠI
BIỆN PHÁP CHỐNG THẤM HỐ THANG MÁY BIỆN PHÁP CHỐNG THẤM MẠCH NGỪNG THI CÔNG (1) BIỆN PHÁP CHỐNG THẤM MẠCH NGỪNG THI CÔNG (2)
BIỆN PHÁP THI CÔNG CỐP PHA VÁCH TOPDOWN (BÊ TÔNG TỰ LÈN-PA1)
I KINGPOST
BIỆN PHÁP HẠ KINGPOST VÀO CỌC NHỒI/ BARRETTE (2) BIỆN PHÁP ÉP KINGPOST SỬ DỤNG BÚA RUNG THỦY LỰC BIỆN PHÁP CẮT KINGPOST
BIỆN PHÁP NHỔ KINGPOST (KÍCH NẰM Ở SÀN HẦM ĐÁY) BIỆN PHÁP NHỔ KINGPOST (KÍCH NẰM Ở CÁC SÀN BÊN TRÊN) BIỆN PHÁP XỬ LÝ LỖ KINGPOST
(TRƯỜNG HỢP 1: CÓ NƯỚC CHẢY TỪ DƯỚI LÊN QUA LỖ KINGPOST) BIỆN PHÁP XỬ LÝ LỖ KINGPOST
(TRƯỜNG HỢP 2: KHÔNG CÓ NƯỚC CHẢY TỪ DƯỚI LÊN QUA LỖ KINGPOST)
II CỪ LARSEN
BIỆN PHÁP ÉP CỪ LARSEN BẰNG BÚA RUNG BIỆN PHÁP ÉP CỪ LARSEN BẰNG ROBOT BIỆN PHÁP NHỔ CỪ LARSEN BẰNG ROBOT
III CỌC KHOAN NHỒI
BIỆN PHÁP THI CÔNG CỌC KHOAN NHỒI TỪ CÓ ĐƯỜNG KÍNH D<=D600 BIỆN PHÁP THI CÔNG CỌC KHOAN NHỒI TỪ CÓ ĐƯỜNG KÍNH D>=D800 (1)
IV GIẾNG HẠ MỰC NƯỚC NGẦM
BIỆN PHÁP KHOAN GIẾNG HẠ MỰC NƯỚC NGẦM BIỆN PHÁP CẮT GIẾNG HẠ MỰC NƯỚC NGẦM ĐIỂN HÌNH BIỆN PHÁP CẮT GIẾNG HẠ MỰC NƯỚC NGẦM SAU CÙNG
0
V BIỆN PHÁP CỐP PHA
BIỆN PHÁP LẮP DỰNG CỐP PHA DẦM SÀN TRÊN NỀN ĐẤT - PA1 BIỆN PHÁP LẮP DỰNG CỐP PHA DẦM SÀN TRÊN NỀN ĐẤT - PA2 CỐP PHA MÓNG (CỐP PHA VÁN)
CỐP PHA MÓNG (CỐP PHA TOLE) CỐP PHA GẠCH KHÍ CHƯNG ÁP (AAC) CHO DẦM
BIỆN PHÁP THI CÔNG CỐP PHA VÁCH TOPDOWN (BÊ TÔNG TỰ LÈN-PA2)
VI BIỆN PHÁP XỬ LÝ
VII BIỆN PHÁP CẮT ĐỤC BÊ TƠNG
BIỆN PHÁP CẮT BÊ TÔNG BẰNG DÂY KIM CƯƠNG (1) BIỆN PHÁP CẮT BÊ TÔNG BẰNG DÂY KIM CƯƠNG (2) BIỆN PHÁP CẮT BÊ TÔNG BẰNG DÂY KIM CƯƠNG (3) BIỆN PHÁP CẮT ĐỤC SÀN BIỆN PHÁP (1)
BIỆN PHÁP CẮT ĐỤC SÀN BIỆN PHÁP (2) VIII BIỆN PHÁP CHỐNG THẤM
BIỆN PHÁP THI CÔNG CỌC KHOAN NHỒI TỪ CÓ ĐƯỜNG KÍNH D>=D800 (2) BIỆN PHÁP THI CÔNG CỌC KHOAN NHỒI TỪ CÓ ĐƯỜNG KÍNH D>=D800 (3)
Trang 3STEP 03
STEP 04
STEP 05 - SECTION 1-1
SỢI NYLON
BƯỚC 03
BƯỚC 04
BƯỚC 05 - MẶT CẮT 1-1
SLAB BOTTOM LEVEL BEAM BOTTOM LEVEL
WOOD PURLIN []80x80 XÀ GỒ GỖ []80x80
1 - INSTALL PLYWOOD FOR BEAM
2 - COMPLETING FORMWORK FOR BEAM
1 - ĐẶT CÁC TẤM VÁN ÉP CHO DẦM
2 - HOÀN THÀNH CỐP PHA DẦM
1 - BACK FILL BY SOIL
2 - INSTALL PLYWOOD FOR SLAB
3 - COMPLETING FORMWORK FOR SLAB
1 - LẤP ĐẤT THÀNH DẦM
2 - ĐẶT CÁC TẤM VÁN ÉP CHO SÀN 3- HOÀN THÀNH CỐP PHA DẦM SÀN
1 - INSTALL WOOD PURLIN []80x80 FOR BEAM
2 - ADJUSTING LEVEL
1 - ĐẶT CÁC THANH XÀ GỒ GỖ []80x80 CHO DẦM
2 - ĐIỀU CHỈNH CA0 ĐỘ
1 - DRIVING EUCALYPTUS PILE D50->80 FOR BEAM
2 - ADJUSTING LEVEL
1 - ĐÓNG CỪ TRÀM D50->80 CHO DẦM
2 - ĐIỀU CHỈNH CA0 ĐỘ
1 - BACK FILLING WITH SAND IN 20mm Thk BELOW BOTTOM BEAM
2 - FLATTEN GROUND BY SURFACE COMPACTOR
1 - LẤP CÁT DÀY 20mm DƯỚI ĐÁY DẦM
2 - LÀM PHẲNG NỀN BẰNG MÁY ĐẦM MẶT
INSTALLING FORMWORK SEQUENCE FOR BEAM QUY TRÌNH LẮP DỰNG CỐP PHA CHO DẦM XÀ GỒ GỖ 80X80 MM@600
NOTE/ GHI CHÚ:
WOOD PURLIN 80X80 MM@600
BEAM BOTTOM LEVEL
- EXISTING GROUND/ ĐẤT HIỆN HỮU
- SAND 20MM/ CÁT 20 mm
- POLYWOOD/ VÁN
- EXISTING GROUND/ ĐẤT HIỆN HỮU
- EUCALYPTUS PILE D80/ CỪ TRÀM D80
- WOOD PURLIN 80x80 MM/ XÀ GỒ GỖ 80x80 mm
- POLYWOOD/ VÁN
ADJUSTING LEVEL CÂN CHỈNH CAO ĐỘ
L1, L2 FOLLOW ACTUAL TESTING RESULT ON SITE BEFORE INSTALLING FORMWORK FOR B1, B2, B3, B4
SUGGEST L1, L2 @ 600 FOR LOAD TESTING WITH THE AVERAGE SETTLEMENT -5MM (ACCORDING TCVN 4453-1995 )
L1, L2 THEO KẾT QUẢ THÍ NGHIỆM THỰC TẾ TẠI CÔNG TRƯỜNG TRƯỚC KHI THI CÔNG CỐP PHA SÀN HẦM B1, B2, B3, B4
ĐỀ XUẤT L1,L2 @600 ĐỂ THỬ TẢI VỚI ĐỘ LÚN TRUNG BÌNH ±5MM (THEO TCVN 4453-1995 BẢNG 20)
PLYWOOD VÁN ÉP
BACK FILL BY SOIL LẤP LẠI BẰNG ĐẤT PLYWOOD
1
- EXISTING GROUND/ ĐẤT HIỆN HỮU
- POLYWOOD/ VÁN
STEP 01
BƯỚC 02
SAND 20mm LẤP CÁT DÀY 20mm
1 - INSTALL WOOD PURLIN []80x80 FOR SLAB
2 - BACK FILLING WITH SAND IN 20mm Thk BELOW BOTTOM SLAB
STEP 02 BƯỚC 02
1 - EXCAVATION/ ĐÀO ĐẤT
2 - FLATTEN SURFACE/ LÀM PHẲNG BỀ MẶT
STEP 01 BƯỚC 01
1 - INSTALL PLYWOOD FOR SLAB
2 - ĐẶT CÁC TẤM VÁN ÉP CHO SÀN
STEP 03 BƯỚC 03
INSTALLING FORMWORK SEQUENCE FOR SLAB QUY TRÌNH LẮP DỰNG CỐP PHA CHO SÀN
EXISTING SOIL ĐẤT TỰ NHIÊN
1 - ĐẶT CÁC THANH XÀ GỒ GỖ []80x80 CHO SÀN
2 - LẤP CÁT DÀY 20mm DƯỚI ĐÁY SÀN
WOOD PURLIN []80x80 XÀ GỒ GỖ []80x80 SAND 20mm
- WOOD PURLIN []80x80/ XÀ GỒ GỖ []80x80
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MƠ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
BIỆN PHÁP LẮP DỰNG COPPHA DẦM SÀN
CỐP PHA ĐIỂN HÌNH DẦM SÀN CHO HẦM B1,B2,B3,B4 TRÊN NỀN ĐẤT SÉT - PHƯƠNG ÁN 1
TRÊN NỀN ĐẤT- PA1
Trang 4STEP 03 - SECTION 2-2 BƯỚC 03 - MẶT CẮT 2-2
SLAB BOTTOM LEVEL BEAM BOTTOM LEVEL
1 - INSTALL PLYWOOD FOR BEAM (BOTTOM & SIDE)
2 - BACK FILL BY SOIL
3 - COMPLETING FORMWORK FOR SLAB & BEAM
1 - ĐẶT CÁC TẤM VÁN ÉP CHO ĐÁY DẦM VÀ THÀNH DẦM
2 - LẤP ĐẤT THÀNH DẦM 3- HOÀN THÀNH CỐP PHA DẦM SÀN
1 - ADJUSTING LEVEL
2 - POURING LEAN CONCRETE FOR BEAM 80mm THK
1 - ĐIỀU CHỈNH CA0 ĐỘ
2 - ĐỔÛ BÊ TÔNG LÓT CHO DẦM 80mm
1 - DRIVING EUCALYPTUS PILE D50->80 FOR BEAM
2 - ADJUSTING LEVEL
1 - ĐÓNG CỪ TRÀM D50->80 CHO DẦM
2 - ĐIỀU CHỈNH CA0 ĐỘ
NOTE/ GHI CHÚ:
L1, L2 FOLLOW ACTUAL TESTING RESULT ON SITE BEFORE INSTALLING FORMWORK FOR B1, B2, B3, B4 SUGGEST L1, L2 @ 600 FOR LOAD TESTING WITH THE AVERAGE SETTLEMENT -5MM (ACCORDING TCVN 4453-1995 ) L1, L2 THEO KẾT QUẢ THÍ NGHIỆM THỰC TẾ TẠI CÔNG TRƯỜNG TRƯỚC KHI THI CÔNG CỐP PHA SÀN HẦM B1, B2, B3, B4.
ĐỀ XUẤT L1,L2 @600 ĐỂ THỬ TẢI VỚI ĐỘ LÚN TRUNG BÌNH ±5MM (THEO TCVN 4453-1995 BẢNG 20).
PLYWOOD VÁN ÉP
BACK FILL BY SOIL LẤP LẠI BẰNG ĐẤT
- EXISTING GROUND/ ĐẤT HIỆN HỮU
- LEAN CONCRETE 80mm/ BÊ TÔNG LÓT 80mm
- POLYWOOD/ VÁN
1 - POURING LEAN CONCRETE FOR SLAB 80mm THK
2 - ĐỔ BÊ TÔNG LÓT CHO SÀN DÀY 80mm
STEP 02
BƯỚC 02
STEP 03 BƯỚC 03
STEP 02 BƯỚC 02
STEP 01 BƯỚC 01
1 - INSTALL PLYWOOD FOR SLAB
2 - ĐẶT CÁC TẤM VÁN ÉP CHO SÀN
STEP 03 BƯỚC 03
EXISTING SOIL
ĐẤT TỰ NHIÊN PLUMBING SỢI NYLON
EXISTING SOIL ĐẤT TỰ NHIÊN
ADJUSTING LEVEL CÂN CHỈNH CAO ĐỘ
2
2
POLYWOOD/ VÁN
1 - EXCAVATION/ ĐÀO ĐẤT
2 - FLATTEN SURFACE/ LÀM PHẲNG BỀ MẶT
INSTALLING FORMWORK SEQUENCE FOR SLAB QUY TRÌNH LẮP DỰNG CỐP PHA CHO SÀN
INSTALLING FORMWORK SEQUENCE FOR BEAM QUY TRÌNH LẮP DỰNG CỐP PHA CHO DẦM
CỐP PHA ĐIỂN HÌNH DẦM SÀN CHO HẦM B1,B2,B3,B4 TRÊN NỀN ĐẤT SÉT - PHƯƠNG ÁN 2
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MƠ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
BIỆN PHÁP LẮP DỰNG COPPHA DẦM SÀN TRÊN MẶT ĐẤT - PA2
CỐP PHA ĐIỂN HÌNH DẦM SÀN CHO HẦM B1,B2,B3,B4 TRÊN NỀN ĐẤT SÉT - PHƯƠNG ÁN 2
Trang 5ÐÁY MĨNG/ BOTTOM OF PC
600 BPILECAP 600
TY/ TIE Ø17@1000
VÁN/ PLYWOOD TK 17mm
HOLLOW STEEL BOX [ ] 50x50@300mm HOLLOW STEEL 2x[ ] 50x100@1000mm
HOLLOW STEEL [ ] 50x100
RÃNH THU NƯỚC
TIE Ø17@1000mm VÁN/ PLYWOOD ThK 17mm
HOLLOW STEEL [ ] 50X50X1.8@300mm
D49 OR [ ]50x50 £@2000mm
CHI TIẾT 2 DETAIL 2 WATER SUMPS TANK
THÉP CHỜ DẦM (CHI TIẾT A/ DETAIL A)
MẶT BẰNG COFFA VÁN ĐIỂN HÌNH CHO MĨNG CAO 1500mm TYPICAL DETAIL OF PLYWOOD FORMWORK FOR PILE CAP WITH
HEIGHT H=1500mm
BƯỚC 4: THI CƠNG CỐT THÉP MĨNG
STEP 4: INSTALLING REBAR PILE CAP
BƯỚC 5: THI CƠNG COFFA MĨNG
STEP 5: INSTALLING FORMWORK OF PILE CAP
BƯỚC 6: ĐỔ BÊ TƠNG MĨNG ĐẾN COTE ĐÁY SÀN HẦM
STEP 6: POURING CONCRETE TO BOTTOM OF BASEMENT SLAB
BƯỚC 7: THÁO COFFA, LẤP CÁT SAN LẤP
STEP 7: REMOVAL FORMWORK, BACKFILL BY SAND AT SITE
BƯỚC 8: THI CƠNG ĐÀ KIỀNG BẰNG CỐP PHA GẠCH AAC VÀ SÀN HẦM
STEP 8: CONSTRUCTION FOUNDATION BEAM BY AAC FORMWORK AND BASEMENT SLAB
FOUNDATION BEAM (REVIEW METHOD IN NEXT DRAWING) DẦM MĨNG (XEM BPTC)
BASEMENT SLAB SÀN HẦM
BPILECAP
BPILECAP
BƯỚC 1: ĐÀO XUỐNG COTE ĐÁY BÊ TƠNG LĨT MĨNG
STEP 1: EXCAVATION TO LEVEL BOTTOM OF LEAN CONCRETE OF PILE CAP
BƯỚC 2: ĐÀO RÃNH THU NƯỚC MẶT
STEP 2: EXCAVATION WATERWAY
BƯỚC 3: ĐỔ BÊ TƠNG LĨT MĨNG VÀ BÊ TƠNG ĐẦU CỌC
STEP 3: POURING LEAN CONCRETE AND HEAD PILE
600
CUT PILE CONCRETE LEVEL
CAO ĐỘ CẮT CỌC
600
SECTION 1-1
BPILECAP
CỌC GỖ/WOOD PILE
HOLLOW STEEL [ ] 50x100x1.8
DETAIL 2
£1000 £1000 £1000
ÐÁY SÀN/ BOTTOM SLAB
CÂY CHỐNG/ STEEL SUPPORT D49 OR [ ]50x50 £@2000mm
ÐÁY MĨNG/ BOTTOM PILECAP
ÐÁY MĨNG/ BOTTOM OF PILECAP
ÐÁY MĨNG/ BOTTOM OF PC
ĐỈNH SÀN HẦM/ TOP OF BASEMENT SLAB
GHI CHÚ:
- BIỆN PHÁP COFFA THI CÔNG TÙY THUỘC VÀO ĐỊA HÌNH THỰC TẾ CHO PHÙ HỢP VÀ ĐÚNG KỸ THUẬT METHOD FORMWORK CONSTRUCTION CUSTOMIZED IN THE REAL SITUATION FOR FITNESS AND TECHNICALLY CORRECT
- BIỆN PHÁP THI CÔNG NEO, CHỐNG KHÔNG ĐƯỢC HÀN VÀO THÉP KẾT CẤU CHÍNH METHOD STATEMENT OF ANCHOR, STRUD CAN NOT WELDED TO MAIN STRUCTURE
ÐÁY SÀN/ BOTTOM SLAB
ÐÁY SÀN/ BOTTOM OF SLAB
MAKE ROUGH BY RUGASOL TẠO NHÁM BẰNG RUGASOL
CHI TIẾT 1 DETAIL 1
THÉP BIỆN PHÁP Ø14@£1000mm
CHI TIẾT 1/ DETAIL 1
BÊ TÔNG CONCRETE
THÉP KẾT CẤU MAIN REBAR
THÉP CẤU TẠO CHÂN ³Ø12 CONSTRUCTIVE REBAR ³Ø12
THÉP/ REBAR Ø14@£1000mm
CHI TIẾT A: COFFA GIAO DẦM DETAIL A
600~1500
BƯỚC 01-03 / STEP 01-03
BƯỚC 04-06 / STEP 04-06
BƯỚC 07-08 / STEP 07-08
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MƠ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
CỐP PHA VÁN CHO MĨNG
WATER SUMPS TANK
Trang 6BƯỚC 1: ĐÀO XUỐNG COTE ĐÁY BÊ TƠNG LĨT MĨNG, DẦM MĨNG
STEP 1: EXCAVATION TO BOTTOM LEVEL OF LEAN CONCRETE OF PILECAP, FOUNDATION BEAM
BƯỚC 2: ĐÀO RÃNH THU NƯỚC MẶT
STEP 2: EXCAVATION WATERWAY
BƯỚC 3: ĐỔ BÊ TƠNG LĨT MĨNG VÀ BÊ TƠNG ĐẦU CỌC
STEP 3: POURING LEAN CONCRETE AND HEAD PILE
600
LEAN CONCRETE PILECAP
BÊ TƠNG LĨT MĨNG
600
CUT PILE CONCRETE LEVEL
CAO ĐỘ CẮT CỌC
BƯỚC 8: THI CƠNG COPPHA ĐÀ KIỀNG BẰNG GẠCH AAC
STEP 8: CONSTRUCT BEAM FOUNDATION FORMWORK BY AAC
BƯỚC 9: THI CƠNG CỐT THÉP VÀ ĐỔ BÊ TƠNG MĨNG, ĐÀ KIỀNG VÀ SÀN HẦM
STEP 9: INSTALL REBAR AND POUR CONCRETE FOR PILECAP, BEAM FOUNDATION AND BASEMENT SLAB
BPILECAP
BƯỚC 4: THI CƠNG LẮP DỰNG COFFA TOLE
STEP 4: INSTALLING FORMWORK BY TOLE
BƯỚC 5: LẤP ĐẦM ĐẤT ĐẾN ĐÁY BÊ TƠNG LĨT SÀN HẦM
STEP 5: BACKFILL SOIL TO BOTTOM LEAN CONCRETE BASEMENT SLAB
BƯỚC 6: ĐỔ BÊ TƠNG LĨT CHO ĐÀ KIỀNG
STEP 6: POURING LEAN CONCRETE FOR BEAM FOUNDATION
BƯỚC 7: THÁO CÂY CHỐNG
STEP 7: REMOVAL STEEL SUPPORT
BPILECAP
FORMWORK BY TOLE (DETAIL 1) COFFA TÔN (CHI TIẾT 1)
THÉP Ø8@1000 STEEL Ø8@1000
CÂY CHỐNG/ STEEL SUPPORT Ø49 or [ ]50x50
FORMWORK BY TOLE (DETAIL 1) COFFA TÔN (CHI TIẾT 1)
THÉP Ø8£@1000 NEO VÀO BÊ TƠNG
STEEL SUPPORT
MẶT BẰNG CHI TIẾT COFFA TOLE ĐIỂN HÌNH CHO MĨNG CHIỀU CAO H=1500mm TYPICAL DETAIL OF TOLE FORMWORK FOR PILECAP WITH HEIGHT H=1500mm
DẦM MĨNG BEAM PILECAP
SECTION 2-2
ÐÁY MĨNG/ BOTTOM PILECAP
[ ]40x40x1.2 or [ ]50x50x1.2
380 380
400
[ ]40x40x1.2 or [ ]50x50x1.2
400
[ ]40x40x1.2 or [ ]50x50x1.2
CHI TIẾT 1: COFFA TOLE DETAIL 1: FORMWORK BY TOLE
MODUL 800x1100
MODUL 400x1100 MODUL 700x400
SỬ DỤNG TẠI VỊ TRÍ ĐÁY LIÊN KẾT DẦM MÓNG USING AT LOCATION LINK BOTTOM BEAM PILECAP
CỬ THÉP Ø10@500 STEEL Ø10@500
GHI CHÚ: CÁC TẤM KHƠNG ĐIỂN HÌNH ĐO THEO THỰC TẾ THI CƠNG NOTE: ATYPICAL PLATE MEASURING BY ACTUAL CONSTRUCTION
GHI CHÚ:
- BIỆN PHÁP COFFA THI CÔNG TÙY THUỘC VÀO ĐỊA HÌNH THỰC TẾ CHO PHÙ HỢP VÀ ĐÚNG KỸ THUẬT METHOD FORMWORK CONSTRUCTION CUSTOMIZED IN THE REAL SITUATION FOR FITNESS AND TECHNICALLY CORRECT
- BIỆN PHÁP THI CÔNG NEO, CHỐNG KHÔNG ĐƯỢC HÀN VÀO THÉP KẾT CẤU CHÍNH METHOD STATEMENT OF ANCHOR, STRUD CAN NOT WELDED TO MAIN REBAR
ÐÁY SÀN/ BOTTOM SLAB
ÐÁY SÀN/ BOTTOM SLAB
FOUNDATION BEAM (REVIEW METHOD IN NEXT DRAWING)
DẦM MĨNG (XEM BPTC) BASEMENT SLAB
SÀN HẦM
BPILECAP
ÐÁY MĨNG/ BOTTOM OF PC
ĐỈNH SÀN HẦM/ TOP OF BASEMENT SLAB
BƯỚC 01-03 / STEP 01-03
BƯỚC 04-07 / STEP 04-07
BƯỚC 08-09 / STEP 08-09
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MƠ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
CỐP PHA TOLE CHO MĨNG
THÉP Ø10 MĨC VÀO TẤM CỐP PHA TOLE TẤM CỐP PHA TOLE
TẤM ĐAN BÊ TƠNG CỐT THÉP
*** CĨ THỂ SỬ DỤNG TẤM ĐAN BÊ TƠNG CỐT THÉP + THÉP D10 ĐỂ NEO GIỮ TẤM CỐP PHA TOLE
Trang 7BÊ TÔNG LÓT DẦM/ LEAN CONCRETE
BƯỚC 01: ĐỔ BÊ TÔNG LÓT DẦM MÓNG
STEP 01: POURING LEAN CONCRETE FOUNDATION BEAM
COFFA AAC FORMWORK AAC
BƯỚC 2: LẮP COFFA TẤM GẠCH KHÍ CHƯNG ÁP (AAC) STEP 2: INSTALLING FORMWORK AAC
CỬ NEO THÉP ³Ø12
@500
CHỐNG STRUT
TÔN THÉP (1 mét/ 1 cái)
(LIÊN KẾT BẰNG VÍT HOẶC ĐINH VÀO TẤM ACC)
BƯỚC 3: LẤP ĐẤT VÀ ĐỔ BÊ TÔNG LÓT SÀN HẦM STEP 3: BACKFILL SOIL AND POURING LEAN CONCRETE BASEMENT SLAB
BƯỚC 4: THI CÔNG CỐT THÉP VÀ ĐỔ BÊ TÔNG DẦM SÀN HẦM STEP 4: CONSTRUCTION REBAR AND POURING BEAM, SLAB BASEMENT
CHI TIẾT LIÊN KẾT 2 TẤM AAC
COFFA AAC FORMWORK AAC
TÔN THÉP (LIÊN KẾT BẰNG VÍT HOẶC ĐINH VÀO TẤM ACC)
LẤP CÁT SAN LẤP BACKFILL AT SITE SAND
COFFA AAC (SỬ DỤNG TẤM 200/300/400/500x600 DÀY 65) FORMWORK AAC (USING PLATE 200/300/400/500x600 THICK 65)
XỬ LÝ KÍN NƯỚC BẰNG VỮA TREAMENT WATERTIGHT BY MOTAR
XỬ LÝ KÍN NƯỚC BẰNG VỮA MỎNG TREAMENT WATERTIGHT BY MOTAR
TÔN THÉP (LIÊN KẾT MẶT NGOÀI BẰNG VÍT HOẶC ĐINH VÀO TẤM ACC)
ĐÁY DẦM MÓNG BOTTOM BEAM
BƯỚC 01/ STEP 01
BƯỚC 02/ STEP 02
BƯỚC 03/ STEP 03
BƯỚC 02/ STEP 02
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
SỬA NGÀY PHÊ DUYỆT MÔ TẢ
PHÊ DUYỆT:
REV DATE APPRVD BY DESCRIPTION
PROJECT/DỰ ÁN:
DEVELOPER/CHỦ ĐẦU TƯ:
STRUCTURE AND MEP CONSULTANT/TƯ VẤN KẾT CẤU
VÀ CƠ ĐIỆN:
PHÊ DUYỆT:
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
GENERAL CONTRACTOR/TỔNG THẦU:
GIÁM ĐỐC DỰ ÁN:
PROJECT DIRECTOR:
CHỈ HUY TRƯỞNG:
SITE MANAGER:
KIỂM TRA:
CHECKED BY:
TRIỂN KHAI:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
DRAWING TITLE/BẢN VẼ:
SCALE/TỶ LỆ: DATE/NGÀY: REV./HIỆU CHỈNH:
00 DRAWING NO./SỐ BẢN VẼ:
CỐP PHA GẠCH KHÍ CHƯNG ÁP (AAC) CHO DẦM
ĐÁY DẦM MÓNG BOTTOM BEAM
Trang 8B
MẶT ĐỨNG CỐP PHA CỘT
CÂY CHỐNG
THÉP HỘP
TI THÉP D16aL3
SÀN BÊ TÔNG
GÔNG NGANG CÂY CHỐNG
MẶT BẰNG CỐP PHA CỘT
A
TI THÉP D16
TI THÉP D16 L1 L1 L1
L3
L1
VÁN ÉP DÀY 18-20mm
THÉP HỘP 50x50aL1 GÔNG NGANG
2L3
CHI TIẾT 1
CHI TIẾT 2
E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
THI CƠNG PHẦN HẦM- CƠNG TÁC PHỤ
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
PROJECT DIRECTOR:
SITE MANAGER:
CHECKED BY:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
00
GHI CHÚ
+ L1 : LÀ KHOẢNG CÁCH XÀ GỒ PHƯƠNG ĐỨNG + L2 : LÀ KHOẢNG CÁCH GÔNG NGANG + L3 : LÀ KHOẢNG CÁCH TY
QUY TRÌNH THI CÔNG
BƯỚC 01: ĐỊNH VỊ VỊ TRÍ CỘT BƯỚC 02: ĐỤC NHÁM BỀ MẶT BÊ TÔNG BƯỚC 03: LẮP ĐẶT CỐT THÉP VÀ NGHIỆM THU BƯỚC 04: LẮP ĐẶT CỐP PHA, CÂY CHỐNG VÀ NGHIỆM THU BƯỚC 05: ĐỔ BÊ TÔNG
BƯỚC 06: KIỂM TRA LẠI ĐỘ THẲNG ĐỨNG, BỀ MẶT MẠCH NGỪNG
VÁN ÉP DÀY 18-20mm
THÉP HỘP
TI THÉP D16a600
GÔNG NGANG ỐNG NHỰA PVC
SÀN BÊ TÔNG
CỮ ĐỊNH VỊ
TI THÉP GIẰNG GÔNG NGANG
THÉP HỘP THÉP HỘP
BIỆN PHÁP CỐP PHA CỘT TOPDOWN
SÀN BÊ TÔNG
BƯỚC 07: THÁO CỐP PHA VÀ CHÈN VỮA ĐẦU CỘT (VỮA KHÔNG CO NGÓT)
Trang 9CHI TIẾT 1 CHI TIẾT 2
VÁN ÉP DÀY 18-20mm
THÉP HỘP
TI THÉP D16a600
GÔNG NGANG ỐNG NHỰA PVC
A
TI THÉP D16 GÔNG NGANG
THÉP HỘP 50x50aL1 DÀY 18-20mmVÁN ÉP TI THÉP D16
A
MẶT ĐỨNG CỐP PHA VÁCH
B
MẶT ĐỨNG CỐP PHA VÁCH
THÉP HỘP 50x50
SÀN BÊ TÔNG
THÉP HỘP 50x50aL1
CÂY CHỐNG
GÔNG NGANG
TI THÉP D16aL3
MẶT BẰNG CỐP PHA VÁCH
CÂY CHỐNG CÂY CHỐNG
CHI TIẾT -1
CHI TIẾT 2
-SÀN BÊ TÔNG
CỮ ĐỊNH VỊ
TI THÉP GIẰNG GÔNG NGANG
THÉP HỘP THÉP HỘP
GHI CHÚ
+ L1 : LÀ KHOẢNG CÁCH XÀ GỒ PHƯƠNG ĐỨNG + L2 : LÀ KHOẢNG CÁCH GÔNG NGANG + L3 : LÀ KHOẢNG CÁCH TY E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
THI CƠNG PHẦN HẦM- CƠNG TÁC PHỤ
REV DATE APPRVD BY
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
PROJECT DIRECTOR:
SITE MANAGER:
CHECKED BY:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
00
SÀN BÊ TÔNG
QUY TRÌNH THI CÔNG
BƯỚC 01: ĐỊNH VỊ VỊ TRÍ VÁCH BƯỚC 02: ĐỤC NHÁM BỀ MẶT BÊ TÔNG BƯỚC 03: LẮP ĐẶT CỐT THÉP VÀ NGHIỆM THU BƯỚC 04: LẮP ĐẶT CỐP PHA, CÂY CHỐNG VÀ NGHIỆM THU BƯỚC 05: ĐỔ BÊ TÔNG
BƯỚC 06: KIỂM TRA LẠI ĐỘ THẲNG ĐỨNG, BỀ MẶT MẠCH NGỪNG
BIỆN PHÁP CỐP PHA VÁCH TOPDOWN
BƯỚC 07: THÁO CỐP PHA VÀ CHÈN VỮA ĐẦU VÁCH (VỮA KHÔNG CO NGÓT)
GÔNG NGANG
TI THÉP
D16aL3
SÀN BÊ TÔNG
Trang 10E-mail Website
ADD
FAX
No 60 Nguyen Dinh Chieu Str
Da Kao Ward, Dist 1, HCMC : contact@ newtecons.vn : www.newtecons.vn
: Floor 5th - 6th, Rosana Tower
: (84-28)3 514 6677
THI CÔNG PHẦN HẦM- CÔNG TÁC PHỤ
APPROVED BY:
PROJECT MANAGEMENT & SUPERVISION CONSULTANT/QLDA & TVGS:
PROJECT DIRECTOR:
SITE MANAGER:
CHECKED BY:
PREPARED BY:
NGUYEN DUC THANH TRAN NGOC DUC
00
2200
500 500 500 500
500 500
:
50x50mm
50x50mm