BẢN VẼ BIỆN PHÁP THI CÔNG BỂ XỬ LÝ NƯỚC THẢI BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P. 1) WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.1) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P. 2) WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.2) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P. 3) WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.3) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 1) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.1) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 2) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.2) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 3) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.3) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 4) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.4) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 5) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.5) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P. 6) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.6) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P. 7) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.7) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P. 8) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.8) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P. 9) WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.9)
Trang 1BẢN VẼ BIỆN PHÁP THI CÔNG BỂ XỬ LÝ NƯỚC THẢI
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 1)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.1) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 2)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.2) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 3)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.3)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 1)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.1)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 2)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.2)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 3)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.3)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 4)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.4)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 5)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.5)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 6)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.6)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 7)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.7)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 8)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.8)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 9)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.9)
Trang 2BẢN VẼ BIỆN PHÁP THI CÔNG BỂ XỬ LÝ NƯỚC THẢI
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 1)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.1) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 2)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.2) BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI ĐÀO ĐẤT (P 3)
WASTEWATER TANK - CONSTRUCTION METHOD FOR EXCAVATION (P.3)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 1)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.1)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 2)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.2)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 3)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.3)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 4)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.4)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 5)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.5)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG(P 6)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.6)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 7)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.7)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 8)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.8)
BỂ XỬ LÝ NƯỚC THẢI - BIỆN PHÁP THI CÔNG VÁN KHUÔN VÀ ĐỔ BÊ TÔNG (P 9)
WASTEWATER TANK - CONSTRUCTION METHOD FOR FORMWORK AND CONCRETE (P.9)
Trang 3THUYẾT MINH THI CÔNG
LỚP ĐÁ CẤP PHỐI DÀY 250 MM THEO THIẾT KẾ ĐẾN CAO ĐỘ NL -10.550
THI CÔNG CHỐNG MỐI THEO THIẾT KẾ
3 TRẢI TẤM NI LON DÀY 0,25MM
4 ĐỔ BÊ TÔNG LÓT ĐÁY MÓNG, DẦM DÀY 100MM
5 THI CÔNG CHỐNG THẤM THEO THIẾT KẾ
6 GCLD VÁN KHUÔN, CỐT THÉP, ĐỔ BÊ TÔNG LỚP 1 ĐẾN CAO ĐỘ NL -8.950 (BÊ
TÔNG CHỐNG THẤM W10)
7 THI CÔNG CHỐNG THẤM, LỚP HOÀN THIỆN THEO THIẾT KẾ
8 ĐẮP ĐẤT TỪ CAO ĐỘ NL -10.550 ĐẾN CAO ĐỘ NL -8.950
9 GCLD VÁN KHUÔN, CỐT THÉP, ĐỔ BÊ TÔNG LỚP 2 ĐẾN CAO ĐỘ NL -8.350
10 THI CÔNG CHỐNG THẤM, LỚP HOÀN THIỆN THEO THIẾT KẾ
11 THÁO HỆ VĂNG CHỐNG CỪ
12 ĐẮP ĐẤT TỪ CAO ĐỘ NL -8.950 ĐẾN CAO ĐỘ NL -8.250
13 GCLD VÁN KHUÔN, CỐT THÉP, ĐỔ BÊ TÔNG LỚP 3 ĐẾN CAO ĐỘ NL -5.600
14 THI CÔNG CHỐNG THẤM, LỚP HOÀN THIỆN THEO THIẾT KẾ
15 ĐẮP ĐẤT ĐẾN CAO ĐỘ NL - 8.250 ĐẾN CAO ĐỘ NL - 5.700
16 GCLD VÁN KHUÔN, CỐT THÉP, ĐỔ BÊ TÔNG LỚP 4 ĐẾN CAO ĐỘ NL -5.100