Test Bank for Project Management The Managerial Process 6th Edition Larson Multiple Choice Questions Project managers who understand the role that their project plays in accomplishing
Trang 1Test Bank for Project Management The Managerial Process 6th Edition Larson
Multiple Choice Questions
Project managers who understand the role that their project plays in
accomplishing the organization's strategy are able to do all of the
following EXCEPT
1 A Demonstrate to senior management how their project contributes to the firm's mission.
2 B Explain to team members why certain project objectives and priorities are critical.
3 C Explain to stakeholders why certain project objectives and priorities are critical.
4 D Be able to respond appropriately to delays and/or questions about product design.
5 E Be able to focus on problems or solutions, even if the project is a low priority strategically.
Which of the following would be classified as an organizational
opportunity?
1 A Low debt
2 B Excellent employees
3 C Increasing product demand
4 D Talented management
5 E Government regulation
Which of the following is NOT a problem associated with the absence of a project portfolio system?
1 A Organizational politics
2 B Lack of funding
3 C Resource conflicts
Trang 24 D Multitasking
5 E Implementation gap
Which of the following would be classified as an organizational threat?
1 A Slowing of the economy
2 B Excellent employees
3 C Poor product quality
4 D Declining facilities
5 E High labor costs.
Examples of nonfinancial criteria include all of the following EXCEPT
1 A Capturing a larger market share.
2 B Reducing dependency on unreliable suppliers.
3 C Preventing government intervention and regulation.
4 D Making it difficult for competitors to enter the market.
5 E Calculating the time it will take to recover the project investment.
Which of the following is true of multiweighted scoring models?
1 A Will include quantitative criteria
2 B Will include qualitative criteria
3 C Each criterion is assigned a weight
4 D Projects with higher scores are considered more desirable
5 E All of these are true
A project screening matrix typically contains all of the following EXCEPT
1 A The list of available projects
2 B Specific criteria
3 C Weights assigned to specific criteria
Trang 34 D Costs to complete each project
5 E All of these are typically contained
All of the following are symptoms of organizations struggling with
strategy disconnect and unclear priorities EXCEPT
1 A Frequent conflicts between managers.
2 B Inadequate resources.
3 C Confused employees regarding which projects are more important.
4 D Not enough projects within the portfolio to make a profit.
5 E People are working on multiple projects and feel inefficient.
The following are responsibilities of the governance team when managing
a portfolio system EXCEPT
1 A Deciding how they wish to balance the available organizational resources among the different types of projects.
2 B Publishing the priority of every project and ensuring the process is open and free of power politics.
3 C Evaluating the progress of the projects in the portfolio.
4 D Constant scanning of the external environment to determine if organizational selection criteria need to be changed.
5 E Communicating which projects are approved.
The assessment of the external and internal environments is called
_ analysis
2 B Competitive
3 C Industry
4 D Market
5 E Strategic
Trang 4Projects are usually classified into all but one of the following categories Which one is NOT one of the typical classifications?
1 A Compliance and emergency
2 B Operational
3 C Strategic
4 D Political necessity
5 E All of these are typical classifications
In order to formulate strategies that align with the mission the
organization will need to
1 A Assess internal strengths and weaknesses.
2 B Analyze competitors.
3 C Examine the external environment.
4 D Know their core competencies.
5 E All of these should be considered when formulating strategies.
Which of the following is the correct order for the strategic management process?
1 A Strategies, mission, objectives, projects
2 B Objectives, projects, mission, strategies
3 C Mission, strategies, objectives, projects
4 D Objectives, mission, strategies, projects
5 E Projects, mission, strategies, objectives
Which of the following is NOT true when managing a portfolio system?
1 A The qualities of a particular project are assessed within the context of existing projects
2 B It does not require a constant effort
Trang 53 C Within a small organization it can be managed by a small group of key
employees
4 D It requires input from senior management
5 E It involves monitoring and adjusting criteria to reflect the strategic focus of the organization
Which of the following is NOT true about organizational politics?
1 A Project managers should not engage in organizational politics
2 B Politics can have a significant influence on which projects receive funding
3 C Politics exist in every organization
4 D Politics can influence project selection
5 E Politics can play a role in the aspirations behind projects
Regardless of the criteria differences among different types of projects, the most important criterion for project selection is
1 A How the project will balance risk within the project portfolio
2 B The project's fit to the organization strategy
3 C Compliance
4 D Nonfinancial
5 E Profit
Which of the following is NOT true for strategic management?
1 A It should be done once every few years just before developing the operating plan
2 B It supports consistency of action at every level of the organization
3 C It develops an integrated and coordinated long-term plan of action
4 D It positions the firm to meet the needs of its customers
5 E It involves responding to changes in the external market and allocating scarce resources to improve a competitive position.
Trang 6Why do project managers need to understand their organization's mission and strategy?
1 A To reduce project duration and increase the number of projects implemented
2 B So they can make appropriate decisions and adjustments and be effective project advocates
3 C It is only important for senior management to understand the organization's mission and strategy
4 D To get their job done and increase opportunities for promotion
5 E So that they can make sure the customer is satisfied
Which of the following is NOT true about an organization's strategy?
1 A Strategy determines how an organization will compete
2 B Strategy is implemented through projects
3 C Only top management must understand strategy
4 D Project selection should be clearly aligned with strategy
5 E Project management plays a key role in supporting strategy
A project selection process that is strongly linked to strategy results in
1 A The most profit.
2 B Better utilization of the organization's resources.
3 C More projects.
4 D A larger and more diverse organization.
5 E Stronger core competencies.
Which of the following questions does the organization's mission
statement answer?
1 A What are our long-term strategies?
2 B What are our long-term goals and objectives?
3 C How do we operate in the existing environment?
Trang 74 D What do we want to become?
5 E All of these are answered by the mission statement
Which of the following is NOT one of the characteristics of effective objectives?
1 A Realistic
2 B Assignable
3 C Flexible
4 D Specific
5 E Measurable
The financial model measures the current value of all cash inflows using management's minimum desired rate of return
1 A FUBAR
2 B ARR
3 C IRS
4 D IRB
5 E None of these
Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?
1 A Sacred cow
2 B Pet project
3 C Political necessity
4 D Special undertaking
5 E Strategic ploy
Trang 8One who endorses and lends political support for the completion of a specific project is known as the
1 A Project manager.
2 B CEO.
3 C Project sponsor.
4 D Project lead.
5 E Sacred cow.
Which of the following is NOT one of the traditional components found in mission statements?
1 A Major products and services
2 B Profitability
3 C Target customers and markets
4 D Geographic domain
5 E Contribution to society
Susie's department is implementing many projects She finds herself starting and stopping work on one task to go and work on another task, and then return to the work on the original task Susie is experiencing
1 A Poor scheduling.
2 B Excess work burden.
3 C Flexible tasking.
4 D Multitasking.
5 E Burnout.
Trang 9Which of the following problems refers to lack of understanding and consensus of organization strategy among top and middle-level managers? This also can result when top management formulates strategy and leaves implementation to functional managers
1 A Multitasking
2 B Organization politics
3 C Implementation gap
4 D Resource conflicts
5 E Employee turnover
Project selection criteria are typically classified as
1 A Financial and nonfinancial.
2 B Short-term and long-term.
3 C Strategic and tactical.
4 D Required and optional.
5 E Cost and schedule.
Which of the following is NOT one of the requirements for successful implementation of strategies through projects?
1 A Allocation of resources
2 B Prioritizing of projects
3 C Motivation of project contributors
4 D Adequate planning and control systems
5 E Quality management
True - False Questions
Trang 10A proposed project that ranks high on most criteria may not be selected because the organization's portfolio already includes too many projects with the same characteristics
1 True
2 False
Objectives should be specific, marketable, assignable, realistic, and time related
1 True
2 False
Organizational objectives set targets for all levels of the organization not just for top management
1 True
2 False
Multiweighted scoring models include only quantitative criteria, not qualitative
1 True
2 False
Generally, people working on several projects at the same time are more efficient than people working full-time on one project
1 True
2 False
Project management historically has been preoccupied solely with the planning and execution of projects while strategy was under the purview
of senior management.
1 True
2 False
Trang 11Mission statements typically change frequently, responding to changes in the external environment
1 True
2 False
Project managers should not engage in organizational politics
1 True
2 False
Intermittent scanning of the external environment is required when
managing organization strategy
1 True
2 False
One benefit of project portfolio management is that it can justify killing a project that doesn't support organization strategy
1 True
2 False
Studies have shown that companies using predominantly financial criteria
to prioritize projects yield unbalanced portfolios and projects that aren't strategically aligned
1 True
2 False
Strategy is implemented through projects
1 True
2 False
Trang 12One way to offset the influence of politics on project management within
an organization is to have a well-defined project selection model
1 True
2 False
Strategy formulation ends with cascading objectives or projects assigned
to lower divisions, departments, or individuals
1 True
2 False
The NPV financial model measures the time it will take to recover the project investment
1 True
2 False
If a proposed project does not meet one of the designated "must"
objectives it is immediately removed from consideration
1 True
2 False
The information gap refers to the lack of understanding and consensus of organization strategy among top and middle-level managers
1 True
2 False
Opportunities and threats can be viewed as flip sides of each other; that
is, a threat can be viewed as an opportunity, and vice versa
1 True
2 False
Trang 13The first step in the Strategic Management Process is to set long-range goals and objectives
1 True
2 False
The assessment of the external and internal environments is called the SWOT analysis
1 True
2 False
A written mission statement provides focus for decision making when shared by organizational managers and employees
1 True
2 False
Many organizations have three different kinds of projects in their portfolio: compliance, operational, and sacred cows
1 True
2 False
Free Text Questions
Strategy is implemented through .
Answer Given
projects.
In some cases organizations will use a(n) to solicit ideas for projects when the knowledge requirements for the project are not
available in the organization.
Answer Given
RFP (Request for Proposal).
Trang 14translate the organization's strategy into specific, concrete, and measurable terms.
Answer Given
Objectives.
Starting and stopping work on one task to go and work on another
project, and then returning to work on the original task is known as
_.
Answer Given
multitasking.
A project that a powerful, high-ranking official is advocating is often termed a(n) _.
Answer Given
sacred cow.
The assessment of the internal and external environments is known as a(n) .
Answer Given
SWOT analysis.
In classifying the kinds of projects an organization has in its portfolio, projects that directly support the organization's long-term mission are projects.
Answer Given
strategic.
the portfolio system involves monitoring and adjusting
selection criteria to reflect the strategic focus of the organization.
Answer Given
Managing.
Trang 15The process of assessing "what we are" and deciding and implementing
"what we intend to be and how we are going to get there" is
.
Answer Given
strategic management.
A list of potential projects, several criteria, weights for those criteria, and criteria scores for those projects are all typically included on a(n)
_ matrix.
Answer Given
project screening.
When considering criteria used to select projects, capturing a larger
market share or reducing the dependency on unreliable suppliers would both be examples of criteria.
Answer Given
nonfinancial.
The financial model that measures the time it will take to recover the project investment is the model.
Answer Given
payback.
The lack of understanding and consensus of organization strategy among top and middle-level managers is known as the .
Answer Given
implementation gap.
In a SWOT analysis, strong competition, reduced product demand, and a maturing product life cycle are examples of external .
Answer Given
Trang 16What the organization wants to become and the scope of the firm in terms
of its product or service would be identified in the organization's
.
Answer Given
mission statement.
How strategies will be realized, given available resources, is answered through .
Answer Given
implementation.
A weighted scoring model typically uses several weighted selection
criteria to evaluate project proposals An example of this would be a(n) .
Answer Given
project screening matrix.
change infrequently and may require revision only when the nature of the business changes or shifts.
Answer Given
Mission statements
The financial model that measures the current value of all cash inflows and outflows using management's minimum desired rate of return is known as the _ model.
Answer Given
net present value (NPV).