METHOD SATEMENT OF FIRE SYSTEM FOR OM ACCOMODATION METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM 1 0 2022 05 13 V K Hoan T D Thinh T N Khoa First Issue Rev Date Prepared Checked Approved Details of Revision Owner VUNG ANG II THERMAL POWER LLC Owner’s Engineer TOKYO ELECTRIC POWER SERVICES CO , LTD EPC Contractor PACIFIC CORPORATION JSC Subcontractor HOP LUC CONSTRUCTION JOINT STOCK COMPANY Project VUNG ANG II THERMAL POWER PLANT PROJECT Title METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM Document.
... 42 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM * Some picture about ceiling mount equipment installation: Picture 5.6-4 Dome IP camera installation 43 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM. .. equipment * All the installation of process above base on the design drawings follow in: 45 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM 46 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM + Some picture... 40 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM Picture 5.9-2 Install and align by water leveling Picture 5.9-3 Installation inspection 41 METHOD STATEMENT OF EXTRA LOW VOLTAGE SYSTEM * Equipment