3 project network example (AON) Basic Scheduling with AON Networks

18 402 0
3 project network example (AON) Basic Scheduling  with AON Networks

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

NETWORK TECHNIQUES Basic Scheduling with A-O-N Networ ks ALTERNATIVE PROJECT REPRESENTATIONS Activity on Arc Activity on Node (A-O-A) Arrow Diagrams Event Oriented (A-O-N) Precedence Networks Activity Oriented Network Networks Activity, a i i i EXAMPLE – (A-O-N) JOB PREDECESSORS DURATIONS (Days) A - B - C a D a,b E d F d G c,e H c,e I f,g,h Project Network Example-1 (A-O-N) cc aa g d e h b f i FORWARD PASS FOR EXAMPLE-1 BACKWARD PASS FOR EXAMPLE-1 EARLY & LATE SCHEDULE FOR EXAMPLE-1 Job Duration ES EF LS LF TF a 2 b 3 c 11 12 d 7 e 12 12 f 15 10 18 g 12 18 12 18 h 12 16 14 18 i 18 21 18 21 CRITICAL PATH FOR EXAMPLE-1 CRITICAL PATH FOR EXAMPLE-1 FLOATS FOR EXAMPLE Job Total Safety Free Independent a 1 0 b 0 0 c 9 d 0 0 e 0 0 f 3 3 g 0 0 h 2 0 i 0 0 FLOAT COMPUTATIONS FOR ACTIVITY a Total Float = LS-ES = LF – EF = Safety float = Total Float – {(Max(LF of predecessors) – ES)} = Free Float I – (0-0) = I = Total Float – {( LF – Min( ES of successors)} = I –(0-0) = Independent float = Total float – both the latter terms = I- (0+1) = FLOAT COMPUTATIONS FOR ACTIVITY c Total Float = LS-ES = LF – EF = Safety float = Total Float – {(Max(LF of predecessors) – ES)} = Free Float = Total Float – {( LF – Min( ES of successors)} = – Independent float = Total float –both the latter terms = 9-(1+0)= – (3-2) = (12-12) = PRECEDENCE DIAGRAMMING METHODS  Generalized precedence relations  Start to Start (SS)  Finish to Finish (FF)  Start to Finish (SF)  Finish to Start (FS)  Permit partial or complete overlap of activities START TO START LAG (SS) FINISH TO FINISH LAG (FF) START TO FINISH LAG (SF) FINISH TO START LAG (FS) Thank you

Ngày đăng: 03/07/2016, 20:35

Từ khóa liên quan

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan