1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

VA2 OM MS ME ES 001 method statement of electrical system rev 0

84 16 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Tiêu đề Method Statement of Electrical System
Tác giả V.K.Hoan, T.D.Thinh, T.N.Khoa
Trường học Vung Ang II Thermal Power LLC
Chuyên ngành Electrical System
Thể loại method statement
Thành phố Tokyo
Định dạng
Số trang 84
Dung lượng 7,58 MB

Cấu trúc

  • 1.1 General discription (4)
  • 1.2 Power supply summary (5)
  • 1.3 Based on documents (6)
  • 2.1 List of materials (7)
  • 2.2 List of machinery & tools (8)
  • 2.3 List of PPE (9)
  • 3.1 Site organization chart (9)
  • 3.2 Manpower for construction (10)
  • 4.1 Coordination at site (10)
  • 4.2 Trình tự công việc / Sequence of work (11)
  • 5.1 Medium voltage (MV) system installation (12)
  • 5.2 Transformer Installation (20)
  • 5.3 Generator Installation (24)
  • 5.4 Electrical underground conduit installation (28)
  • 5.5 Low Voltage Electrical Panel Installation (32)
  • 5.6 Cable ladder and tray installation (36)
  • 5.7 Electrical conduit installation (41)
  • 5.8 Power cabling (46)
  • 5.9 Electrical Equipment installation (53)
  • 5.10 Lightning protection and Earthing installation (66)
  • 6.1 Organization (73)
  • 6.2 Responsibilities (73)
  • 7.1 General (77)

Nội dung

METHOD SATEMENT OF FIRE SYSTEM FOR OM ACCOMODATION METHOD SATEMENT OF FIRE SYSTEM FOR OM ACCOMODATION 1 0 V K Hoan T D Thinh T N Khoa First Issue Rev Date Prepared Checked Approved Details of Revision Owner VUNG ANG II THERMAL POWER LLC Owner’s Engineer TOKYO ELECTRIC POWER SERVICES CO , LTD EPC Contractor PACIFIC CORPORATION JSC Subcontractor HOP LUC CONSTRUCTION JOINT STOCK COMPANY Project VUNG ANG II THERMAL POWER PLANT PROJECT Title METHOD STATEMENT OF ELECTRICAL SYSTEM Document No VA2 OM.

General discription

Electrical system construction methods are essential for various settings, including residential apartments, management houses, multifunctional gyms, healthcare facilities, supermarkets, restaurants, external areas, substations, pumping stations, and sewage treatment plants.

Power supply summary

Transformer Oil immersed type 750KVA-

Figure 1.2.1 Electrical station floor plan

Based on documents

 Standards Required by Statutory Regulations

1 National technical regulation on fire safety for houses and buildings

2 National technical regulation on energy efficient construction works

3 National technical regulation on electrical system of housing and public works

4 National technical regulation on electrical engineering, QCVN QTĐ

NO ITEM STANDARD volume 8: Technical regulations on low voltage 08:2010/BCT

5 Electrical equipment regulations I, II, III, IV 11 TCN

6 Place electrical equipment in houses and public works -

7 Installation of electrical lines in houses and public works -

9 Lightning protection for constructions - Design - construction standards TCVN 9385:2012

10 Lightning protection parts I, II, II, IV TCVN 9888 :2013

11 Ecgonomi - Workplace lighting - Part 1: In the home TCVN 7114-

12 Ecgonomi - Workplace lighting - Part 3: requires safe lighting and protection of outdoor workplaces

13 Artificial lighting outside public works and urban infrastructure engineering - Design standards

14 Power cables with extruded insulation and their accessories for rated voltages Cables IEC 60502

15 Conductors of Insluated Cables IEC 60228

16 Power transformers – General Transformer IEC

17 A new standard on Switchgear and Controlgear Assemblies Switchboard IEC

18 Rotating electrical machines Diesel IEC 60034

19 Protection of structrures and open areas against lightning using Early Streamer Emission air terminals

List of materials

Materials use at project for install of electrical system: Transformer, Generator, Medium voltage cable,LV electrical panel, Cabinets voltage, Cable ladder & tray, power cable, Electrical equipment, conduit,….

List of machinery & tools

No Name Unit Quantity Note

1 Drilling machine Pcs 1pcs/5 person

3 Electrical jack Pcs 1pcs/5 person

4 Cutting machine Pcs 1pcs/5 person

5 Electrical Panel Pcs 1pcs/5 person

8 Hand tools Pcs 1pcs/1 person

9 Measuring tape Pcs 1pcs/1 person

10 Line marker Pcs 1pcs/1 person

Table 2.1 List of tools and machinery

+ Note: The certificated and relevant document of the special equipment will be submitted prior to use at site.

List of PPE

1 Hi vis 7 Half Rubber Coated Gloves

2 Safety shoes 8 Plastic coated gloves

Table 2.2 List of safety equipment mobilization

Site organization chart

TA DUC THINH Deputy Site Manager 0982.351.435

TRINH NGOC KHOA Site Manager 090.3468.016

DO DINH HUONG Mechanical Engineer 0359.445.933

Manpower for construction

No Work item Quantity Scope of work

1 Mechanical worker 5 Workers are rotated from one item to another depending on the actual construction

Coordination at site

- Survey at site before the installation

- Survey and understand the current progress of the main structure and the site with reference to Safety Management System and contract requirement and engineering due diligence

Multi-functional gym and health care house

Trình tự công việc / Sequence of work

- Listing for all materials used for electrical system, making plan for submission, purchasing and installation

- Listing for all shopdrawing used for electrical system, making plan for submission and installation

- Listing for all methodstatement used for electrical system, making plan for submission and installation

Proceed to other related works

Refer to the shop drawings and the project's MEP technical specification to make an installation methodology for the electrical system

Medium voltage (MV) system installation

- Describe electrical works relate with installating of medium voltage systems

Works are execute base on construction schedule and detailed approval drawing a Material:

Medium voltage concrete pole, medium voltage equipment (Transformer, isolator, outdoor isolator switch, recloser circuit breaker 35kV-630A, support, etc.), medium voltage cable

- Material background check: origin, date of manufacture, assembly drawings, schematics diagrams, technical specifications with test run data, CO, CQ

When positioning materials, it is crucial to assess the risks of mechanical damage Materials should not be situated near moving vehicles, particularly close to the curb, as this increases the likelihood of being hit by heavy vehicles on the roadway or those entering or exiting driveways.

- Tools and equipment for installation must suitable with the manufacturer's instructions b Preparation

- Check Medium voltage system location follow to approved shop drawing are ready for installation

- Check the route to transport material, equipment of MV system to the installation location

- Determine actual correct type of material as per position need to install follow to approval drawing

- Determine actual, correct & type of support(angle bars, c-channel) and bolt, nut as per type of equipment and installation position

- Prepare sand, 1x2 stone, rebar, wood plates, cement to pour the column foundation

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Clean and flatten bottom of pit

- Make formwork and put in pit

- Cut, bend, tie the rebar and put in the pit

- All steps of pouring the pole foundation follow the Civil construction method of concrete pouring

Picture 5.1-1 Cross section drawing of pole foundation

- After pouring concrete, the column foundation must wait for the allowed number of days to be erected

- Clean pole foundation before erection

- Re-check collisions with other systems while lifting process

- Accurately locate the center of the pole After the pole has been put into position, adjust the pole to vertical

- Grout void between pole base and foundation Use non-shrinking or expanding concrete grout firmly packed in entire void space

+ Some picture about the medium voltage pole erection work:

Picture 5.1-2 Poles erection by crain

- Install support and secure them firmly before installing MV equipments

- Determine actual correct type of support as per MV equipment and position need to install follow to approval drawing

- Lift or winch each support to the correct position and tighten the bolts

- After checking that all supports are in place and firmly fixed, Determine correct type of equipment for each position according to the approval shop drawings

- Install each equipment and fix it firmly by bolts and nuts of the correct manufacturer’s type

Picture 5.1-3 Detailled MV equipment support installation

Picture 5.1-4 Detailled MV equipment installation + MV cable pulling and laying

Attention before lay, stretch cable :

- The anchorage of the cable tension section must be temporarily increased: the anchor corresponds to the anchorage for preparation for tensioning

- Corridor of cable pulling route must be cleared to ensure enough conditions for rope pulling

- At the intersections that need scaffolding to support the wire, the scaffolding must be made firmly Special locations will have their own detailed methodology

- Hanging Puly, erect scaffolding to support the cable to cross the road

- Transport cable drum to laying, pulling location

To ensure a safe cable pulling process, the cable from the drum should be routed through the pulley, and the signaling system must be checked for any issues Once confirmed that the signal is clear, proceed with the command to pull the cable It is essential to pull slowly, maintaining the cable in a natural position on the ground to prevent any damage during the operation.

- When pulling the cable, the cable drum are placed on the cable drum support dedicated to the uncoil cable

- After putting the cable on the pole, proceed to lock the cable

- Stretch the cable to get the deflection according to the design

- Proceed to lock in place by cable belt after stretching enough deflection

- Details of cable pulling, laying and connection can be refer in section 5.8.3

Picture 5.1-5 Cable pulling and stretch cable get design deflection

Picture 5.1-6 Installation and connection on pole

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment

• Check tightening connection bolts between components

• Check the cable connection to the equipment

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment by PAC’s Inspector

• Check tightening connection bolts between components

• Check the power cable connection to the devices

• Continuty and insulation test record

Transformer Installation

- Describe electrical works relate with installating of Transformer Oil immersed type 750KVA-35(22)/0.4KV Y/∆/YO-12-11

5.2.2 Biện pháp thi công/ Method statement

Works are execute base on construction schedule and detailed approval drawing a Equipment

Transformer Oil immersed type 750KVA-35(22)/0.4KV Y/∆/YO-12-11

- Transformer shall be standard manufacture’s as per approved type

- As per approved shop catalogue manufacture b Preparation

- The work shall be start when civil works of Transformer room have completed, clean, handed over and approval of installation schedule

- Check Transformer location follow to approved shop drawing at transformer room where the Transformer’s position are ready for installation

- Check the route to transport the genrator to the installation location

- Check floor level of Transformer plinth, check the door hight and wide

- Before construction, it is required to clean the construction site area

- For transformer installed on foundation, floor use means such as rollers, cranes, and lifts etc

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Making of position for Transformer on foundation

- Bring the transformer into installation position by forklift or wooden roller

- secure panel base to the floor/wall using anchor bolts

- Check and align level by bolt, nut leveling before tighten bolt

- After installation, fix the transformer, proceed to connect the ground to the transformer

- Insulation test for cable before connecting the switchboard, record the insulation measurements

To maintain the transformer, start by using a vacuum cleaner for thorough cleaning Ensure all connections are secure by checking for tightened bolts, inspecting the insulation of colored cables, and verifying cable markings Finally, connect the ground wire from the cable tray ladder to the transformer cover for safety.

- Fix the anchor bolt to the plinth

- Check the leveling by adjusting the leveling bolt

- Some picture about the transformer installation work:

Figure 5.2-2 Transport transformer by forklift

Figure 5.2-4 Push transformer into position

- Materials shall be checked for quality, quantity, rating and size

- Check technical installation after setting

• Check position, leveling and condition of Transformer

• Check correct anti vibration base

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, rating and size by PAC’s Inspector

• Check quality of installed Transformers on site

• Check position, leveling, rating and condition of Transformers

• Check correct components of Transformer

• Check correct anti vibration base

- Take a sample of circulating cooling oil for testing and take test record

Generator Installation

- Describe electrical works relate with installating of Generator 750KVA-

Works are execute base on construction schedule and detailed approval drawing a Equipment

Generator 380V/220V AC, 3 phase, 4 wire - capacity 750/825kVA, with noise shell :

• Engine brand: VMAN (German technology), Made in: China Model: D22AZ

• Alternator brand: VMAN Made in China Model: VA750

• Controller: VMAN Made in China Model: VMAN4.0

- Generator shall be standard manufacture’s as per approved type

- Size, type: As per approved catalogue manufacture b Preparation

- The work shall be start when civil works of Generator room have completed, clean, handed over and approval of installation schedule

- Check Generator location follow to approved shop drawing at generator room where the Generator’s position are ready for installation

- Check the route to transport the genrator to the installation location

- Check floor level of Generator plinth, check the door hight and wide

- Before construction, it is required to clean the construction site area

- Use means such as rollers, cranes, and lifts etc

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Making of position for Generator on foundation

- Secure panel base to the floor/wall using anchor bolts

- Check the leveling before tighten bolt

- After installation, fix the electrical cabinet, proceed to connect the ground to the cabinet

- Insulation test for cable before connecting the switchboard, record the insulation measurements

To maintain your generator, start by vacuuming it thoroughly to remove dust and debris Next, inspect all connections for any loose bolts, ensuring that the insulation on colored cables is intact and that cable markings are clear Finally, connect the ground wire from the cable tray ladder securely to the generator cover for safety.

- Fix the anchor bolt to the plinth

- Check the leveling by adjusting the leveling bolt

+ Some picture about the Generator installation work:

Picture 5.2-1: Transport generator to installation location by forklift

Picture 5.2-2: Fix the generator position

Picture 5.2-3: Check generator after installation

- Materials shall be checked for quality, quantity, capacity

- Check technical installation after setting

• Check position, leveling and condition of generator

• Check correct anti vibration base

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, capacity by PAC’s Inspector

• Check quality of installed generator on site

• Check position, leveling, rating and condition of generator

• Check correct components of generator

• Check correct anti vibration base

Electrical underground conduit installation

- Describe construction works relate with installating of electrical underground conduit

Works are execute base on construction schedule and detailed approval drawing a Material

- Electrical underground conduit must be ordered according to the approved type and manufacturer b Preparation

- Prepare the excavator to excavate ditches to lay conduit

- The work shall be start when installation schedule allowed

- Check Electrical underground conduit location follow to approved shop drawing are ready for installation

- Check the route to transport the Electrical underground conduit to the installation location

- Determine actual, correct size, type of conduit as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Mark the route of underground conduit the ground before excavate

- Re-check collisions with other systems

- Use the excavator to excavate underground duct until the required depth, wide and length

- Check the depth of trench for proper elevation

- Clean to ensure the trench is free from debris and foreign materials

- To execute install electrical underground conduit

- Invite main contractor and consultant to inspect

- Back-fill until the depth 300mm below finish grade then install warning tapes

- After inspect with consultant or take verification piecture, back-fill until finish grade

- Ensure that the back-fill material is properly compacted

- Use conduit cap and electrical tape to seal the exposed terminals on the ground to avoid rocks and foreign objects falling into the conduit

* Some picture about the electrical underground conduit installation work:

Picture 5.7.1 Excavation and conduit installation works

Picture 5.7.2 Install fixed bearing for conduit

- Materials shall be checked for quality, quantity, size, type

- Inspect Electrical underground conduit installation:

• Check location, route of Electrical underground conduit follow to appoval shop drawing

• Check for warning tape laying and take verification photo to save record

• Check for compaction work after back-fill

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

- Inspect electrical underground conduit installation:

• Check location, route of Electrical underground conduit follow to appoval shop drawing

• Check for warning tape laying and take verification photo to save record

• Check for compaction work after back-fill

Low Voltage Electrical Panel Installation

Describe electrical works relate with installating of low voltage electrical panels

Works are execute base on construction schedule and detailed approval drawing a Equipment

Low Voltage Electrical Panel (LV Panel):

- LV panels shall be standard manufacture’s as per approved type

- Size, type: As per approved catalogue manufacture b Preparation

- The work shall be start when civil works of LV panels location have completed, clean, handed over and approval of installation schedule

- Check LV panels location follow to approved shop drawing are ready for installation

- Visually inspect the device for warping, dents, scratches, etc Read the installation instructions of the equipment supplier

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Determine actual, correct & type of panel as per position need to install follow to approval drawing

- Before construction, it is required to clean the construction site area

- For LV panels on the floor, use means such as rollers, cranes, and lifts etc

- Making of position for LV panels on foundation or wall (panel’s position)

- Check the route to transport the LV panels to the installation location

- Secure panel base to the floor/wall using anchor bolts

- Check the leveling before tighten bolt

- After installation, fix the electrical cabinet, proceed to connect the ground to the cabinet

- Insulation test for cable before connecting the switchboard, record the insulation measurements

- LV panels cable connection (refer section 5.8.3)

To maintain electrical safety, regularly clean the electrical cabinet using a vacuum cleaner Inspect all connections for tight bolts, ensure the insulation on colored cables is intact, and verify the markings on the cables Additionally, connect the ground wire from the cable tray ladder to the cabinet cover and seal any openings for input and output cables.

+ Some picture about the LV panels installation work:

Picture 5.5-1 Transport LV panels to installation position by forklift

PHòNG Tủ ĐIệN Hạ THế

Picture 5.5-2 Bring the LV panel into position using wooden rollers and levers

Picture 5.5-3 Panels cleaning after install

Picture 5.5-4 LV panels installation completion

Picture 5.5-5 Checking and internal inspection

- Materials shall be checked for quality, quantity, size, type

• Check position, leveling and condition of LV panels

• Check panel base frame bolt tightening

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

• Check quality of installed LV panels on site

• Check position, leveling, rating and condition of LV panels

• Check correct components of LV panels

Cable ladder and tray installation

- Describe electrical works relate with installating of cable ladder and tray

Works are execute base on construction schedule and detailed approval drawing a Material

- The Cable Ladder and Tray will be standard manufacturer’s galvanized structural steel & with all standard accessories

- As per approved catalogue manufacture

- Prepare angle bars or c-channel or unistrut as supporting

- Prepair anchor bolt, thread rod, nut M10, M12 b Preparation

- The work shall be start when civil works of Cable ladder and tray location have completed, clean, handed over and approval of installation schedule

- Check Cable ladder and tray location follow to approved shop drawing are ready for installation

- Check the route to transport the Cable ladder and tray to the installation location

- Determine actual correct size & type of ladder, tray as per location need to install follow to approval drawing

- Determine actual, correct & type of support(angle bars, c-channel,unistrut, thread rod) as per type of ladder, tray and installation location

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work

- Making of position for Cable ladder and tray support on foundation or wall or ceiling

- Use a laser machine to mark the cable ladder, tray according to the approved drawing

- Re-check collisions with other systems

- Drilling hole & setting of anchor

- Setting thread rod and tghiten by hand tool (at ceiling location)

- Install the support bars for the cable tray with distance 1,2m – 1,5m

- Tighten bolt to fix support after verify correctly elevation of support

- Move each to the support

- Fix 2 adjacent cable ladder/tray by connection of cable ladder/tray and bolt, nut

- Between 2 cable trays connected by grounded braided copper wire

- Aligning cable ladder/tray route correctly in elevation, vertical, horizontal

+ Some picture about the cable ladder and tray installation work:

Picture 5.6-2 Drill hole and setting anchor bolt, thread rod

Picture 5.6-3 Ladder,tray support installation

Picture 5.6-5 Cable tray installati Finishing and installation of cable ladder, tray

- Materials shall be checked for quality, quantity, size, type

- Inspect Cable ladder and tray installation:

• Check position, leveling and condition of Cable ladder and tray

• Check tightening connection bolts between components

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

- Inspect Cable ladder and tray installation:

• Check quality of installed Cable ladder and tray on site

• Check position, leveling, rating and condition of Cable ladder and tray

• Check correct components of Cable ladder,tray and connection

Electrical conduit installation

- Describe electrical works relate with installating of electrical conduits for protection of power cabling

Works are execute base on construction schedule and detailed approval drawing a Material

- Electrical conduit must be ordered from an approved type and manufacturer b Preparation

- Check Electrical conduit location follow to approved shop drawing are ready for proceed work

- Determine actual, correct & type of conduit as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work:

* PVC conduit on concrete floor

- Install PVC conduit exaclly of switch, Joint box in the wall/ floor follow shop drawing approved

- Use painting or pen colour marking location Switch, Junction box…

- After finish layer 1 rebar, and then install conduit exaclly area Fix conduit strong on rebar

- After install conduit finish we wiring iron fix all conduit Between 2 wiring fix conduit under 800mm- 1000mm

- Install conduit must follow area equipment and structure on floor

To optimize sound distribution, position two sound boxes 10 to 15 meters apart and incorporate an additional intermediate sound box Ensure that the pipes connecting the boxes are securely joined with joints and bonded using plastic pipe glue, while also being firmly reinforced to the floor with iron supports.

- Boxed inside the wall/ floor, we have push polyform and taping

- All Boxed must fix strong on the wall/ floor by wiring iron, 1 side boxe tangent coffa From boxes to wiring maxium 300mm

When installing pipelines with two or more parallel pipes, it is essential to maintain a minimum distance of 20mm between the inner edges of adjacent pipes This spacing is crucial to facilitate proper concrete insertion, excluding the areas where the pipes connect to an intermediate box.

To ensure optimal installation, it is crucial that the pipes on the cabinet and their ends on the equipment are securely reinforced Additionally, there must be a minimum distance of 20mm between the inner edges of adjacent pipes to maintain proper spacing and functionality.

- Before casting conrecte must be check all boxed and conduit and during time we have 1 worker checking full time

* Electrical conduit conceal in wall

- The job cutting walls are deployed after construction was complete walls and has been hand over by the parties

When conducting a deployment cut for a wall, it is crucial that the cut aligns precisely with the pipe installation requirements The width of the wall cut should exceed the pipe diameter by at least 20 mm, while the depth of the cut must be greater than the pipe size by approximately 5 to 10 mm to ensure a proper fit.

- Marker the position of the switch and box in brick as approved drawings

- After finishing layer of bricks, the contractor will pipe marking on brick wall with 2 lines marked as pipe size, distance & number installed

- Use cutting tool or specialized cutters to cut brick wall exactly with 2-way marking and around box or cabinet

- Installation PVC conduit with sound box & room cabinet by threaded connection as approved drawing

- The conceal box must twist screw and filled with foam in box and taped to prevent sticking motar on the box

- Location as buit of pipe must be saved before to plastering

- The pipe must be fix to steel to prevent movement during plastering

- Use specialized stuccos and ciments wall to phaster where installed PVC conduits

* PVC conduit floating on ceilings, walls:

Conduit size Maximum distance between 2 saddle ỉ20 ≤1.0 m ỉ 25 ≤1.2 m ỉ 32 ≤1.5 m

Maximum distance from connection box to saddles : 0.3 m

Chi tiết lắp đặt ổng điện nổi/Detailled conduit installation

+ Some picture about the electrical conduit installation work:

- Materials shall be checked for quality, quantity, size, type

• Check position, route of Electrical conduit follow to approval shop drawing

• Check the physical condition of the conduit after installation (no distortion, damage )

• Check the inside of the pipe: there are no obstructions (bricks, mortar, etc.) to avoid blockages during cable pulling

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type by PAC’s Inspector

• Check position, route of Electrical conduit follow to approval shop drawing

• Check the physical condition of the conduit after installation (no distortion, damage )

• Check the inside of the pipe: there are no obstructions (bricks, mortar, etc.) to avoid blockages during cable pulling

Power cabling

Describe electrical works relate with power cabling

Works are execute base on construction schedule and detailed approval drawing a Material

- Make storage for gathering construction materials

- Gather materials to site or necessary location

- Request the representatives of main contractor and owner to inspect input materials b Preparation

- Prepare specific tools for pulling and laying cables: cable drum rack, rotation shaft, roller, bait wire, cable winch machine (if necessary), cordless crimper, etc

- The work shall be start when cable ladder, tray, underground conduit, conduit have completed and cleaned base on installation schedule

- Check cable route location follow to approved shop drawing are ready for pulling, laying

- Check the route to transport the cable to pulling, laying location

- Based on detailed schedule, approvalled cable route shop drawing, cable schedule to determine actual, correct type of cable as per location need to pull, lay

- The Safety Officer will check the area to ensure no potential incidents before lifting

- Deploy personnel depending on the details progress of construction:

 Each team of 20 to 25 people

 Each crew of 2 to 3 people

When designing an integrated building system, it is essential to combine the HVAC, water supply, ELV electric, electrical, and fire fighting systems to ensure that installations do not overlap Proper cable pulling and laying techniques are crucial for maintaining efficiency and safety within these interconnected systems.

* Pulling cable on ladder & trunking

- Before putting up wide cable conduct discharge each cable wires in rulo cable, using specialized cable discharge arm with large cross section

- Conduct scattered each cable wire by circulating method, prohibits use drag-end scratch and stretch cables

- When all of the cable in a process have finished, conduct rearrange and positioning them in ladder by nylon cable ties, ensure that the parallel cables and no cross,confusion

To install the cable across the floor, an electric winch is mounted on the roof of the technical box to facilitate vertical hooking This process begins with securing the cable into the cable ladder that has already been installed.

To ensure labor safety, the technical box application will be utilized to clean the working platform on all floors To facilitate synchronized operations between the upper and lower levels, as well as with the electric winch operator, contractors will provide radios for effective communication during this process.

To ensure a smooth inspection process, the team leader must oversee the organization of all scattered cable wires along designated lines Each cable line should be clearly marked according to the specifications outlined in the drawings, and these markings must receive approval from the main contractor and consultant.

- All other exceptions and problems encountered during the construction must be reported to suppervidor try to correct, not arbitrarily constructed to avoid serious consequences later

To ensure proper identification of cable phases, mark the two exposed ends of the cable with colored glue, adhering to the approved construction drawings It is essential to maintain the colored tape markings from the moment the cable is pulled until the electrical panel connection is completed.

* Pulling cable method in PVC conduit

- Before pulling the wire, must used bait thread through all the PVC conceal conduit to fix the broken pipes or stuffy concrete during concreting

- PVC conduit conceal are filled befor pulling cable

- Follow shopdrawing approved, prepared raw wire coil and node rope Threaded bait thread in section PVC conduit for pulling wire

To ensure proper identification, mark the two exposed ends of the cable with colored glue, adhering to the approved construction drawings It's essential to maintain the colored tape markings from the moment the cable is pulled until the connection to the electrical cabinet is completed.

When connecting equipment to electrical cabinets, ensure that the wiring length is reasonable for easy connections For ceiling-mounted lights, use a wire length of 20 cm, and for recessed ceiling lights, extend the wire over the gypsum ceiling by 20 cm Additionally, maintain a rectangular length at the electrical cabinets and a wire length of 15 cm for switches.

* After completing work the pull the wire, shall test insulation, between the cables, between phases, continuty test Testing record d Termination:

 Step 1: Prepare plans, materials and construction tools

 Step 2: Make sure all cables are neatly arranged in the electrical cabinet with the right space

 Step 3: Cut the cable and mark the phase

 Step4: Put the cosse in the cable end, the number of holes in the cosse depends on the cable size

 Step5: Use a cordless crimper to press the cosse and cables

 Step 6: Insulated tubing for phase indication

 Step 7: Use a spanner to connect the cosse and the busbar with the appropriate force

 Step 8: Use a marker to mark bolt and bolt positions

+ Some picture about the electrical equipment installation work:

Picture 5.8-3 Arrange cable and fix by cable tie

Picture 5.8-4 Finish cable pulling, laying

Picture 5.8-5 Crimp terminal by cordless hydraulic crimper

Picture 5.8-6 Connect cable into terminal block

Picture 5.8-6 Continuty and insulation test

- Check cable type correctly with appoval cable shop drawing

• Fix cable by cable tie with requirement distance

• Physical check termination work at start point and end point

- Check cable status (start point, end point, cable route )after cable pulling, laying, termination compare with cable shop drawing and detailled cable schedule

- Continuty test and insulation test between phase, neutral, grounding

+ Inspect with Contractor’s and Owner’s Inspector

- Materials (power cable)shall be checked for type by PAC’s Inspector

• Fix cable by cable tie with requirement distance

• Physical check termination work at start point and end point

- Check cable status (start point, end point, cable route )after cable pulling, laying, termination compare with cable shop drawing and detailled cable schedule

- Continuty test and insulation test between phase, neutral, grounding Sub-contractor performs the testing in the presence of the main contractor and the consultant

- Record test report and signed by 3 parties

Electrical Equipment installation

- Describe electrical works relate to installating of electrical equipments

Works are execute base on construction schedule and detailed approval drawing a Material

Outet socket, switch, recessed downlight, recessed fluorescent ceiling light, ceiling mounted lamp, led tube light, wall mounted light, flood lights

- Electrical equipment must be ordered from an approved type and manufacturer b Preparation

- The work shall be start when civil works of Electrical equipment location have completed, clean, handed over and approval of installation schedule

- Check Electrical equipment location follow to approved shop drawing are ready for installation

- Determine actual correct type electrical equipment as per location need to install follow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents before lifting c Installation work:

- Moving wiring device to job site, unpacking and check material inside

- Specify type of equipment follow to shop drawing

- Use wiring cutting tool to take out pvc shell then use screw driver connect wiring to device follow instruction manual

- Fix wiring device on available conceal box by bolt M4

- Use level tool to check level of wiring device

+ Some picture about outlet socket and witch installation work:

Picture 5.9-2 Install and align by water leveling

- Based on partition, column for specify grid line then use laser machine and scale meter for specify location of lighting fixture or depend on ceiling panel frame

- Note: While make shop drawing, we have to combine with HVAC, firefighting, ELV for combine system

- Determine actual correct type of light as per location need to install follow to approval drawing

- Specify support, hanger, fix support with the wall, concrete column

- Marking by marking pen or chalk

- For the long line of lighting, we need use laser machine for checking straight and level

- For the wall mounted lighting: ensure that level, dimension, beautiful

-For the ceiling mounted or concrete surface mounted lighting: ensure that dimension, direction and no gap Use laser machine and scale for check square, parallel and straight

- All the installation & connection of process above base on the symbolic drawings following:

+ Some picture about indoor lighting fixture:

Picture 5.9-6 Connect power cable to lamp

Picture 5.9-7 Complete and inspect indoor lighting system

To ensure optimal lighting along the road, erect poles in alignment with the theoretical profile, maintaining both horizontal and vertical alignment Additionally, brackets should be positioned at a 90-degree angle to the road's longitudinal axis for effective light distribution.

- Install lighting poles as follows:

• Determine actual correct type of light as per location need to install follow to approval drawing

• Erection work for lighting poles is after complete the works of the assembly of the lights

• Use web fabric slings (not chain or cable) to raise and set poles

• Install pole to foundation with leveling nuts, and tighten top nuts to torque level recommended by pole manufacturer

• Grout void between pole base and foundation Use non-shrinking or expanding concrete grout firmly packed in entire void space

• Use a short piece of !3-mm diameter pipe to make a drain hole through grout

• Arrange to drain condensation from interior of pole

• Connect earthing wire to lighting poles

• Arrange temporary generator to test the lighting system

All the installation & connection of process above base on the symbolic drawings follow in:

+ Some picture about outdoor lighting system

Picture 5.9-8 Lighting pole lifting, erection

Picture 5.9-10 Road lighting system testing

Picture 5.9-11 Complete and inspect garden ligting system

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment

• Check tightening connection bolts between components

• Check the power cable connection to the devices

• Temporary power supply for testing electrical equipment

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment by PAC’s Inspector

• Check tightening connection bolts between components

• Check the power cable connection to the equipment

• Temporary power supply for testing electrical equipment

Lightning protection and Earthing installation

- Describe electrical works relate with installating of lightning protection and earthing system

Works are execute base on construction schedule and detailed approval drawing a Material

- The Hệ thống trung thế will be standard manufacturer’s galvanized structural steel

- Size, type as per approved shop drawing b Preparation

- Check lightning protection & earthing system location follow to approved shop drawing are ready for installation

- Note: While make shop drawing, we have to combine with structure, architect drawing for make detail installation of lightning pole, cable and test box

- Determine actual type of material as per location need to install flow to approval drawing

- The Safety Officer will check the area to ensure no potential incidents while proceed install c Installation work:

- Based on partition, column for specify grid line then use laser machine and scale meter for specify location of earthing rod, air terminal, test box

- The down conductor 70mm2 bare copper wire shall be connected directly to the mounting base of the lightning arrester by terminal lug

- Determine burying depth of the earthing rod

- Connect rods with copper wire/bar

- Check junctions, welded joints, pit

- Connect to main electric main protective earth MPE, APE, main switch board, building structures…

- All the installation & connection of process above base on the symbolic drawings following:

+ Some picture about lightning protection and earthing installation work:

Picture 5.10-1 Weld earthing cable to earthing rod

Picture 5.10-3 Test resistance for earthing system

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment

• Check tightening connection bolts between components

• Check the connection by welding

+ Inspect with Contractor’s and Owner’s Inspector :

- Materials shall be checked for quality, quantity, size, type according to approvalled shop drawing, document, certificate of equipment by PAC’s Inspector

• Check tightening connection bolts between components

• Check the connection by welding

• Earthing system resistance test record

Organization

HCA Contractor is responsible for ensuring effective Health, Safety, and Environmental (HSE) Field Supervision by appointing a qualified Site HSE Manager, along with an adequate number of Superintendents, Supervisors, and Officers The quantity of these personnel must correspond to the number of direct work employees and the various work locations that require supervision.

- Each isolated area will be arranged with at least one safety officer per a working team

- One full time field safety officer will be arranged for per each 50 workers

- One full time field safety supervisor will be arranged for per each 200 workers

- The Vapco may varify Hsse personnel of CONTRACTOR and its subcontractors during implementation of the Project

VAPCO retains the authority to reject any HCA Contractor or Subcontractor's Site HSE Manager following ongoing competency evaluations In the event of such a rejection, the HCA Contractor is required to submit the CV of a new Site H&S Manager to VAPCO for approval within seven days.

Responsibilities

The Project Manager is responsible for creating the project's Health, Safety, and Environment (HSE) organization and appointing a registered Health and Safety (H&S) Manager This individual will have clearly defined roles, responsibilities, and authority to ensure the effective establishment, implementation, and maintenance of the HSE Management System in compliance with relevant regulations.

The Project Manager provides an organization chart that outlines the site management team responsible for executing the Works This project management team is adequately sized and possesses the necessary experience and competence to effectively implement the Health and Safety management system.

The Project Manager can delegate specific tasks or functions to a member of their management team, granting them the necessary authority to fulfill their responsibilities; however, the ultimate accountability for the project still resides with the Project Manager.

The Project Manager is responsible for establishing effective communication channels to inform employees about Health, Safety, and Environmental (HSE) matters Additionally, he must ensure that all staff members receive the necessary training relevant to their specific roles.

- The Project Manager shall take the lead in developing and promoting initiatives in HSE matters and shall use the management system to establish the required standards

He shall monitor on a regular basis the performance of the workforce under his control in achieving the HSE targets of the project

The Project Manager plays a crucial role in upholding HSE commitments and ensuring accountability within the project management team This involves a comprehensive understanding of the key objectives and requirements outlined in the HES policy, standards, and procedures, which is essential for effectively assigning responsibilities across various levels of supervision.

- Specifically, the Project Manager shall:

- Assure that approved HSE procedures are adopted for defining methods and systems to be applied

- Assure that all relevant laws, regulations and other requirements in matters of HSE are respected

- Maintain HSE relations with Owner, Sub-contractors, Vendors and with Governmental Authorities and organizations for all items regarding HSE

- Overall charge of the Project HSE organization, including medical care and first aid, HSE Training, etc

6.2.2 Responsibilities of the HSE Manager

The HSE Manager will report directly to the Project Manager regarding all health, safety, and environmental (HSE) activities on site This role involves supporting the Project Manager in health and safety matters, promoting HSE programs, and ensuring compliance with all HSE requirements.

- Set up an adequate and strong HSE management system

- Ensure the development and implementation at site on activities described in this plan and other procedures

- Organize site so that work is carried out to the required standard with minimum risk to men, equipment, and materials

- Provides H&S consultancy to project management team

- Report any HSE issues/incident/accident to VAPCO

- Lead and ensure HSE incidents and non-compliances are investigated and corrected;

- Set up an site emergency response plans and procedure

- Leads the development and maintenance of Site Emergency Response Plans and

- Participates in the development of Site Security Plans and Procedures

The development of a strong Health, Safety, and Environment (HSE) culture is essential for achieving excellence in HSE performance This involves creating effective coaching and training plans, overseeing the preparation of training materials, and ensuring the successful delivery of these programs throughout the project.

- Leads the investigation of accidents and incidents

 Conduct and chair the site HSE Monthly Committee Meetings;

- Conduct and chair the weekly, monthly site HSE tours

- Update HSE plans and procedures

- Review and approve subcontractors’ HSE plans/procedures/permit to work

- Review Risk Assessment & JSEA’s when required

- Conduct and chair incident response drills

- Ensure construction methods minimize risk to public & workers e.g through adequate Traffic Management

All equipment delivered to the site must be safe, fully operational, and equipped with appropriate safety devices It is essential that all plant machinery is tested in accordance with HSE Management Plans, and that documentation of all certifications is readily available on-site.

- Manage the H&S organization at site

- Ensure that all activities regarding work safety and hygiene are carried out in accordance with the HES plan and procedures

6.2.3 Responsibilities of H&S Officers (Engineers & staffs)

H&S officers play a vital role in supporting the H&S Manager by ensuring compliance with the H&S plan and related requirements among HCA CONTRACTOR personnel and subcontractors across all work areas.

- They ensure direct supervision and coordination of the Sub-contractors’ activities and day to day contacts with them to deal with any H&S matters

6.2.4 The H&S officers’ general responsibilities include, but not limited to:

- Verifying that all workforce under HCA CONTRACTOR’s direct or indirect responsibility receive appropriate H&S information, induction and training, including supervision and control on the H&S training program by Sub-contractors

- Advising the H&S Manager of any necessary required actions to improve working and living conditions in the field under their individual responsibility

- The H&S officers shall attend tools box meetings

- The H&S officers shall inspect unsafe conditions and acts

- Organizing, managing and recording of meetings with sub-contractors as per the H&S relevant meetings program

- Ensuring adequate levels of working and living conditions by means of regular inspections on housekeeping, hygiene, potable water system, kitchens and canteens, sewer system and waste disposal etc

- Leading accident, incident investigations and attending any major accident investigation in areas under their responsibility and reporting on them to the H&S Manager as per the Accident Reporting Procedure

- Organizing and managing the medical and first aid facilities in areas under their control

- Daily check and regular inspection of PPE

- The H&S officers shall report to the H&S Manager on H&S matters

6.2.5 Responsibilities of Construction Manager, Section Managers and

- Construction Manager, Section Managers and supervisors generally shall assist the Project Manager / the H&S Manager in the execution of their duties

- Being familiar with the requirements and recommendations for Safe Working

Practices Method Statements and Risk Assessments etc applicable to their work place and ensure that they are enforced

- Incorporating H&S instructions into the routine day to day orders and make sure they are understood and obeyed

- Preventing site persons from taking unnecessary risks

To guarantee a safe working environment, it is essential that all operatives and laborers receive appropriate training for their specific tasks This includes ensuring that new employees and subcontractor personnel are well-informed about and adhere to the correct safety and health precautions.

- Checking that all plant and equipment, including power and hand tools are maintained in a good condition and remove from use any defective items

- Maintaining organized, tidy and safe working areas

- Maintaining all welfare facilities in a clean and safe condition

- Ensuring that all operatives/labor are provided with and use approved personal protective equipment

- Ensuring that instructions are given in the use of any potentially hazardous materials

- Ensuring that other persons including Owner representatives, other contractors and members of the public are protected from the work activities of HCA CONTRACTOR and its subcontractors

It is essential to discourage horseplay in the workplace and to take appropriate action against individuals who repeatedly neglect their own health and safety, as well as that of their colleagues and those nearby.

- Stopping any activity on site if there is an immediate risk of injury to any site personnel, or the possibility of a dangerous occurrence happening

- Each section or working groups’ supervisors shall have a skill to monitoring, supervision and instructions through the training courses

6.2.6 Responsibilities of Subcontractors and Vendors Personnel

Every Sub-contractors / Vendors Personnel working on the Project Site shall:

- Comply with all H&S rules and other requirements

- Adhere to this H&S plan and comply with the H&S requirements and procedures These are to be observed as minimum requirements

To ensure compliance with health and safety regulations, it is essential for subcontractors to designate a Health and Safety (H&S) supervisor who will report directly to the site manager This H&S supervisor will assist in overseeing that all activities within the subcontractors' scope of work adhere to project-specific H&S requirements, the established H&S plan, and safe working procedures.

To ensure effective health and safety management on-site, organizations must maintain a sufficient number of health and safety supervisors relative to the total workforce of subcontractors These supervisors play a crucial role in assisting the health and safety officer and enforcing the proper implementation of health and safety procedures throughout the execution of the work.

- Ensure that all of their own personnel are aware of H&S requirements arising from laws, regulations and the contract and observe them by planning appropriate training of their personnel

To ensure workplace safety, it is essential to identify and analyze all potential job hazards that employees may face Implementing necessary preventative and protective measures is crucial, along with providing appropriate personal protective equipment (PPE) tailored to the specific tasks being performed.

- Regularly record site H&S inspections and appropriate inspections for maintenance of installations, plant /equipment, work tools and personal protective equipment, with the objective of identifying early any potential hazard

- Cooperate with HCA CONTRACTOR in investigating incidents, accidents to identify and enforce corrective actions to prevent recurrence

Participate in health and safety meetings and adhere to established coordination procedures to effectively prevent or reduce risks associated with overlapping activities in shared spaces.

General

HCA CONTRACTOR will ensure the availability of medical facilities on-site to provide immediate assistance to workers in case of an incident The site will be equipped with trained first-aid personnel, appropriate first-aid equipment, and facilities, including the assignment of a doctor and a nurse Their qualifications will be submitted to Vapco for approval The medical resources offered by the contractor will comply with local medical support service standards Additionally, the contractor is considering a medical service contract with Ky Anh General Hospital and will provide the necessary documentation to Vapco.

Each work site will ensure effective communication with the Occupational Medical Service, whether it be a hospital or clinic A comprehensive list of nearby hospitals, including their locations and contact numbers, will be prominently displayed in all site offices, including those of subcontractors and camp offices.

- Prior to the start of work, arrangements will be made for medical facilities and medical personnel to be available at the construction Site and the camp

- Effective communication and transportation to care for injured workers will be provided

- Where professional medical services are available, each work Site will set up terms and conditions for use and maintain close communication with them

- A list of the available hospitals including locations and their phone numbers will be displayed at all Site and camp offices including Subcontractors’

- First aid arrangements and how-to use them will be thoroughly covered in inductions and other appropriate training

The medical facility will provide:

- A waiting / reception area, consultation / examination area, treatment area, sick bay / observation area, sanitary facilities, secure storage for drugs and medical equipment and confidential storage of medical records;

A comprehensive inventory of essential medical equipment and supplies is crucial for delivering first aid, immediate treatment, and stabilization of significant illnesses and injuries that may occur during work activities This inventory must include, at a minimum, a bed, stretcher, chair, table, heating, lighting, a sink with a water supply, cabinets, and first aid supplies, such as a portable defibrillator.

- A detailed inventory of medicines and drugs shall be kept and checked regularly

- Plans for medical transport/evacuation of injured or ill Personnel including detailed specifications for a dedicated ambulance and arrangements for on-going care

The Contractor shall appoint at least one nurse with a college degree or higher

His or her roles and responsibilities are to:

- Monitor the health and well-being of all Site employees and notify any adverse trends to the HSE Manager

- Make sure the medical facility is equipped with sufficient and adequate materials, consumables, instruments, and staff to function effectively

- Ensure that the medical facilities are always kept clean and hygienic and ready to use

- Be aware of any dangerous substances in use at Site, and obtain any Material Safety Data Sheets (MSDS) to be able to take proper care when required

- Notify the HSE Manager of any trends with illness or injuries, especially for infectious disease

- Periodically check hygiene conditions of the canteens/restaurants, including all food

- Provide all possible medical assistance and care to improve the condition of persons suffering injury or illness

- Be available to attend accidents/incidents on Site to give medical treatment as required

- Carrying out training programs for construction personnel (First aid training, etc.)

- Dispense pharmaceutical items as prescribed by the doctor and maintain records of prescription drugs

- Keep stock records of pharmaceutical/clinic items, and order replacement items to maintain minimum stock levels

- Periodically check the hygiene conditions of all camps

- Keep accurate records of all medical matters and ensure they are kept strictly ‘Medical in Confidence’ and restrict access to Authorized Persons only

- Prepare a Monthly Report on major activities and topics on medical matters and monthly statistics including trend of patients, etc , for submitting to the HSE Manager

- Provide guidance for HSE Manager on Incident Classifications

- CONTRACTOR will provide the first aid equipment as per regulation of Cicular 19/2016/TT-BYT

The CONTRACTOR will ensure the availability of a fully equipped first aid treatment room, featuring essential amenities such as a bed, stretcher, chair, table, heating, lighting, and a sink with a water supply This room will also include cabinets and necessary first aid supplies, including a portable defibrillator, to effectively address medical emergencies.

- HCA Contractor shall sign a medical service contract with Ky Anh General Hospital therefore a 24/7 first aid service and facility is available

Address: Hung Hoa residential group, Song Tri ward, Ky Anh town, Ha Tinh province

- CONTRACTOR and its Subcontractors will provide First Aid boxes for emergency use only

- CONTRACTOR and its Subcontractors will supply enough First Aid boxes to suit the size of the workforce, and locate them in close proximity to the work areas and check

- The stock of disposable medical items will be maintained according to the number of employees and consumption

- Guidance for medical personnel is one advanced First Aid staff per 50 workers and

- CONTRACTOR will ensure that adequate number of employees is trained in First Aid First

- Aiders will be competent people, trained in First Aid at Work

First Aiders will be easily identifiable by displayed photographs that include their name, location, company, and contact number Each First Aider will wear safety helmets featuring a self-adhesive green cross sticker on both sides The Contractor Site HSE Manager will oversee the design and implementation of high-visibility jackets or vests for First Aiders, ensuring they align with the HSE personnel identification requirements and the BBS safety program or recognition initiative.

To become a "Principal First Aider," an individual must hold a valid certificate from an accredited association, having completed an approved course that culminates in the First Aider at Work Certificate.

- The principal First Aider will always be available at the first aid station of each

- A CONTRACTOR of any incident / accident happening with the required information for the Site H&S Statistics, as per the incident / accident reporting procedure

- The sub-contractor’s H&S supervisor shall ensure liaison between the sub-contractor and the HCA CONTRACTOR Site HSE organization

Evaluate the risk and decide on precautions

Table 1 outlines consequence levels by assigning numerical values that define their impacts on environmental, health and safety, production loss, and property damage In cases of uncertainty regarding which outcome presents a greater risk, it is advisable to evaluate both scenarios and choose the one with the higher risk level.

Where there is doubt as to which outcome would have the highest risk level, both should be considered with the highest one being selected

Negligible impact on strategic objectives Nil/negligible:

Injury, loss, service interruption, environmental/estate impact, impact on reputation impact on quality litigation or complaint

Small variance from overall strategic objective First aid treatment with full recovery

Complaint possible Local low key external interest

Minor: financial loss (up to 5K),service interruption

,environmental/estate impact, impact on reputation, impact on quality

Notable variance from overall strategic objective Medical treatment required up to 3 months to recover

Reportable under RIDDOR(Reporting of Injuries, Diseases and

A moderate financial loss ranging from $5,000 to $200,000 may occur, accompanied by service interruptions lasting over one week This situation can lead to environmental and estate impacts, as well as damage to the organization's reputation Local press and stakeholders are likely to express concern, highlighting the implications on quality Additionally, there is a moderate risk of losing recoverable information, which could result in low-value claims.

Significant variance from overall strategic objective Long term illness or injury (up to one year)

Reportable under RIDDOR Complaint expected/received

A major incident can lead to financial losses ranging from $200,000 to $3 million, along with service interruptions exceeding one month The environmental and estate impacts may further exacerbate service disruptions, resulting in significant reputational damage Such events often attract extensive media attention for over a week, raising serious concerns among stakeholders Additionally, the overall quality of service may decline, increasing the risk of failing to meet established performance standards.

‘excellent’ in annual health check in one or more standards, major loss of information (recoverable) , high value claim or action by HSE anticipated, moderate risk of low value claim

Failure to meet strategic objective threatens independent functioning or stability

The potential consequences of a significant data breach include severe financial losses exceeding $3 million, reputational damage highlighted by national press coverage lasting over three days, and the risk of long-term or permanent loss of critical information affecting service delivery quality External controls may be enforced, and the threat of judicial review looms, with anticipated litigation costs surpassing $1 million Additionally, high-profile breaches involving confidential information, such as patient identities, can lead to the condemnation of buildings or properties, resulting in substantial service disruptions.

Likelihood can be examined with regard to the chance that a particular outcome will happen to any of the following:

• A single person or member of the general public

• The project (more persons potentially exposed)

Table 2 outlines the Likelihood Levels, assigning numerical values to varying degrees of likelihood This variability highlights the importance of using the designated Likelihood Level for a "Project" to ensure the safety and protection of individuals involved.

Scor e Descriptor LIKELIHOOD OF REPEAT EVENT

1 Very unlikely to occur Will only occur in exceptional circumstances

2 Unlikely to occur Unlikely to occur but the potential exists

3 Could occur Reasonable chance of occurring – has happened before on occasions

4 Likely to occur Likely to occur – strong possibility

5 Almost certain to occur The event is expected to occur in most circumstances

• Use the Risk Matrix Tool and guidance in the Risk Assessment pro forma to grade the risk

Negligib le Minor Moderate Major Catastroph ic / Fatal Consequence

A combination of Tables 1 and 2 can be used to evaluate the risk by determining the overall risk level of a particular outcome eventuating

The matrix (Table 3 - Risk Level Matrix) below is shown in the conventional format of

Consequence on the horizontal axis increasing to the right and Likelihood on the vertical axis increasing with height

Escalation of Risk is determined by risk score

Risk level Risk score Escalation level

Extreme Red 15- 25 Board of Directors

High Orange 9-12 Management committee (reporting to Board) Moderate Yellow 6-8 Directorate/Department

Department but monitored at Directorate level

• For an initial risk assessment, the Risk Level is known as the Risk Factor Number

• For a residual risk assessment, the Risk Level is known as the Residual Risk

• In both cases, the risk level dictates the response and timing of risk controls required

The management of risks identified through the risk assessment process will be determined by the risk rating

The amount of effort/resources that are to be committed to an identified risk is determined by the risk score The Contractor has a scheme of escalation

• Risks scored 1-5: are considered low risk (L) and therefore risks are accepted

(tolerated) by the Contractor No more countermeasures are required.

Ngày đăng: 15/05/2022, 15:01

TỪ KHÓA LIÊN QUAN

w