TRENCHING AND CONDUIT STANDARD FOR UNDERGROUND DISTRIBUTION CABLE NETWORKS Published: September 2012 SA Power Networks www.sapowernetworks.com.au TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TECHNICAL STANDARD – TS-085 TS-085: Trenching & Conduit for Underground Distribution Cable Networks REVISION NOTICE: May 2012 September 2012 EXPLANATION Clause 7.2.8 merged into clause 7.0 Updated clause 11.2 and added tables 3A & 3B Updated clause 12.0, 17.12 and Appendices - C, H-1 and H-2 Clause 16.0 is moved and included as clause 8.8 Various tables consolidated for better readability Company name change only No other content of this Technical Standard has been altered Any revision markings are from the May 2012 edition SA Power Networks – SA Power Networks means Distribution Lessor Corporation subject to a two hundred year lease to the partnership of companies trading as SA Power Networks or SA Power Networks in its own right SA Power Networks, ABN 13 332 330 749, a partnership of: Spark Infrastructure SA (No.1) Pty Ltd, ABN 54 091 142 380 Spark Infrastructure SA (No.2) Pty Ltd, ABN 19 091 143 038 Spark Infrastructure SA (No.3) Pty Ltd, ABN 50 091 142 362 each incorporated in Australia CKI Utilities Development Limited, ABN 65 090 718 880 PAI Utilities Development Limited, ABN 82 090 718 951 each incorporated in The Bahamas Anzac Highway, Keswick, South Australia, 5035 SA Power Networks Disclaimer: The use of the information contained in this Technical Standard is at your sole risk The information in this Technical Standard is subject to change without notice SA Power Networks, its agents, instrumentalities, officers and employees: a Make no representations, express or implied, as to the accuracy of the information contained in this Technical Standard; b Accept no liability for any use of the said information or reliance placed on it; and c Make no representations, either expressed or implied, as to the suitability of the said information for any particular purpose SA Power Networks and its agencies and instrumentalities not endorse or in any respect warrant any third party products or services by virtue of any information, material or content referred to or included on, or linked from or to this Technical Standard SA Power Networks Copyright @ 2012: This publication is copyright SA Power Networks reserves to itself all rights in such material You must not reproduce any content of this Technical Standard by any process without first obtaining SA Power Networks permission, except as permitted under the Copyright Act 1968 All rights reserved TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet DATE TS-085: Trenching & Conduit for Underground Distribution Cable Networks 1.0 PURPOSE 2.0 SCOPE 3.0 GRACE PERIOD 4.0 REFERENCES 5.0 DEFINITIONS 6.0 BACKGROUND 12 7.0 CUSTOMER’S RESPONSIBILITIES 12 8.0 CIVIL CONTRACTORS RESPONSIBILITIES 13 8.1 Access Permit Requirements 13 8.2 Safe Edge Shovel Requirements 13 8.3 Civil Works Notification Requirements 14 8.4 Civil Works Compliance Requirements 14 8.5 Civil Works Non-Compliance 14 8.6 Requirements of Changes to Civil Works 15 8.7 Directional Bore Drawing Requirements 15 8.8 Backfilling and Consolidation 15 9.0 RETAINING WALLS 16 9.1 General 16 9.2 Design Consideration for the Retaining Walls 16 9.2.1 Other Design Requirements 18 10.0 TRENCHING 20 TS-085 10.1 General 20 10.2 Trench Requirements for Road Reserve/Crossing 21 10.3 DPTI Requirements for DPTI Controlled Roads 23 10.3.1 DPTI Open Shared Trenching Requirements 23 10.3.2 DPTI Trenchless Boring Requirements 23 10.3.3 DPTI Notification 24 10.3.4 DPTI Traffic Control Notification Process 24 10.3.5 DPTI Emergency Work Requirements 24 10.3.6 DPTI Maintenance Period Requirements 25 10.4 Public Road (Non DPTI Roads) Controlled by Council 25 10.5 Conduits within Railway Boundaries 25 10.5.1 Telecommunications Pilot Cable Only 26 10.5.2 Telecommunications Fibre Optic Only 26 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet CONTENTS TS-085: Trenching & Conduit for Underground Distribution Cable Networks Clearances between Services 26 10.6.1 Vertical Separation between Services 27 10.6.2 Horizontal Separation between Services 28 10.7 Changes in Levels and Directional Changes 29 10.8 Shared Trench Arrangement 30 10.8.1 Typical Shared Trench Cross Sections 31 10.8.2 Trenching for SA Power Networks Telecom Only 31 10.8.3 Typical SA Power Networks only Trench 32 10.8.4 URD Trench Design Requirements 32 10.8.5 Trenching for Retrospective (PLEC Schemes) 32 10.9 Reduced Cover Trenching 32 10.10 Underground Cables on Bridge Crossings 33 10.11 Pit Installations 33 10.12 Cable Location Markers 34 10.13 Trenchless/Directional Boring 34 10.13.1 Requirements for Directional Boring 34 10.14 Hydro Vacuum Excavation 35 11.0 CONDUITS and BENDS REQUIREMENTS 35 11.1 General 35 11.2 Spare Conduit Provision 35 11.2.1 Wherever an electrical cable is buried direct 36 11.2.2 When a cable is installed in a conduit 36 11.2.3 Road Crossings 38 11.3 Conduit Bend Requirements 38 11.4 Conduit Reinforcement 40 11.5 Conduit Sizes 40 11.6 Conduit Cable Entry into Service Pillars 43 11.7 Typical Over to Under Conduit Entry into Ground 43 11.8 Conduits Compliance to AS/NZS Standards 43 11.8.1 Identification of Conduit Sizes 43 11.8.2 Colour of Conduits/Couplings 44 11.9 11.9.1 11.10 Conduit for Directional Boring 44 Drawing Requirements for Directional Boring 44 Conduit Installation (for and up to 33kV) 46 11.10.1 General 46 11.10.2 Requirements for the Conduit Installation 46 11.10.3 Additional Requirements for the Conduit Installation 47 11.10.4 Sealing of Conduits 47 TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet 10.6 TS-085: Trenching & Conduit for Underground Distribution Cable Networks 14.0 EXCAVATION FOR VAULTS AND PIERS 49 15.0 BEDDING SAND FOR LESS THAN 66Kv 49 16.0 POLYMERIC CABLE COVERS / MARKER TAPE 51 17.0 66kV UNDERGROUND CABLE INSTALLATION 51 17.1 Introduction 51 17.2 66kV Design Information 51 17.2.1 Extent of 66kV Civil Work 52 17.2.2 66kV Cable Route Design Changes 52 17.3 66kV Cable Trench Dimensions 52 17.4 66kV Cable Separation from Other Services 52 17.5 66kV Directional Boring 52 17.6 Installation of (66kV) Conduits in Open Trench 53 17.7 Lubrication Points – 66kV 53 17.8 Laying 66kV Cables 53 17.9 Thermocouples – 66kV 53 17.10 Flowable Thermal Backfill in Cable Trenches – 66kV 54 17.10.1 Background Information on FTB 54 17.10.2 General Factors for FTB 54 17.10.3 Installation Requirements for FTB 55 17.11 Bentonite Mixture in Conduits – 66kV 55 17.12 Protective Cover Slabs – 66kV 56 17.13 66kV Sand Backfilling Requirements 56 17.13.1 Sand Backfill – 66kV 56 17.14 Cable Marker Tapes – 66kV 57 17.15 Cable Markers – 66kV 57 17.16 Pits – 66kV 57 17.17 Joint Bays – 66kV 58 18.0 CONTAMINATED SOIL 58 APPENDICES: 59 A: Civil Works Notification & Compliance 59 B: Cable Location Marking Drawings 60 C: Example of Directional Bore Drawing 61 D: Typical Shared Trench Arrangements 62 D-1 Cables Buried Direct – (Shared Trench) 62 TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet 12.0 TRENCHING ON PRIVATE PROPERTY 48 13.0 TRENCHING FOR SINGLE CUSTOMER ON VERGE 49 TS-085: Trenching & Conduit for Underground Distribution Cable Networks (In Footpath or Road Crossing for Non DPTI Roads) 63 E: Typical SA Power Networks Trench Only 64 E-1: Cables Buried Direct - (SA Power Networks Only) 64 (In Footpath for Non DPTI Roads) 64 E-2: Cables in Conduits - (SA Power Networks Only) 65 (In Footpath or Road Crossing for Non DPTI Roads) 65 F: Typical Reduced Cover Trenching 66 G: Typical SA Power Networks Telecomm Trench (Only) 67 H: Trenching on Private Property 68 H-1: Cables in Conduit Cable at 1.0m Cover 68 H-2: Cables in Conduit Cable at 750mm Cover 68 H-3: Cable Buried Direct at 1.0m Cover 69 H-4: Trench for Single Customer on Verge 69 J: Typical Trench Arrangements for 66kV 70 J-1: Typical Flat Arrangement – 66kV - Roadway 70 J-2: Typical Trefoil Arrangement – 66kV - Roadway 71 J-3: Typical Under Bore Arrangement – 66kV Cables 72 K: Typ Over to Under Pipe Entering Detail 73 TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet (In Footpath for Non DPTI Roads) 62 D-2: Cables in Conduits – (Shared Trench) 63 TS-085: Trenching & Conduit for Underground Distribution Cable Networks PURPOSE This Technical Standard specifies the standard trench, conduit, retaining walls and Civil works requirements for a new or upgraded installation that will be a component of SA Power Networks‟ distribution network Once the scope for a trench, conduits, retaining walls and Civil works is determined, then this technical standard will assist the Customer in the Civil component of electrical works/network extension The construction could encompass a network extension, PLEC projects, SA Power Networks‟ capital works, specific arrangements or customer works These works could be on private property or on a public road verge This standard will assist in clarifying the responsibilities of customers regarding agreements, approvals, construction requirements and the SA Power Networks requirements for “Civil Works Compliance” 2.0 SCOPE The specification in this technical standard is applicable (but not limited) to all parties involved in the activities of trenching, conduit installation, retaining walls and Civil works associated with the underground installation or alteration of distribution cable networks This technical standard is to cover all underground trenching and conduit installations; however, section 17.0 is an additional requirement for applications to 66kV underground networks The appendices at the end of this document provides more detailed information on trench arrangements, Civil Works notification and Civil works compliance and cable location markers The “Electricity (General) Regulations 1997”, other statutory authority requirements, AS/NZS standards and the Building Code of Australia (BCA) are the basis of TS-085 For any situation that is not covered in this standard, the requirement of AS/NZS 3000 applies There may be additional requirements and specifications that are project specific For further assistance/information concerning this technical standard, please contact the relevant SA Power Networks‟ Manager This technical standard is available at the SA Power Networks websites below: Intranet website (Internal) Internet website (External) 3.0 GRACE PERIOD The maximum grace period acceptable by SA Power Networks for implementing this Standard is months from the date of publication All projects that are not in receipt of “Specification Compliance” at the revised date of issue for this technical standard will need to incorporate the latest requirements This is applicable to both the design and construction phases of the project The validity period for a “Specification Compliance” is 60 days On the expiry of a “Specification Compliance”, any specification change without a documented exemption must be incorporated into the design and construction of SA Power Networks infrastructure TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet 1.0 TS-085: Trenching & Conduit for Underground Distribution Cable Networks REFERENCES The following listed documents are for additional information It is advisable to refer to the current publications before implementing them Other documentation may be required on a project specific basis For Civil Contractors conducting regular Civil works for any SA Power Networks installations, there is a Civil Construction Manual – 40 available on request This manual details many project specific aspects of Civil works that my not be detailed in this standard Essential Services Commission of South Australia (ESCOSA) Codes: Essential Services Commission of South Australia (ESCOSA) Codes: SA Electricity Distribution Code (EDC) Energy Networks Association (AUS) Publications: ENA NENS 03 - 2006 - National Guidelines for Safe Access to Electrical and Mechanical Apparatus ENA NENS 04 - 2006 - National Guidelines for Safe Approach Distances to Electrical and Mechanical Apparatus South Australian Legislation: This technical standard does not necessarily align with AS/NZS Standards Australia Publications SA Electricity Act 1996 SA Electricity (General) Regulations 1997 SA OHS&W Act 1986 SA OHS&W Regulations 2010 Environment, Heritage and Native Vegetation Protection Acts: Environment Protection Act 1993 Environment Protection Regulations 2009 Aboriginal Heritage Act 1988 Native Vegetation Act 1991 Heritage Places Act 1993 National Parks & Wildlife Act 1972 Natural Resources Management Act 2004 AS/NZS ISO 14001:2004 – Environmental Management System Standard Standards Australia Publications: AS 60038 - Standard Voltages AS/NZS 3000 - Electrical Installations (known as the AS/NZ Wiring Rules) AS/NZS 1158 - Lighting for Roads and Public Spaces Set AS 1345 - Identification of the Contents of Pipes, Conduits and Ducts AS/NZS 2032 - Installation of PVC pipe systems AS/NZS 2053 - Conduits and Fittings for Electrical Installations – Part & - General Requirements AS/NZS 2648.1 - Underground Marking Tape - Non-Detectable Tape AS 2885.1 - Pipelines - Gas and Liquid Petroleum - Design and Construction TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet 4.0 AS/NZS 3500 (Set) - Plumbing and Drainage Set AS 3798 - Guidelines on earthworks for commercial and residential developments AS/NZS 4645.3 - Gas Distribution Networks - Plastics Pipe Systems AS/NZS 4130 - Polyethylene (PE) Pipes for Pressure Applications AS 4678 - Earth-Retaining Structures AS 4799 - Installation of Underground Utility Services and Pipelines within Railway Boundaries AS/NZS ISO 31000 - Risk Management - Principles and Guidelines Note: AS/NZS4360 is superseded and replaced by AS/NZS ISO31000 ASTM STP1331-98 - The Design and Application of Controlled Low-strength Materials (flowable thermal backfill) ASTM STP1459-04 - Innovations In Controlled Low-strength Material (Flowable thermal backfill) AS/ACIF S009 - Installation requirements for customer cabling (Telecommunications Wiring Rules) WSAA Codes - Water Services Association of Australia: WSA 02: Sewerage Code of Australia WSA 03: Water Supply Code of Australia SA Power Networks Documents: Service and Installation Rules Technical Standards NICC Brochures Guidelines for SA Power Networks Crossings of the Electrified DPTI Railway Network Relevant E-Drawing Series; and Civil Construction Manual – 40 5.0 DEFINITIONS AS/NZS – stands for Australia and New Zealand Standards published by Standards Australia Authorised Person – the person in charge of the premises, or the registered electrical worker or licensed electrical Contractor or other person appointed or selected by the person in charge of the premises, to perform specific duties associated with the electrical installation on the premises Boring – refers to activities of directional drilling (typically horizontal or vertical) Cable/s – a wire, conductor or form of material designed for carrying electric current or communications signals, installed underground Customer – has the meaning given to that term in the Electricity Act 1996, namely a person who has a supply of electricity available from a transmission or distribution network for consumption by that person and includes: (a) (b) (c) (d) TS-085 The occupier for the time being of a place to which electricity is supplied; Where the context requires, a person seeking an electricity supply; A person of a class declared by regulation to be customers; and Customer may or may not necessarily be the landowner Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks Customer Agents – Customer agents are parties representing the customers Such parties may include registered electrical workers, licensed electrical Contractors, consulting engineers, architects, and equipment manufacturers CLER – stands for Customer Lighting Equipment Rate DCDB – Digital Cadastral Database (DCDB) or landbase date is obtained from the S.A Govt Department of Environment and Heritage The landbase data includes parcel shapes, parcel line work, parcel text, road centre lines, road names, suburb shapes, suburb text, Local Government Authority shapes and text DPTI – Department of Planning, Transport and Infrastructure Distribution Network – has the meaning given to that term in the Electricity Act 1996, namely the whole or a part of a system for the distribution of electricity, but does not include anything declared by regulation not to be a distribution network or part of a distribution network For the purposes of these rules references to Distribution Network means the network poles, wires, underground cables, padmount transformers, substations etc, operated by SA Power Networks, which transports electricity from the transmission system to a customer‟s Connection Point Excavation Depth – is the vertical distance measured between ground level and the deepest part of the excavation (a) Electricity Infrastructure means – (b) electricity generating plant; and (c) powerlines; and (d) substations for converting, transforming or controlling electricity; and (e) equipment for metering, monitoring or controlling electricity; and (f) any wires, equipment or other things (including tunnels and cavities) used for, or in connection with, the generation, transmission, distribution or supply or electricity Excavation – refers to the activities of digging or trenching and can be by mechanical means or by hand SA Power Networks’ Manager – The SA Power Networks‟ Manager/Responsible Officer serving that area of the customer‟s installation Ground Level – is nominally the final level of the ground that SA Power Networks equipment is to be installed at High Voltage (HV) – For the purpose of this document shall mean a voltage exceeding 1,000V A.C up to and including 33,000V A.C Low Voltage or LV – For the purpose of this document shall mean a nominal voltage exceeding 50V A.C but not exceeding 1,000V A.C MNSP – stands for SA Power Networks‟ Manager Network Standards and Performance MNP – stands for SA Power Networks‟ Manager Network Planning NA – stands for SA Power Networks‟ Network Assets NM – stands for SA Power Networks‟ Network Management TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 10 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-A: Civil Works Notification & Compliance Responsibility APPENDICES: A: Civil Works Notification & Compliance CaMS / BSO (Minor Works only) CaMS / Contract Supervisor (Minor & Major project) Customer (When responsible for Trenching) CPO (Major projects only) Civil Contractor Civil Works Notification Form NICC - 453 available on Intranet and on Internet websites Customer doing the Trenching Fill in B: Contract Supervisor/TSW8 Issue to Customer SA Power Networks doing the Trenching Insert point of Contact: Compliance Co-Ord Issue to Customer as part of Information Pack Customer to forward form to the Contracted Civil Contractor Fill in B: Contract Supervisor/TSW8 Issue to Civil Contractor Return Form to: For a Contestable Project For all other Projects (Contract Supervisor /TSW8) Return Form to: Contract Supervisor /TSW8 Civil Works Compliance Form NICC - 452 available on Intranet and on Internet websites Customer doing the Trenching Insert name of Contract Supervisor/TSW8 Issue to Customer SA Power Networks doing the Trenching TS-085 2 Issue: 03/09/12 Highlight point of contact as Electrical Contractor Issue as part of Information Pack Customer to insert Electrical Contractor details Forward form to Civil Contractor Fill in SA Power Networks’ Contract Supervisor/TSW8 Issue to Civil Contractor Authorised: Jehad Ali Return Form to: Electrical Contractor If unknown, the Customer Return Form to: Electrical Contractor If unknown, Contract Supervisor / TSW8 Date: 03/09/12 Page 59 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-B: Cable Location Marking Drawings WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet B: Cable Location Marking Drawings TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 60 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-C: Example Drawing C: Example of Directional Bore Drawing TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 61 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-D1: Typical Shared Trench Arrangements – Cables Buried Direct WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet D: Typical Shared Trench Arrangements D-1 Cables Buried Direct – (Shared Trench) (In Footpath for Non DPTI Roads) D-1(a): Trench Size: 600mm Wx1200mm D D-1(b): Trench Size: 900mm Wx1200mm D TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 62 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-D2: Typical Shared Trench Arrangements – Cables in Conduits WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet D-2: Cables in Conduits – (Shared Trench) (In Footpath or Road Crossing for Non DPTI Roads) D-2(a): Trench Size: 600mm Wx1200mm D D-2(b): Trench Size: 900mm Wx1200mm D TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 63 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-E1: Typical SA Power Networks Trench Only – Cables in Conduits WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet E: Typical SA Power Networks Trench Only E-1: Cables Buried Direct - (SA Power Networks Only) (In Footpath for Non DPTI Roads) E-1(a): Trench Size: 600mm Wx1200mm D E-1(b): Trench Size: 900mm Wx1200mm D TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 64 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-E2: Typical Shared Trench Arrangements – Cables in Conduits WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet E-2: Cables in Conduits - (SA Power Networks Only) (In Footpath or Road Crossing for Non DPTI Roads) E-2(a): Trench Size: 600mm Wx1200mm D E-2(b): Trench Size: 900mm Wx1200mm D TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 65 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-F: Typical Reduced Cover Trenching F-1(a): TYPICAL REDUCED COVER TRENCH ARRANGEMENT F-1(b): TYPICAL REDUCED COVER TRENCH ARRANGEMENT TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 66 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet F: Typical Reduced Cover Trenching TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-G-1: Typical SA Power Networks Telecommunication Trench Only G-1: Cables in Conduit – (SA Power Networks Telecomm Only) G-1: Trench Size: 600mm Wx1200mm D TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 67 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet G: Typical SA Power Networks Telecomm Trench (Only) TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-H: Trenching on Private Property WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet H: Trenching on Private Property H-1: Cables in Conduit Cable at 1.0m Cover (For more details, refer to clause 12.0 in this document) H-1: Cable in Conduit at 1.0m Cover H-2: Cables in Conduit Cable at 750mm Cover (For more details, refer to clause 12.0 in this document) H-2: Cable in Conduit at 750mm Cover TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 68 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-H: Trenching on Private Property H-3: Cable Buried Direct at 1.0m Cover WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet (For more details, refer to clause 12.0 in this document) H-3: Cable Buried Direct at 1.0m Cover H-4: Trench for Single Customer on Verge (For more details, refer to clause 12.0 in this document) H-4: Trenching for Single Customer on Verge TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 69 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-1: Typical Flat Arrangement - 66kV Cables J: Typical Trench Arrangements for 66kV J-1: Typical Flat Arrangement – 66kV - Roadway J-1: TYPICAL FLAT ARRANGEMENT - 66kV CABLES TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer Page 70 of 73 WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-2: Typical Trefoil Arrangement - 66kV Cable J-2: Typical Trefoil Arrangement – 66kV - Roadway J-2: TYPICAL TREFOIL ARRANGEMENT - 66kV CABLES TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer Page 71 of 73 WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks App-J-3: Typical Under Bore Arrangement - 66kV Cables J-3: Typical Under Bore Arrangement – 66kV Cables J-3: Typical Under Bore Section Arrangement - 66kV CABLES TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer Page 72 of 73 WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet TS-085: Trenching & Conduit for Underground Distribution Cable Networks WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED The most up-to-date version is located on the internet/intranet K: Typ Over to Under Pipe Entering Detail TS-085 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 73 of 73 The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer ... Underground Distribution Cable Networks TS-085: Trenching & Conduit for Underground Distribution Cable Networks NPO/NPM – stands for SA Power Networks Network Project Officer/Manager NSP – stands for. .. TS-085: Trenching & Conduit for Underground Distribution Cable Networks TS-085: Trenching & Conduit for Underground Distribution Cable Networks The Department of Planning, Transport and Infrastructure... D-2: Cables in Conduits – (Shared Trench) 63 TS-085: Trenching & Conduit for Underground Distribution Cable Networks PURPOSE This Technical Standard specifies the standard trench, conduit,