PB-Nr: R05.03.03
Machine instruction Sieve station
Issued by Date of release Version Page
Hr. Pfanzagl Oktober 2001 1
1/1
1 Line-up of the filter
Boilers over filter place
cell wheel air-lock switch on filter
switch on boiler
flap open filter, whereby it is to be made sure that the correct filter body is in the
sieve jigger, is attached the bearing play flushing and is adjusted the prescribed
operating pressure.
With the filter discharge connecting piece a transparent bag is fastened with the
quick-locking mechanism. With the over grain discharge a bag is fastened by means
of bungee cords.
2 Cleaning
For the cleaning of the sieve jigger the star-wheel feeder present over it is removed.
The star-wheel feeder is blown off in the suction cab by means of compressed air.
The strainer basket is taken from the sieve jigger and likewise blown off in the
suction cab.
The sieve jigger is cleaned by means of hand and material rags cleaned (if not given
by the production manager differently)
Following the surrounding field by means of vacuum cleaners, and assembled the
sieve jigger again.