Trang 1FOR COMMENT
DN02 UNIT
P0
Title
COMMISSIONING PROCEDURE
FOR UPS SYSTEM OF SITE TEST
KKS
BRU Reg No
840001 Rev
B
Document No
T10206-DN02-P0BRU-840001
Pages –No
Trang 2Table of Contents
1.0 GENERAL PURPOSE 3
1.1 INTRODUCTION AND COMMISSIONING BOUNDARY 3
1.2 SCOPE OF COMMISSIONING PACKAGE 4
1.3 THE SAFETY KNOWLEDGE IN OPERATION 4
2.0 INSPECTION AND TEST ITEMS 6
3.0 ATTACHMENTS 24
Attachment 3.1 UPS Application
Attachment 3.2 Schedule commissioning
Attachment 3.3 Specification of load bank test
Attachment 3.4 Battery test guide
Attachment 3.5 Material safety data sheet
Attachment 3.6 1120069_AC_Relay-UPS
Attachment 3.7 Filling acid Battery Procedure
Trang 31.0 GENERAL PURPOSE
This procedure covers the activities required for testing and commissioning of the following UPS system for Unit 1, 2, consist of the below table
Trang 41.2 SCOPE OF COMMISSIONING PACKAGE
The commissioning package for UPS system, consist of the following packages :
1.3.1 Before the start of any testing it should be confirmed that all power supplies to the system
have been isolated or that they are in a known condition The Commissioning engineer is responsible for the safety of those personnel working of the system Check for the presence of
harmful electrical or mechanical potential energy before starting work
1.3.2 Project lockout / Tagout(LOTO) procedures must be adhere to all test area
1.3.3 Fire is strictly prohibited on site, no smoking there must be a warning mark in hazardous area
1.3.4 Strictly comply with the safety and environmental protection regulations of local government
1.3.5 In order to ensure the reliable operation of every part of the system, strictly obey the
corresponding procedures
1.3.6 Have a regular maintenance for the long-time standby equipment
Trang 51.3.7 Obey the relevant safety regulations of the power plant during commissioning all along
Ensure the successful commissioning work
1.3.8 All personnel directly involved with the commissioning that will attend a kickoff safety meeting
to review for the dangers Ensure that all personnel understand the process and the operation
Any personnel involved in the commissioning have the authority to terminate the operation at
any time, if a serious problem or safety issue develops
1.3.9 Before start up battery commissioning shall be issue concern and shall be open hot work for
battery operation
1.3.10 Before energizing the main power to the system, keep panel heaters on for at least 48 hours
and make sure transformers are dry
1.3.11 Subsequent to commissioning system will be live as batteries need to be kept float charged
Hence access control restrictions has to be implemented for the two rooms
Trang 62.0 INSPECTION AND TEST ITEMS
COVER SHEET SITE ACCEPTANCE TEST
Contact Person at site :
Site Office Address :
Vendor : GUTOR Electronic Asia Pacific Sdn Bhd
Documents included Q 490.101– :
4GB: Rectifier test sheet ( pages) 13GB: Battery: Temperature ( pages)
6GB: Inverter test sheet ( pages) 15GB: UPS Alarm test sheet
16GB: DC Alarm test sheet
Observe Safety Precautions!
Trang 7GENERAL & PUNCH LIST
OK Installation Check
Rectifier Test Battery Check Inverter Test Bypass Test Bypass Stabilizer Test Battery: Initial Charge Battery: Discharge Test Battery: Specific Gravity Test Options
Alarm Test Functional Test
Operation Instruction supplied to Contractor : Yes
Punchlist : The following outstanding items have to be corrected:
by GUTOR :
Trang 8
Recommendation for system location observed
Climatic recommendation observed
Internal connections (inter cubicle connections)
External connections (permanent / temporary)
System earthing (permanent / temporary)
Temporary Upstream Fuses / Breaker rating AAC
Permanent Upstream Fuses / Breaker rating AAC
Trang 9Mechanical checks completed
AC supply available (permanent / temporary)
Rectifier safe for start-up
Observe Safety Precautions!
Trang 10Mechanical checks completed
AC supply available (permanent / temporary)
Rectifier safe for start-up
Trang 11Batteries cover fitted
Connectors protected against corrosion
Check the cells for leakage
Check the liquid level of each cell
Trang 12Mechanical checks completed
DC supply available (permanent / temporary)
Inverter safe for start-up
Set Value Actual Value
Inverter in synchronism
Auto change-over from inverter to bypass
Auto change-over from bypass to inverter
Date:
Observe Safety Precautions!
Trang 13Mechanical checks completed
AC supply available (permanent / temporary)
Bypass Stabilizer safe for start-up
Trang 14Batteries cover fitted
Connectors protected against corrosion
Check the cells for leakage
Check the liquid level of each cell
Trang 15BATTERY INITIAL CHARGE RECORD
E 720.101 G.096-1GB-1
``
Trang 16Each cell voltage ≥ .Vdc Yes No
BATTERY DISCHARGE RECORD
E 720.101 G.096-1GB-1
Trang 17BATTERY SPECIFIC GRAVITY RECORD
E 720.101 G.096-1GB-1
Trang 18
BATTERY TEMPERATURE
E 720.101 G.096-1GB-1
Trang 19BATTERY CHECK LEVEL ACID LIQUID
E 720.101 G.096-1GB-1
Trang 20BATTERY EQUALIZER CHARGE RECORD
E 720.101 G.096-1GB-1
Charge current: 2.4 Adc Charge voltage: 145.2 V
Trang 21BATTERY DISCHARGE RECORD
E 720.101 G.096-1GB-1
Charge current: 2.4Adc Charge voltage: 154.2 V
Trang 22UPS ALARM TEST GUTOR Order No : 1110285002 Client Tag No : UPS-IT-NPLQ
1.Alarms
a) Perform lamp test and check that all Led’s illuminate
Note that common alarm Led on display is not included
b) Check each individual Alarm for indication
OK
Trang 23UPS FUNCTION TEST
1 Functional test for complete system
Condition: Complete System is working in normal operation and no alarm is pending
● Open Rectifier Main Input Breaker (Q001) => UPS switch over to Battery Operation
● Open Battery Breaker (Q004) => UPS goes to Bypass Operation (EN is closed)
● Close Rectifier Main Breaker (Q001) => UPS switch to Normal Operation
● Close Battery Breaker (Q004) => Batteries will be recharged
● Set System Bypass Operation ON from the User Stack, green LED for EN will ON, display show Bypass
● Set UPS OFF and measure the output voltage in distribution
● Turn Manual Bypass Switch (Q050) from Test to Bypass position
● Open the Rectifier Main Input Breaker (Q001) and Battery Breaker (Q004)
● Turn Manual Bypass Switch (Q050) from Bypass to Test position
● Close the Rectifier Main Input Breaker (Q001)
● Set UPS ON
● Measure DC Voltage via front panel if the voltages within tolerance close the Battery Breaker (Q004)
● After Inverter synchronized with Bypass supply set the system to Bypass Operation ON from the User
Stack
● Turn the Manual Bypass Switch (Q050) from Test to Auto position
● Set system Bypass Operation OFF from the User operation
● Turn Manual Bypass Switch (Q050) from Auto to Test position, Load is supplied by Bypass Main
supply
Stack
System was back to Normal Operation, and reset all the front panel alarm
Trang 243.0 ATTACHMENTS
Attachment 3.1 UPS Application
Attachment 3.2 Schedule commissioning
Attachment 3.3 Specification of load bank test
Attachment 3.4 Battery test guide
Attachment 3.5 Material safety data sheet
Attachment 3.6 1120069_AC_Relay-UPS
Attachment 3.7 Filling acid Battery Procedure