CONG TY CP THi NGHIEM KHAO SAT VA XAY DUNG BACH DANG
BACH DANG TESTING SURVEY AND CONSTRUCTION JOINT STOCK COMPANY
VILAS 240
DE CUONG THI NGHIEM KIEM TRA SUC CHIU TAI BANG PHUONG PHAP NEN TINH DOC TRUC COC BTDUL
OUTLINE TEST OF BEARING CAPACITY OF PRESTRESSED CONCRETE PILES BY STANDARD TEST METHOD FOR PILES UNDER AXIAL COMPRESSIVE LOAD Du an: Project: Địa điểm : Location : Chủ đầu tư: TiiUeSfoF¿ Tông thâu: Contructor: Hạng mục: tem:
DỰ ÁN PHÁT TRIÊN CÔNG NGHIỆP BW NAM HẢI CN10-01
BW NAM HAI INDUSTRIAL DEVELOPMENT PROJECT CN10-01
LÔ CN10-01, KHU PHI THUÊ QUAN VÀ KCN NAM ĐÌNH VŨ (KHU 1) THUỘC KHU KINH TẾ ĐÌNH VŨ - CÁT HÁI, P ĐÔNG HAI 2, Q HAI AN, TP HAI PHONG
LOT NO CN10-01, NON-TARIFF AND NAM DINH VU INDUSTRIAL PARK (ZONE 1), DINH VU - CAT HAI ECONOMIC ZONE, DONG HAI 2 WARD, HAI AN DISTRICT, HAI PHONG CITY, VIET NAM CONG TY TNHH PHAT TRIEN CONG NGHIEP BW NAM HAI BW INDUSTRIAL DEVELOPMENT NAM HAI LIMITED LIABILITY COMPANY
CONG TY CO PHAN XAY DUNG MEGASPACE
MEGASPACE CONSTRUCTION JOINT STOCK COMPANY
NHA KHO VA NHA PHU TRO
Trang 2Cộng hoà xã hội chủ nghĩa Việt Nam Độc lập - Tự do - Hạnh phúc
VILAS 240
DE CUONG THI NGHIEM KIEM TRA SUC CHIU TAI
BẰNG PHƯƠNG PHAP NEN TINH DOC TRUC COC BTDUL OUTLINE TEST OF BEARING CAPACITY OF PRESTRESSED CONCRETE PILES BY STANDARD TEST METHOD FOR PILES UNDER AXIAL COMPRESSIVE LOAD
Dự án : DU AN PHAT TRIEN CONG NGHIEP BW NAM HAI CN10-01 Project : BW NAM HAI INDUSTRIAL DEVELOPMENT PROJECT CN10-01
Địa điểm : LÔ CN10-01, KHU PHI THUE QUAN VA KCN NAM ĐÌNH VŨ (KHU 1) THUỘC KHU KINH TẾ ĐÌNH VŨ - CAT HAI, P ĐÔNG HAI 2, Q HAI AN, TP HAI PHONG
Location: LOT NO CN10-01, NON-TARIFF AND NAM DINH VU INDUSTRIAL PARK (ZONE 1), DINH VU - CAT HAI ECONOMIC ZONE, DONG
HAI 2 WARD, HAJ AN DISTRICT, HAI PHONG CITY, VIET NAM Chủ đầu tư: CONG TY TNHH PHAT TRIEN CONG NGHIEP BW NAM HAI
Investor: BW INDUSTRIAL DEVELOPMENT NAM HAI LIMITED LIABILITY COMPANY Tổng thầu: — CÔNG TY CỎ PHẢN XÂY DỰNG MEGASPACE
Contrudor: | MEGASPACE CONSTRUCTION JOINT STOCK COMPANY Hangmue: | NHA KHO VA NHA PHU TRO
Item: WAREHOUSE, ULTILITY
ĐẠI DIỆN ĐƠN VỊ PHÊ DUYỆT
PHO GIAM BOC
Trang 3DE CUONG
THI NGHIEM KIEM TRA SUC CHIU TAI BANG PH UONG PHAP NEN
TINH DOC TRYC COC BIDUL_
I GIỚI THIỆU
SN Z
- Đề cương giới thiệu quy trình thí nghiệm nén tĩnh dọc trục cọc èhơ dự án: DỰ
AN PHAT TRIEN CONG NGHIEP BW NAM HAI CN10-01
II CƠ SỞ THÀNH LẬP
- Yêu cầu thí nghiệm của Chủ đầu tư;
- Yêu cầu kỹ thuật, hồ sơ và các bản vẽ do Chủ đầu tư cung cấp;
- TCVN 9393-2012 : Cọc - Phương pháp thí nghiệm hiện trường bằng tải trọng
tĩnh nén đọc trục
- Và các tiêu chuẩn Việt Nam có liên quan
2.1 ĐẶC ĐIÊM CỌC THÍ NGHIỆM
Chỉ tiết cọc thí nghiệm được trình bay trong Bang A.1 Bảng A.1 - Chỉ tiết cọc thí nghiệm
STT Kích thước cọc Tải trọng thiết Tái trọng thí £
; ; ; Sô lượng (cọc) (mm) kê Pr (Tân) | nghiệm Pụ, (Tân)
i D350 50 100 3
2 D350 75 151 15
2.2.DAC DIEM CONG TRINH
Dy 4n : DU AN PHAT TRIEN CONG NGHIEP BW NAM HAI CN10-01 sử dung
hé coc D350
2.3 MUC DICH THI NGHIEM
Công tác thí nghiệm coc bằng tải trọng nén tĩnh dọc trục được thực hiện để kiểm tra sức chịu tải thực tế theo từng loại tiết điện Kết quả thí nghiệm là cơ sở dé tu van
thiết kế quyết định chiều đài, tiết diện cọc và điều chỉnh phương án móng
Trang 4I PHUONG PHAP THI NGHIEM
on
Các cọc thí nghiệm trong cơng trình được thực hiện bing peng Pháp Thí nghiệm nén cọc bằng tải trọng fĩnh nén dọc trục
3.1 THIẾT BỊ THÍ NGHIỆM
7
+ Coe thi nghiém tai trong tinh duoc tién hanh bang phuong pháp hat đối trọng
trước
3.1.1 Hệ đối trọng:
- Hệ đối trọng sử dụng trong cơng trình là một hệ bao gồm nhiều cục bê tơng có vỏ thép đúc sẵn, trọng lượng 5,0 tắn/cục và được xếp thành khối trên một hệ dầm thép
của máy ép cọc (rô bốt ép cọc) Hệ đối trọng được tính tốn phù hợp với tải trọng cần thí nghiệm (tải trọng gấp 1,2 lần tải trọng thí nghiệm)
- Hệ đầm giá thí nghiệm bao gồm dầm chính và hệ dầm phụ Dầm chính là hệ dầm truyền lực chính lên đầu cọc DẦm chính 200x400x1900mm được gia cường bởi
thép chịu lực đủ khả năng chịu lực chiều dài từ 1,9m Dam phu la mot hé dam bao gồm
nhiều thanh dim I gia cường liên kết đặt trên máy ép cọc (rô bét ép coc) Hệ dầm này được tính tốn đủ chịu lực khi chất tải cũng như trong suốt quá trình thí nghiệm Trên
đầu kích, đầu cọc đặt tắm đệm để đảm bảo cho việc truyền lực đến luôn ln doc theo trục cọc thí nghiệm
- Hệ gối đỡ : Là hệ máy ép cọc (rô bốt ép cọc)
3.1.2 Hệ thống gia tải:
+ Hệ thống gia tải thí nghiệm trong cơng trình sử dụng kích thủy lực có sức nâng > 2000 KN được kiểm định và cấp giấy phép cho phép sử dụng kích này được đặt trên đầu cọc thí nghiệm Trên đầu kích có bộ phận tự điều chỉnh đảm bảo cho việc truyền lực nén luôn đọc theo trục cọc thí nghiệm bằng cách đặt tâm kích thủy lực trùng với tâm
cọc thí nghiệm Việc xác định tâm cọc thí nghiệm và tâm kích được xác định bằng cách
dùng thước đo và quan sát bằng mắt Dùng thước đo để xác định tâm cọc và tâm kích ( vì cọc và kích thủy lực đều là trịn nên tâm kích và cọc là giao điểm của hai đường
kính ) sau đó đánh dấu lại đặt sao cho tâm kích và cọc trùng nhau
Trang 5
cọc thí nghiệm được tính thơng qua số đọc đồng hồ thủy lực và hệ số sức nâng của kích thủy lực
lực và cung cấp dầu vào các kích qua một bộ chia nhằm điều ditt h Site, bags theo ý muốn Dầu thủy lực phải được dự trù khoảng 20 lít để thực hiện vide tainghiem,
3 1.3 Hệ thong do bién dang:
+ Hệ thống đo biến dạng bao gồm 2 đồng hồ đo lún có đải đo 0 - 50mm, có độ chính xác 0,01mm gắn chặt lên thân cọc thí nghiệm thông qua một hệ gá đỡ và gông thép Đồng hồ kiểm định và cấp giấy phép sử dụng hai đồng hồ này được dán thước mm lên để kiểm soát chuyên vị của đồng hồ do tác động của bên ngoài
+ Hệ gá đỡ đồng hồ đo lún: Là hệ gá đỡ có chân từ tính bằng nam châm vĩnh cửu gắn chặt vào hệ thống gông thép gắn trên đầu cọc thí nghiệm
+ Hệ gông đầu cọc: Hệ này được chế tạo thành tắm thép tắm đủ cứng và gắn chặt vào thân cọc bằng bu lông và trám xi măng, không bị ảnh hưởng đến hệ thống gia tải
năm trên đầu cọc
+ Hệ thống mốc chuẩn: Hệ thống mốc chuẩn dùng trong công trình là một hệ thép hình được chơn sâu xuống lòng đất Từ mốc chuẩn đến cọc thí nghiệm lớn hơn 3D (D là chiều rộng tiết điện cọe) nhưng trong mọi trường hợp không nhỏ hơn 1,5m Độ cứng của hệ mốc cọc đảm bảo không bị biến dạng trong q trình thí nghiệm và không chịu ảnh hưởng do các tác động bên ngoài
* Hệ thống đo biến dạng này phải được bảo vệ tránh va chạm cách ly với người lạ khơng có trách nhiệm trong khu vực thí nghiệm Trong q trình thí nghiệm phải có cơng nhân, kỹ thuật trực thí nghiệm 24h/24h
3.2 QUY TRÌNH THÍ NGHIỆM
+ Thí nghiệm nén thử tải trọng tĩnh cọc trong cơng trình được tiễn hành theo tiêu
chuẩn Việt Nam TCVN 9393 - 2012
+ Cọc đã đủ thời gian “nghỉ” theo quy định của quy phạm + Phương pháp gia tải:
- Cọc được thí nghiệm theo 02 chu kì theo bảng quy trình được ghi như sau : ~ Chu kil
* Tang tdi: 0% >25% > 50% >75% >100%
Trang 6* Gidm tdi: 100% >50% >0%
- Chu kill WAS
* Tăng tải: 0%6 >2516 >06 >75!6 > 10086 >12596/25 >175% >200% S N \\LAS 09 Z⁄ * Giảm tải: 2006 >175% >150% >100% >50% >08Ề; LY
+ Tăng tải : Tải trọng được chat theo từng cấp < 25% tai trọng thiết kế Mỗi cấp giữ tải cọc đạt độ lún ôn định theo quy ước thì tăng cấp tải tiếp theo Tổng thời gian giữ tải cấp trung gian không quá 02 giờ
+ Giảm tải : Mỗi cấp giảm tải bằng 2 lần cấp tăng tải tức là 50% tải trọng thiết kế Thời gian giữ tải là 30 phút riêng cấp 0% có thể lâu hơn
- Kiểm tra hoạt động của thiết bị thí nghiệm và tạo tiếp xúc tốt giữa thiết bị và đầu
cọc: trước khi tiễn hành thí nghiệm, các đồng hồ đo lún được điều chỉnh về Ú, gia tải trước được thực hiện bằng cách tác động lên đầu cọc 5% tải trọng thiết kế, gift tai trong
này trong thời gian 10 phút sau đó hạ tải về 0 và không hiệu chỉnh đồng hồ đo lún về 0,
các giá trị hiện có của đồng hồ được ghi thành số đọc ban đầu khi tải trọng thí nghiệm
bằng 0 tắn
- Tải trọng thí nghiệm được chia làm các cấp tải theo quy định, mỗi cấp tải < 25% tải trọng tính tốn của thiết kế
- Gia tải thí nghiệm được gia tải theo chu trình thí nghiệm
BẢNG QUY TRÌNH GIA TẢI THÍ NGHIỆM
(Theo TCVN 9393 - 2012) tải trọng thí nghiệm
Coc D350mm Cấp tải trọng
„ " Thời gian duy trì tải trọng thí Thời gian theo dõi và ghi chép số thí nghiệm
nghiệm lên đầu cọc thử liệu thí nghiệm
%Ptk
Giữ trong 10° để loại trừ các biến 5% ,
dạng do xếp tải gây ra Chu ky I
Trang 7
Tối thiểu là 1 giờ và đạt độ lún ôn Ghi kết quả ở các thời điểm: 0°;10”;
25% định quy ước 0.25mm/ giờ nhưng|_ 20);30”;45°;60)°; (120X lêu 1 gio
` ⁄ ‘wes
không quá 2 giờ đầu chưa đạt đỗ lún ổn đi» 50% Như trên
75% Như trên Nhu tren ˆ
100% Như trên Như trên
Ghi kết quả ở các thời điểm: 0°;10”;
50% 30 phút
20°;30°
Ghi kết quả ở các thời điểm: 0°;10”;
0% lgiờ
20°;30°;45°;60” Chu kỳ II
Ghi kết quả ở các thời điểm: 0°;10';
25% 30 phút
20°;30° 50% Như trên Như trên
75% Như trên Như trên
Tối thiêu là 1 giờ và đạt độ lún ôn| Ghi kết quả ở các thời điểm: 0°;10°;
100% định quy ước 0.25mm/ giờ nhưng 20';30°;45”;60”; (120°) Nếu 1 giờ
không quá 2 giờ đầu chưa đạt độ lún ỗn định
125% Như trên Như trên 150% Như trên Như trên 175% Như trên Như trên
oo Ll, _ | Ghi kết quả ở các thời điểm: 0°;10°;
Duy trì 6 giờ cho đên khi đạt độ
ko 20°;30°;45°;60°;120” ; 180°; 240’;
200% lún ôn định quy ước 0.25mm/gid, nhưng không quá 24h ; 360°;( 420°; 480); 1440°) Cho
đến khi đạt độ lún ổn định thông
Trang 8
thường 0.25mm/ giờ 150% 30 phút
100% Như trên Nhưưên 2
50% Như trên Như trên
- Ghi kết quả ở các thời điểm: 0°;10”;
0% lgid
20°;30°;45°;60°
- Độ lún ỗn định quy ước: Độ lún của cọc được gọi là ôn định quy ước khi :
- Tốc độ chuyển vị lún của cọc không được quá 0,25mm/1h đối với cọc chống vào
lớp đất hòn lớn, đất cát và đất sét từ dẻo đến cứng (TCVN 9393-2012)
- Tốc độ chuyén vị lún không vượt quá 0,1mm/1h đối với cọc ma sát trong dat mém dén déo chay
- Cọc thí nghiệm được xem là bị phá hoại khi:
+ Khi chưa đạt tới tải trọng thí nghiệm lớn nhất mà tổng chuyên vị lún của cọc đã
vượt quá 10% đường kính cọc theo quy phạm
- Vật liệu cọc DỊ phá hoại trong quá trình thí nghiệm - Thí nghiệm được xem là kết thúc khi:
+ Đạt mục tiêu thí nghiệm theo đề cương
+ Cọc thí nghiệm bị phá hoại (bao gồm phá hoại vật liệu cọc hoặc phá hoại dat
nén)
- Thí nghiệm phải dừng lại nếu phat hiện thấy:
+ Các mốc chuẩn đặt sai, không ổn định hoặc bị pha hong + Kích hoặc thiết bị đo không hoạt động hoặc khơng chính xác + Hệ phản lực khơng én dinh
+ Việc thí nghiệm có thể được tiếp tục sau khi đã xử lý khắc phục
- Thí nghiệm bị hủy bỏ nếu phát hiện thấy: + Cọc bị nén trước khi gia tai
Trang 9IV BIEN PHAP KHAC PHUC THI CONG 4.1 CONG TAC CHUAN BI THI NGHIEM :
- Công tác này bao gôm nhiêu bước tiên hành tuân tự nhắm phục vụ tác thí nghiệm Các bước chuẩn bị bao gồm:
a) Kiêm tra và gia cô đầu cọc thí nghiệm ID, Z⁄
- Các cọc thí nghiệm cần độ cao hiện trạng khoảng 10 - 30 em nếu Soon hoặc thấp hơn phải có biện pháp xử lý gia cố đầu cọc :
+ Đối với các cọc cao hơn 10 - 30 em phải được cắt bỏ phần cao bằng máy cắt chuyên dụng để tránh làm ảnh hưởng tới phần còn lại của cọc Sau đó phải được mài phẳng và trải keo làm phẳng và tạo độ êm cho đầu cọc sau đó sử dụng gông đầu cọc tránh phá hủy cục bộ Gông đầu cọc được chế tạo bằng thép cường độ cao thiết kế làm hai nửa hình trịn có bán kính 20 em khi ốp vào đầu cọc dùng ốc vít siết chặt ôm lay
thân cọc
+ Đối với cọc thấp hơn 10 — 30 em nếu đầu cọc khơng cịn được nguyên vẹn thì sử lý như cọc cao hơn và dùng đoạn nối bằng thép cường độ cao nối cọc lên độ cao thích hợp Nếu cọc còn nguyên vẹn sử dụng đoạn nối bằng thép cường độ cao để nối cọc lên độ cao thích hợp
b) Khi ra hiện trường kiểm tra các cọc thí nghiệm đã đạt yêu cầu để tiến hành thí nghiệm và đã được gia cố lại mặt cọc theo yêu cầu của thiết kế
c) Kiểm tra hệ thống thiết bị thí nghiệm:
+ Hệ thống thiết bị thí nghiệm khi chuyển đến cơng trình phải được kiểm tra chặt chẽ trước khi đưa vào sử dụng Kích thủy lực phải được kiểm tra sức nâng, các đồng hồ
được kiểm tra về độ nhạy
+ Kiểm tra mức độ an toàn của hệ dầm giá chất tái và hệ gỗi đỡ
4.2 TIỀN HÀNH THÍ NGHIỆM
- Cơng tác thí nghiệm chỉ được tiến hành sau khi đã hoàn tất các bước nêu trên
a) Sau khi chuẩn bị xong đầu cọc thí nghiệm phải báo cho chủ đầu tư, tư vấn
Trang 10b) Sau khi thực hiện xong phân việc nêu trong điêu c ở trên, cán bộ thi cong
Cơng trình có trách nhiệm thơng báo cho chủ đầu tư, đơn vị tư vấn thiết kế và đơn vị tư
vận giám sát biệt mới được tiên hành thí nghiệm
c) Việc tiễn hành thí nghiệm được thực hiện theo quy trình đã nê
Khi có sự cố hoặc có bất thường trong q trình thí nghiện.) See thuat ‘hi cơng cơng trường có trách nhiệm thông báo kịp thời cho chủ đầu tư, đơn vị thiết kế, tư van giám sát để có biện pháp sử lý thích hợp
e) Các số liệu ghi chép phải đầy đủ, rõ ràng khơng tẩy xóa và được chuyển về văn phòng xử lý kịp thời
0 Nhân lực bố trí thí nghiệm: Trong mỗi hệ thí nghiệm bố trí 02 người theo dõi (01 người kỹ thuật viên ghi chép kết quả, 01 công nhân phụ việc)
ø) Phải dùng bạt che chắn khu vực thí nghiệm tránh ảnh hưởng tới thời tiết cũng như tác động khác từ bên ngoài ảnh hưởng tới kết quả thí nghiệm
V BIEN PHAP AN TOAN LAO DONG
- Nghiém cấm những người khơng có trách nhiệm, nhiệm vụ đi lại hoặc có mặt
trong phạm vỉ mặt bằng đang thi công
- Khi cầu đang hoạt động, nghiêm cấm tất cả mọi người đi lại hoặc đứng trong tầm hoạt động của cau
- Khi làm việc trên cao, công nhân vận hành phải có những thiết bị an toàn theo
quy định an toàn lao động
- Kỹ thuật viên phụ trách phải thường xuyên kiểm tra mức độ an toàn của thiết bị tham gia thi công: Câu móc của đối tượng, móc cấu, cáp câu, gối kê chân cầu, gối kê hệ
đối trọng, mức độ an tồn và ơn định của hệ giàn dầm thép chất đối trọng
- Sau khi hoàn tất việc chất đối trọng phục vụ cơng tác thí nghiệm, kỹ thuật viên công trình phải kiểm tra 1 lần cuối, nếu đảm báo an toàn mới được tiến hành các công việc tiếp theo
- Nghiêm câm tất cả mọi người khơng có trách nhiệm sử dụng các thiết bị thí nghiệm Chỉ kỹ thuật viên được chỉ định thí nghiệm mới được phép sử dụng các dụng
cụ nói trên
VI KẾ HOẠCH THỰC HIỆN
6.1 TIEN DO THUC HIỆN THI NGHIEM :
- Tiến độ thực hiện tại cơng trình được tính từ ngày bên A bàn giao mặt bằng Tiền
Trang 11+ Chuyén tai, gia công lắp đặt thiết bị thí nghiệm chuẩn bị thí nghiệm là 0,5 ngày + Tiến hành thí nghiệm dự kiến 2,0 n gay
- Như vậy tổng tiến độ dự kiến cho 01 cọc thí nghiệm là 2,5 ngày LậP:báo cáo kết
quả thí nghiệm là 03 ngày Z
6.2 SƠ ĐÔ TÔ CHỨC t LAS 09 72 as
QUAN LY KY THUAT PHONG KỀTOÁN ⁄⁄
iil
A -»
a Y
CHUYEN GIA TU VAN
Vv —*| CHỦ TRÌ CƠNG TRÌNH | ———— Chuyên SỐ liệu về | |
CAN BO KY THUAT HIEN TRUONG Thong tin hign trwong) CAN BO KY THUAT < "| TRONG PHONG
<a #l CÔNG NHÂN : ——————— THÍ NGHIỆM
>) BO PHAN VAN PHONG A
Mô tả quan hệ giữa trụ sở chính và quản lý ngoài hiện trường của sơ đồ tổ chức
công trường
Để thực hiện cơng tác tư vấn thí nghiệm cọc nhằm mục đích bảo đảm chất lượng
tốt nhất, đúng tiến độ, giá thành hợp lý và đảm bảo an tồn cho cơng trình, người lao động trong suốt q trình thực hiện cơng trình, tư van thí nghiệm cọc sẽ thực hiện các
cơng việc sau:
* Chủ trì kiểm định chất lượng cọc
- Chịu trách nhiệm chính quy đinh trình tự thí nghiệm theo đúng quy trình quy
phạm hiện hành
- Đưa ra chủ trương đối với các vấn đề kỹ thuật quan trọng - Xem xét và phê chuẩn báo cáo kết quả thí nghiệm
Trang 12- Xác định cơ câu cán bộ thực hiện thí nghiệm & chức trách của những nhân viên
thí nghiệm
đếtì ng phoi
- Quan hệ với phụ trách các nhà thâu, chủ đâu tư xác định các van £
Sg
⁄
hợp công tác và các tài liệu cân cung câp có liên quan LE
- Thiết kế tổ chức thi công 9
- Kiểm tra tiến độ cơng trình và chất lượng thi công nghiệm thu ting pha ¡ việc
hạng mục công trình, ký chứng từ thanh tốn cơng trình
- Đơn đốc chỉnh lý văn bản hợp đồng và tài liệu hồ sơ kỹ thuật
* Chuyên gia tư vẫn
- Tư vẫn các vân đề kỹ thuật trước và trong quá trình thí nghiệm kiểm tra chất
lượng cọc cho chủ trì kiểm định
- Đánh giá kết qua thí nghiệm
* Cán bộ thí nghiệm hiện trường
- Kiểm tra tồn bộ tình trạng thiết bị trước khi đưa vào thí nghiệm
- Kiểm tra các việc định VỊ, cao độ, gia công đầu cọc và các bước chuẩn bị trước
khi làm thí nghiệm theo đúng đề cương được duyệt
- Theo đõi vận hành thiết bị trong suốt q trình thí nghiệm và tuân thủ theo
đúng quy trình quy phạm và kiểm tra chất lượng cọc
* Cơng nhân thí nghiệm và những thành viên tham gia vào trong q trình thí nghiệm:
- lrợ giúp đắc lực cho tổ tư vẫn thi nghiệm hoàn thành tốt nhiệm vu
- Thao tác an toàn trong q trình thí nghiệm
- Khi hồn thành thí nghiệm tra lai mat ban g * Bộ phan van phòng tư van thí nghiệm
- Trợ lý cho các thành viên tổ tư vấn thí nghiệm, điều hành các công việc văn phòng sao cho hoạt động của tư vẫn luôn đạt hiệu quả cao
- Cán bộ kỹ thuật văn phòng tiến hành sử lý số liệu ghi chép và đo đạc tại hiện trường để viết báo cáo kết quả thí nghiệm
6.3 CƠNG TÁC LẬP BÁO CÁO KÉT QUẢ THÍ NGHIỆM
- Công tác tổng hợp tài liệu và tính toán kết quả phải được tiến hành ngay sau khi kết thúc thí nghiệm hiện trường
Trang 13+ Các sô liệu thí nghiệm của từng cọc thí nghiệm được chuyên về văn phòng để
tổng hợp và tính tốn kết quá thông báo cho thiết kế chậm nhất không quá: 3 ngày kế từ
ngày kết thúc thí nghiệm cọc đó gay A a N `
+ Việc tổng hợp viết báo cáo kết quả thí nghiệm được tiếc TEER ngay sau np ét
À US 7 y
thúc thí nghiệm cọc cuối cùng, giao nép chậm nhất sau 03 ngày cho “chu đầu, và thiết kê
VIL KET QUA THI NGHIEM
7.1 DANG BANG
- Cac sé liéu tai trọng, thời gian, độ lún ghi chép trong thời gian thí nghiệm được
chỉnh ly và biêu diễn dưới dạng bảng “Số liệu thí nghiệm nén tinh” va tổng hợp kết quả
thí nghiệm
7.2 DANG BIEU DO
Từ số liệu thi nghiệm, các biểu đồ sau đây được thành lập:
- Biểu đồ tái trọng - chuyển vị - Biểu đồ chuyển vị - thời gian - Biểu đồ tải trọng - thời gian
- Biểu đồ tái trọng - chuyển vị - thời gian
7.3 PHẢN THUYÉT MINH
Phần thuyết minh gồm các nội dung sau:
- Mục đích thí nghiệm; - Phương pháp thí nghiệm; - Thiết bị thí nghiệm; - Quy trình thí nghiệm; - Kết quá thí nghiệm; - Kết luận và kiến nghị
7.4 PHU LUC BAO CAO
Phần phụ lục gồm các nội dung sau:
- Biểu ghi số liệu thí nghiệm;
- So 46 bé tri coc thí nghiệm;
- Chứng chỉ kiểm định thiết bị thí nghiệm
Trang 14Phụ lục B (Quy định) CÁC BIỀU ĐỒ QUAN HỆ Tải trọng (tần) Chuyển vị (mm)
Hình BI: Biểu đồ quan hệ tải trọng — chuyển vị
Thời gian (phú)
eee „—_ aay
Chuyển
vị
(mm)
Hình B2: Biểu đỗ quan hệ chuyển vị ~ thời gian
tt thoi gian (phut)
Chuyển vị (mm) _ Tỉ trọng (tần)
Hình B3: Biểu đô quan hệ tải trọng - thời gian ~ chuyển vị
a
thời gian (phú!)
Hình B4: Biểu đồ quan hệ tải trọng — thời gian
Tải trọng
Trang 15SO DO THi NGHIEM NEN TINH COC Tinana
Ghi chu /Notice:
1 - Cọc thí nghiệm 4 - Dầm chuẩn 2 - Kích thuỷ lục 5 - Cọc chuẩn 3- Đồng hồ đo lún 6 - Dầm chính
Trang 16OUTLINE
TEST OF BEARING CAPACITY OF PRESTRESSED CONCRETE PILES BY STANDARD TEST METHOD FOR PILES UNDER AXIAL COMPRE
Project: BW NAM HAI INDUSTRIAL DEVELOPMENT PROJECT GN, 0204), 2
⁄
NG SA Location: LOT NO CNI0-01, NON-TARIFF AND NAM DINH VU INDUSTRIAL PARK
(ZONE 1), DINH VU - CAT HAI ECONOMIC ZONE, DONG HAI 2 WARD, HAI AN DISTRICT, HAI PHONG CITY, VIET NAM
I INTRODUCTION
- The outline introduces procedure for test of piles under axial compressive load
for the Project: BW NAM HAI INDUSTRIAL DEVELOPMENT PROJECT CNI10-01
IL BASES
- The Investor’s request for test;
- Technical requirements, documents and drawings provided by the Investor; - TCVN 9393-2012 : Piles - Standard test method in situ for piles under axial compressive load
- And relevant Standards of Viet Nam
2.1 CHARACTERISTICS OF TESTING PILES Details of testing piles are presented in Table A.1
Table A.1 - Details of testing piles
a ấn ‘ Design load Testing load -
No Pile dimensions (mm) Ssign tod Quantity (Pile)
Prx (ton) Pry (ton)
Ị D350 50 100 3
2 D350 TS 151 15
2.2 CHARACTERISTICS OF PROJECT
Project: BW NAM HAI INDUSTRIAL DEVELOPMENT PROJECT CNI10-01 used
piles D350mm
2.3 PURPOSE OF TEST
Trang 17Test of piles under axial compressive load are conducted to test actual load bearing capacity by each type of sections Test results are bases for Design Consultant
to determine lengths and sections of piles and adjust foundation plans 7, +X
o AL) `
Technical requirements and procedure are prepared and applied-on- bile test
ee | Q ⁄
work en
UI TEST METHOD
Testing piles for the construction are tested by: Test method for piles under axial compressive load
3.1 TESTING EQUIPMENT
+ test under axial compressive load shall use weighted boxes
3.1.1 Counterweight system:
3.1.1 Counterweight system:
- Counterweight system to be used is a system comprising of a number of
concreted-filled steel boxes, each of which weighs 5,0 tons; the boxes are placed on to
steel beams of pile driver The counterweight system is calculated in accordance with testing load (with weight being 1,2 times of testing load)
- Beam system for testing comprises of test beams and auxiliary beams Test beams are those that directly transfer load onto pile cap 200x400x1900 main beams are reinforced by load bearing steel having sufficient bearing capacity and length of at least 1,9 meters Auxiliary beams comprise of a number of reinforced ]-shaped beams above pile driver This system is calculated to have sufficient bearing capacity when loaded as well as during the whole course of test On the head of hydraulic jack, there shall be a steel plate to ensure that force transferred is along the axis of testing pile
- Bearing system: Is the supporting system of the pile driver 3 1.2 Loading system:
+ Loading system comprise of a> 2000 KN hydraulic jack, which is inspected and has operational certificate; the hydraulic jack is installed on the cap of testing pile On the head of the hydraulic jack is an automatic adjusting mechanism to guarantee that force transferred is along the axis of testing pile by aligning center of the hydraulic jack with center of the testing pile Determination of center of testing pipe and center of the hydraulic jack is conducted by using gages and visual observation Gages are used for
Trang 18determining center of testing pipe and center of the hydraulic jack (as the testing pile and hydraulic jack have circular cross section, the centers are intersections of two diameters), the centers are then marked and aligned
+ Measurement system: Force measurement system compri
SA N t
having measurement range of (0-60 Mpa) The gages are inspected antshave op! rất
ional
certificates Compressive force acting on cap of testing pile is calculated based on readings of hydraulic gages and lifting force factor of the hydraulic jack
+ Hydraulic pump system: Hydraulic pump (1 pump) is connected to the hydraulic jack Quantity of hydraulic oil to be used for the test is expected to be 20 liters
3 1.3 System for measuring deformation:
+ System for measuring deformation comprise of 2 gages for measuring settlement, having measurement range of 0 - 50mm and accuracy of 0,01mm; the gages are attached to the testing pile by a supporting system and steel fasteners The gages are inspected and have operational certificates The gages are attached with mm rulers for controlling movement of gages under externa] impacts
+ System supporting deformation gages: Is a supporting system having magnetic legs of permanent magnets attached to steel fastening system on the cap of testing pile
+ Pile cap fastening system: This system is made from steel plates having sufficient stiffness and is attached to pile body by bolts and cement, not affecting the loading system on pile cap
+ Reference system: The reference system to be used in this project is a shaped steel system buried deep into ground Distance from the reference system to the testing pile is larger than 3D (D is the width of pile cross section), but in all case shall not be less than 1,5m The reference system shall be strong enough to avoid deformation during test and resist external impacts
This deformation measurement system must be protected from collision and unauthorized individuals in the testing area During the course of the test, there must be workers or technicians guarding the system 24/24
3.2 TEST PROCEDURE
Trang 19+ Test of pile under axial compressive load for the project shall be conducted in accordance with standard TCVN 9393 - 2012 of Viet Nam
+ The testing pile has sufficient “rest” time as specified in rotate, lề
YR
+ Loading method: Zo Wk
Ss
- The testing pile is tested in 02 cycles as in the following Se cipetie 7
Cycle I ae * Loading: 0% >25% >50% >75 Jo > 100% * Unloading: 100% >50% >0% Cycle IL * Loading: 0% >25% >50% >75 % > 100% > 125 o >150% > 165 % >175% >200% | * Unloading: 200% >175% >150% >100% >50% >0%
+ Loading: Loads are applied in increments of 25% of designed load After each increment, load is maintained until the testing pile reach settlement stability; then the next load increment is applied Total time of maintaining such increment shall not be more than 2 hours
+ Unloading: Each load decrement shall be load increment, being 50% of design load Time of maintaining load is 30 minutes, with time at 0% may being longer
- Checking operation of testing equipment and good contact between equipment and pile cap: Before commencing test, settlement measurement gages shall be adjusted to 0, pre-load is conducted by applying 5% of design load on pile cap, and this load is maintained in 10 minutes; then unload to 0 and not re-adjust settlement measurement gage to 0; current readings shall be recorded as initial readings at testing load being 0
ton
- Test load is divided into load increments as regulated, with each increment being 25% calculated load of the design
- Load is applied according to test procedure
Trang 20PROCEDURE OF TEST LOADING
(As per TCVN 9393 - 2012) test load
Applied testing load
Duration to maintain testing load at one end of the pile
A bile D350
om
Monitoring and ¥ecording dite tinte
SS ⁄ a %Ptk ⁄
7 Maintaining in 10’ to eliminate any 5%
deformation caused by loading CYCLE I
0% Recording initial data In minimum | hour and attaining Recording results at: 0’;107;
25% stable subsidence norm at 0.25 | 207;30°;45’;60’; (120°) If don’t get
mm/h but no longer than 2 hours stable settlement in first 1 hour
50% Same as above Same as above
75% Same as above Same as above
100% Same as above Same as above
50% 30 minutes Recording results at: 0°;10°; 20°;30? Recording results at: 0’;10’;
0% lhour
20”;30°;45°;60?
Chu kỳ
25% 30 minutes Recording results at: 0’;10°; 20°;30?
50% Same as above Same as above
75% Same as above Same as above
In minimum 1 hour and attaining Recording results at: 0’;10’; 100% stable subsidence norm at 0.25 20°;30°;45’;60°; (120°) If don’t get
Trang 21
mm/h but no longer than 2 hours stable settlement in first 1 hour
125% Same as above Same as above
3% 150% Same as above Same as: tboye!) >
———— 175% Same as above Samé‘as above} 9
Recording results at: “0?:10°:
Maintain for 06 hours until
- 20°;30°;45”;60°;120' ; 180); 240”; achieve conventional stable
200% 5 360’;( 420°; 480°; .1440’),
settlement 0.25mm/h, but not
Until achieve conventional stable more 24 hours
settlement 0.25mm/h
150% 30 minites Recording results at: 0°;10°; 20°;30’
100% Same as above Same as above
50% Same as above Same as above
Recording results at: 0°10’;
0% 1 hour 20°;30°:45°:60°
- Settlement stability: Settlement of pile is considered to reach stability when: - The rate of settlement movement of pile does not exceed 0,25mm/1h for pile in soil layers of large boulders, sand and clay from plastic to solid (TCVN 9393-2012)
- The rate of settlement movement of pile does not exceed 0,1mm/Jh for friction pile in soft to plastic soil
- Testing pile is considered as failed when:
+ The highest test load increment has not been applied when the total settlement movement of test pile exceed 10% of pile diameter
regulated by norms
- Pile material is damaged during test - Testing is considered as concluded when:
19
Trang 22+ Test targets specified in the outline is accomplished
+ Test pile is damaged (including damage of pile material or of ground)
- Test is stopped if
+ Reference system is placed incorrectly, or becomes unstable
+ Hydraulic jack or measuring equipment fail to run or run incorfectly.\> |
SS
+ Reaction system becomes unstable
+ The test shall be continued when remedy actions are completed - Test is canceled if:
+ Test pile is compressed before loading + Aforesaid conditions cannot be remedied 1V PREPARATION METHOD
4.1 PREPARATION FOR TEST
- This work comprises of a number of sequential steps to prepare for the test Preparation steps are:
a) Inspecting and reinforcing cap of testing pile
- Testing pile shall be 10 - 30 cm higher In case pile is higher or lower than that value, there must be measures for processing and reinforcing pile cap:
+ For pile higher than 10 - 30 cm, the exceeding portion shall be cut off by cutting machine to avoid impacting the remained section of pile Pile cap shall then be filed and applied with plaster to achieve evenness and smoothness of pile cap, then a pile cap cover shall be used for preventing local damage Pile cap cover is made from high strength steel, made into two circular halves having radius of 20cm The two halves are placed on pile cap and then fastened by bolts
+ For pile lower than 10 - 30 cm, if pile cap is not intact anymore, the pile cap is processed as above, then a connecting section of high strength steel shall be installed to achieve correct height If the pile cap is intact, a connecting section of high strength steel shall be installed to achieve correct height
b) On the site, checking pile to ensure that test pile has met requirements to conduct test and have been reinforced as required by the design
c) Checking testing equipment:
Trang 23+ The system of testing equipment must be strictly inspected before being put into use Hydraulic jacks must be checked for lift capacity, and gages checked for sensitivity
+ Checking safety of weigh supporting system and bearing system
4.2 CONDUCTING EXPERIMENT
⁄
a) After completing preparation of cap of testing pile, inform the ` loyeand Consultant to check if test pile is eligible for test before moving to the next steps
b) After completing step c above, person in charge is responsible for informing the Employer, Consultant and Supervisor before commencing test
c) Test shall be conducted in accordance with aforesaid test procedure d) Test must be conducted continuously until the end
In case accident or abnormal event during test, technician in charge shall timely inform the Employer, Consultant and Supervisor to have appropriate remedy action
e) Data must be recorded fully, clearly, without correction and is timely transferred to office for timely processing
f) Testing personnel: For each test system, there shall be 2 staff (01 technician recording results, and 01 assisting worker)
g) Canvas shall be used for protecting testing area from weather impacts as well as other external impacts which may affect test results
V WORK SAFETY MEASURES:
- Individuals who are not assigned or do not have duties are not allowed to enter or stay in the testing area
- While crane is being operated, all individuals are prohibited from walking or standing within operation radius of crane
- When working at height, operating workers must have safety devices in accordance with labor safety regulations
- Technicians in charge must regularly check safety conditions of equipment involved: Hook of counterweight system, crane hook, crane cable, crane outrigger plates, counterweight supports, safety and stability of steel beam supporting counterweight
- After completing placement of counterweight, technician shall conduct final check to ensure safety requirements are met before conducting the next step
Trang 24- All unauthorized individuals are prohibited from using testing equipment Only technicians assigned to conduct test are allowed to use these testing equipment
VI IMPLEMENTATION PLAN
6.1 TEST IMPLEMENTATION SCHEDULE:
- On-site progress is calculated from the date of site handover by P:
project, the testing agency estimates schedule for each testing pile as › fll
+ Transporting counterweights, processing pile cap, installing testing nipment and conducting test preparation: 0,5 day
+ Conducting test: 2,0 day (estimated)
- As such, estimated time for 1 testing pile is 2,5 days Test report 02 day 6.2 ORGANIZATION CHART
CONSULTANT ia
TECHNICAL ACCOUNTING OFFICE
+ Lp Vv PROJECT MANAGER Transferripg data Ý TECHNICIAN ON-SITE b> On-site information TECHNICIAN IN OFFICE WORKER CONDUCTING TEST Ỷ OFFICES A a”
Description of relationship between headquarters and on-site management of the site organization structure
In order to carry out the consultancy of pile testing for the purpose of ensuring the best quality, progress, reasonable price and ensuring safety of the project and workers during the project implementation process, test consultant team will perform the following tasks:
* Leading pile quality inspection
- Responsible for regulating test procedure in accordance with the current norms and regulations
- Providing instructions for important technical issues - Reviewing and approving test result report
Trang 25- Formulating project technical and quality management documents - Determining staff for conducting test and duties of testing personnel
- Cooperating with managers of contractors and the Employer to determine issues ~~
to be deal with and relevant documents to be provided
- Organizing works : Sf
- Checking project progress and quality, conducting acceptancesof các proj
item, signing payment documents
- Leading the revision of contract documents and technical documents * Consultant
- Advising technical issues before and during test, checking pile quality
- Reviewing test results * Testing personnel on-site
- Check the all condition of equipment before putting it into the test
- Checking all positions, elevation, pile cap processing and other preparation steps before commencing test as specified in approved outline
- Monitoring equipment operation during the whole course of test and observing norms and procedures, and inspecting quality of pile
* Workers conducting test and other individuals participating in the test: - Supporting the test consultant team to accomplish their duties
- Acting safely during test
- Restoring site after completion of test * Office of test consultant team
' - Assisting members of test consultant team, arranging office works to ensure high effectiveness of consultancy
- Processing data recorded and measured on-site to formulate test result report 6.3 FORMULATION OF TEST RESULT REPORT
- Document formulation and result calculation must be conducted immediately after the end of the field test
+ Test data of each testing pile shall be transferred to office for consolidating and calculating, and results shall be submitted to the Designer no later than 03 days after the completion of test of that pile
Trang 26+ Formulation of test result report shall be conducted immediately after completion of test of the last testing pile, and the report shall be submitted no later than 03 days to the Employer and the Designer
VII TEST RESULTS ON N
7.1 TABLES <= —=
- Data of load, time, settlement recorded during test is processed aind-présent
Bề
the forms of table of “Axial compressive load test” and summary of test results” 7.2 GRAPHS
Based on test data, following graphs shall be formulated: - Load - movement graph
- Movement - time graph - Load - time graph
- Load - movement - time graph 7.3 EXPLANATION
The Explanation comprises of: - Purpose of test;
- Test method;
- Testing equipment - Test procedure - Test results
- Conclusions and suggestions 7.4 APPENDIX OF REPORT Appendix comprises of:
- Form of test data;
- Diagram of test pile arrangement;
- Certificate of testing equipment inspection
Trang 27Phụ lục B (Quy định) ! CÁC BIẾU ĐỒ QUAN HỆ
Tai trong (tan)
£ £ 3 ss = 2 Oo
Hình B1: Biểu dé quan hệ tải trọng - chuyén vị
Thời gian (phứ")
€ =
i =
õ
Hình B2: Biểu đồ quan hệ chuyển vị ~ thời gian = = 2 s T 4 £ thời gian (phút) 8 £ = = -§ ‘ 3 ầ oO
Hình B3: Biểu dỗ quan hệ tải trọng - thời gian ~ chuyển vị
I
thời gian (phút)
Minh Ba: Biểu đồ quan hệ tải trọng ~ thời gian
Trang 28DIAGRAM OF TEST UNDER AXIAL COMPRESIVE LOAD Notice:
1 - Testing pile 4 - Reference beam 2 - Hydraulic jack 5 - Reference rod
3 - Dial gage 6 - Test beam
Trang 29
CONG HOA XA HOI CHU NGHIA VIET NAM
Doc lap - Tu do - Hanh Phuc
Ky CONG TY CO PHAN TU VAN BO LUGNG
= (Metrology Advisory Joint Stock Company)
Add: 22A Ngõ 294 Kim Mõ - Bq Đình - Hà Nội Dk 102 Tel: 024 3846 1326 - Email: Tuvandoluong294@gmail.com
GIAY CHUNG NHAN HIEU CHI J
(Calibration Certificate) ke
Số @ø): CN5.M.519.22
Tén phuong tién do (Object): Kích thủy lực (Hydraulic Jack)
Kiểu (pe): Thuy luc (Hydraulic power) Sé (Serial Ne): 260506
Cơ sở sản xuất (Manufacturer): Trung Quéc (China)
Dac trung k¥ thuat (Technical Specification): Pham vi do (Range): (0 + 2 000) kN
Co s& sit dung (Customer): Công ty cổ phần Thí nghiệm Khảo sát và Xây dựng Bạch Dang Phương pháp thực hiện (n zccordance with): DLVN 108 : 2002
Phương tiện đo lực - Quy trình hiệu chuẩn
(Force measuring Instrument - Methords and means of calibration)
Chuẩn được sử dung (Standards used): Loadcell NH 2000
gs Xem kết quả hiệu chuẩn trang sau
Ket qua (Results):
(See the results of the calibration on the next page)
Ngày hiệu chuẩn dé nghi (Recalibration recommended): 20 - 07 - 2023
Ngày 20 tháng 07 năm 2022 (Rete of GG eration)
Trưởng phòng thi nghiệm SOẠN
DON
(Head of the calibration Laboratory)
Ngô Hưng Phong
Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu không được sự đồng ý bằng văn bản của Công ty cổ phần Tư Vấn Đo lường
(This calibration certificate shall not be reproduced except in full, without written approval of Metrology „Js€)
Trang:
Trang 30+ 5
2
Hà
KẾT QUẢ HIỆU CHUẨN
(Calibration resulis) TT Lực đo Số chí trên ¿ đồng hỗ, Zz
(Number) (Measured force) (Value onthe: 6060) J ye
(KN) (MPa) ` 01 0 0,0 02 400 8,9 03 600 13,3 04 800 17,8 05 1000 22,2 06 1 200 26,6 07 1 400 30,9 08 1 600 35,0 09 1 800 39,2 10 2000 43,5 f(x) = 0,026 x” + 44,8 x f(x) la luc nén, x 1A số chỉ trên đồng hồ
* Nhiệt độ hiệu chuẩn (Calibration temperature): 28 °C
Với độ không đảm bảo đo mở rộng (Wh the uncertainty of): U = 1,2x10"
Hệ số phủ k = 2 với mức tin cậy P = 95%
Trang: (N2 of pages)
Kèm theo giấy chứng nhận hiệu chuẩn số (attached to certijicate NY: CNS.M.519.22
Trang 31
, CONG HOA XA HOI CHU NGHIA VIET NAM
Độc lập - Tự do - Hanh Phuc
fi) CONG TY C6 PHAN TU VAN BO LUGNG
— (Metrology Advisory Joint Stock Company) Bk 102 Add: 22A Ngõ 294 lim Ma - Ba Binh - Ha Ndi
Tel: 024 3846 1326 - Email: Tuvandoluong294@gmail.com
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate) LS Số (00: CNS.M.523.2 ^
Tén phuong tién do (Object): Kích thuỷ lực (Hydraulic Sàn | h ae
Kiểu (type): CLS-5008 S6 (Serial Ne) : “072003-1
Cơ sở sản xuất (Manufacturer): USA
- Đặc:trưng kỹ thuật (Technical Specification): Pham vi do (Range): (0 + 5 000) KN
Co sé sit dung (Customer): Céng ty cô phần Thí nghiệm Khảo sát và Xây dựng Bạch Đằng
Phuong phap thuc hién (in accordance with): DLVN 108 : 2002 /
Phương tiện đo lực — Quy trình hiệu chuẩn
aS ig ig l y b
2006 (Force measuring Instrument - Methords and means of calibration)
CONG FY a PHA ân được sử dụng (Standards used):
Loadcell NH 2000 va NH 6000
sone Dau do (Loadcells) duge két néi voi VMI có U = 0,3x107
sy
XS Kết quả (Results): Xem kết quả hiệu chuẩn trang sau
(See the results of the calibration on the next page)
Ngày hiệu chuẩn đề nghị (Recalibration recommendea): 20 - 07 - 2023
Ngày 20 tháng 07 năm 2022
(Date of Calibration)
Trưởng phòng thí nghiệm
(Head of the calibration Laboratory)
⁄ ⁄
Ngô Hưng Phong
Trang: 1/2 Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu khơng (N9 nan được sự đồng ý bằng văn bản của Công ty cổ phần Tư Vấn Do lường
- b
(This calibration certificate shall not be reproduced except in full, without written approval of Metrology.,Jsc)
Trang 32
Két QUA HIEU CHUAN
(Calibration results) Luc do Số chỉ trên đồng hà
TT (Measured force) (Value on the gauge) SS
(Number) Ep (KN) <{MPa)- “Ss 01 0 0 02 1000 03 1 500 19,8 04 2 000 26,4 05 2 500 33,0 06 3 000 39,5 07 3 500 45,9 08 4 000 52,4 09 4 500 59,0 f(x) = 0,013 x’ + 75,65 x f(x) la luc nén, x là số chỉ trên đồng hồ
*Nhiệt độ hiệu chuẩn (Calibration temperarure): 28 °C
Độ không đảm bảo đo mở rộng (With the uncertainty): U = 1,6 x10”
Hệ số phủ k = 2 với mức tin cậy P = 95%
Trang: Kèm theo giấy chứng nhận hiệu chuẩn số (attached !o certificate NÓ:
(N2 of pages} CNSM.523.22
Trang 33
CONG HOA XÃ HỘI CHỦ NGHĨA VIET NAM
Doc lap - Tu do - Hanh Phuc
⁄ ` CONG TY CO PHAN TU VAN DO LUONG
ss (Metrology Advisory Joint Stock Company) Add: 22A Ngõ 294 Kim Mư - Bơ Đình - Hà Nội Dk 102 Tel: 024 3846 1326 - Email: Tuvandoluong294@gmail.com
)O LƯỜI _—— ‘NH TH Ss
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate)
Số œ): CN5.M.524.22
Tên phương tiện đo (Ou/eo: Kích thuỷ lực /yảauhc%5ck Ỷ
Kiểu (pa): CLS-5008 Số (Serizl M) :
Cơ sở sản xuất (Manufacturer): USA
Đặc trưng kỹ thuật (Technical Specification): - Phạm vi đo (Rznge): (0 + 5 000) kN
Cơ sở sử dụng (Customer): Céng ty cơ phần Thí nghiệm Khảo sát và Xây dựng Bạch Đằng
Phương pháp thực hiện (Jn accordance with): DLVN 108 : 2002
Phương tiện đo lực — Quy trình hiệu chuẩn
(Force measuring Instrument - Methords and means of calibration)
uan duge str dung (Standards used): Loadcell NH 2000 va NH 6000
Đầu đo /7oadeells) được kết nối với VMI có U =0,3x107
Xem kết quả hiệu chuẩn trang sau
(See the results of the calibration on the next page)
Ngày hiệu chuẩn đề nghị (Recalibration recommended): 20 - Ú7 - 2023
Ngày 20 tháng 07 năm 2022
(Date of Calibration)
Trưởng phịng thí nghiệm
(Head of the calibration Laboratory)
⁄
Ngô Hưng Phong
Không äược sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu không được sự đồng ý bằng văn bản của Công ty cổ phần Tư Vấn Do lường
(This calibration certificate shall not be reproduced except in full, without written approval of Metrology.,Jsc)
Trang: 1/2
(N® of pages)
Trang 34
Két QUA HIEU CHUAN
(Calibration results) Luc do Số chỉ trên đồng hồ
TT (Measured force) (Value on the gauge) (Number) (KN) (MPa)⁄⁄ ` 01 0 AO AD 02 1 000 << 13,2 về 03 1 500 SN 04 2 000 26,5 ` 05 2 500 33,0 06 3 000 39,5 07 3 500 45,9 08 4 000 52,4 09 4 500 58,9 f(x) = 0,016 x°+ 75.5x f(x) là lực nén, x là số chỉ trên đồng hồ
*Nhiệt độ hiệu chuẩn (Calibration temperature): 28 °C
Độ không đảm bao do mé réng (With the uncertainty): U = 1,5 x10? Hé s6 pha k = 2 với mức tin cậy P = 95%
Trang: Kèm theo giấy chứng nhan hiéu chudn so (attached to certificate NY):
(N9 af wages! CNS.M.524.22
Trang 35
CONG HOA XA HOI CHU NGHIA VIET NAM
Độc lập - Tự do - Hạnh Phúc
CÔNG TY CỔ PHẦN TU VẤN ĐO LƯỜNG
SS (Metrology Advisory Joint Stock Company) Add: 22A Ngõ 294 Kim Ma - Ba Dinh - Hè Nội pk.102 Tel 024 3846 1326 - Ernail: Tuvandoluong294@gmai.com
é 4 ~ ~ a
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate) :
Sé (ne): CNS.M.526.22
Tên phương tién do (Odject): Kích thuỷ lực (Hydraulic Jack) or
z8 „ YH
Kiểu (type): CLS-5008 Số (SerialM) : 010205
Cơ sở sản xuất (Manufacturer): USA
Dac trung ky thuat (Technical Specification): Pham vi do (Range): (0 + 5 000) kN
Cơ sở sử dụng (Customer): Céng ty cé phan Thi nghiém Khao sat và Xây dựng Bạch Đằng Phương pháp thực hiện (In accordance with): ĐLVN 108 : 2002
Phương tiện đo lực - Quy trình hiệu chuẩn (Force measuring Instrument - Methords and means of calibration)
an duge sit dung (Standards used): Loadcell NH 2000 va NH 6000
Dau do (Loadcells) được kết nỗi với VMI có U = 0,3x107
An Xem kết quả hiệu chuẩn trang sau
et qua (Results):
(See the results of the calibration on the next page)
Ngày hiệu chuẩn đề nghị (Recalibration recommended): 20 - 07 - 2023
Ngày 20 tháng 07 năm 2022 (Date of Calibration)
Giam déc
Trưởng phịng thí nghiệm (Head of the calibration Laboratory)
Ngô Hưng Phong LIES Nob Viel Hong
Trang: Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu không (N9 : 3) được sự đồng ý bang van ban cia Cong ty cổ phần Tư Vấn Đo lường
Trang 36co
X*
Sa
^
KẾT QUẢ HIỆU CHUẨN
(Calibration results) Luc do Số chỉ trên đồng hồ
m (Measured force) (Value on the gauge) (Number) (kN) 01 0 02 1000 03 1 500 04 2 000 05 2 500 06 3 000 07 3 500 45,8 08 4000 52,3 09 4500 58,7 f(x) = 0,014x°+75,75x
Í(x) là lực nén, x là số chỉ trên đông hô
*Nhiệt độ hiệu chuẩn (Calibration temperature): 28 °C
Độ không dam bao do mé rong (With the uncertainty): U = 1,4 x10?
Hệ số phủ k =2 với mức tin cậy P = 95%
Trang:
(NE of page 12
Kèm theo giấy chứng nhận hiệu chuẩn số (attached to certifìcate N9:
CNS.M.526.22
Trang 37
CONG HOA XA HOI CHU NGHIA VIET NAM
Độc lập - Tự do - Hạnh Phúc
⁄⁄» CONG TY CO PHAN TU VAN DO LUONG
z (Metrology Advisory Joint Stock Company)
Add: 22A Ngõ 294 Kirn Ma - Ba Dinh - Hà Nội
Đkl2 1:022346154 - moi TuondoLong294@onelcom
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate)
86 (a2): CN5.M.525.22
Tén phuong tién do (Object): Kich thuy lwe (Hydraulic Ja — LP
S LAS 09-7
Kiểu (pe): CLS-5008 Sé (Serial M2) S<SS0108~
*
Co sé san xuat (Manufacturer): USA
Dac trung k¥ thuat (Technical Specification): Pham vi do (Range): (0 + 5 000) KN
Cơ sở sử dụng (Cusrome): _ Công ty cổ phần Thí nghiệm Khảo sát và Xây dựng Bach Dang Phương pháp thực hiện (1n accordance with): DLVN 108 : 2002
Phương tiện đo lực - Quy trình hiệu chuẩn
(Force measuring Instrument - Methords and means of calibration)
an duoc str dung (Standards used): Loadcell NH 2000 va NH 6000
Dau do (Loadcells) dugc két ndi voi VMI có U = 0,3x107
Đo Xem kết quả hiệu chuẩn trang sau
Kết quả (Resuiis):
(See the results of the calibration on the next page)
Ngày hiệu chuẩn đề nghị (Recalibration recommended): 20 - 07 - 2023
- Ngày 20 tháng 07 năm 2022
(Date of Calibration)
Trưởng phịng thí nghiệm
(Head of the calibration Laboratory)
Ngé Hung Phong
Trang: Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu khơng (N9 oƒ, " được sự đồng ý bằng văn bản của Cơng íy cổ phần Tu Vấn Đo lường
° (This calibration certificate shall not be reproduced except in full, without written ajproval of Metrology.,Jsc)
Trang 38
KET QUA HIEU CHUAN
(Calibration results) Luc do Số chỉ trên đồng hồ
m (Measured force) Wal on ihe gaa NN
(Number) (kN) (mpg ˆ ) | 01 0 SA 0q 02 1000 13,48 03 1500 20,0 04 2 000 26,7 05 2 500 33,4 06 3 000 40,0 07 3 500 -46,5 08 4000 53,1 09 4500 59,6 f(x) = 0,016 x? + 74,8 x f(x) 14 hie nén, x là số chỉ trên đồng hồ
*Nhiệt độ hiệu chuẩn (Calibration temperature): 28 °C
Độ không đảm bảo đo mở rộng (With the uncertainty): U = 1,4 x10?
Hệ số phủ k = 2 với mức tin cậy P = 95%
Trang: 2/2
(NE of pages)
Kem theo gidy chung nhan hiéu chudn sé (attached to certificate N9:
CN5.M.525.22
Trang 39
CỘNG HOÀ XÃ HỘI CHỦ NGHĨA VIỆT NAM
Độc lập - Tụ đo - Hạnh Phúc
se 2 x # `
iY CONG TY C6 PHAN TU VAN ĐO LƯỜNG
(Metrology Advisory Joint Stock Company)
Add: 22A Ng6 294 kim Ma - Ba Dinh - Ha NGi
Tel 024 3846 1326 - Email: Tuvandoluong294@gmail.com
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate)
Số (): CN4.M.572.23
Tên phương tiện do (Object): Đồng hồ đo biến đạng Km Z2 } : we Kiểu (type): Mitutoyo S6 (Serial 4) K90 255
Co s@ san xuat (Manufacturer): Japan "
Đặc trưng kỹ thuật (Technical Specification): Pham vi do (Range): (0 + 50) mm
Do phan giai (Resolution): d= 0,01mm
Cơ sở sử dụng (Customer): Céng ty cổ phần Thí nghiệm Khảo sát và Xây dựng Bạch Đăng
Phương pháp thực hiện (1n aecordanee with): M.08 - 2011
Đồng hồ đo biến dạng - Quy trình biệu chudn (Methods and means of calibration)
Chuan duoc str dung (Standards used): M.TB3.11 Can mau, may kiém déng hồ so
Độ không đảm bảo đo 0,110”
Nhiệt độ hiệu chuẩn (Calibration temperature): 28 °C
Sai số thành phan: + 26 pm D6 hdi sai: 6 um
Với độ không đám bảo do (With the uncertainty of):
U=(5,8+ 6,2 L) pm L tinh bằng (m)
Kết quả (Resulis):
Ngày hiệu chuẩn đề nghị (Recalibration recommended): 12 - 06 - 2024
Ngày 13 tháng 06 năm 2023
(Date of Calibration)
Trưởng phịng thí nghiệm Giám đốc
(Director)
(Head of the calibration Laboratory)
GIÁM ĐỐC
Ngô Hưng Phong xi?
Trang: Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu khơng
(N9 đƑ Da) § được sự đồng (This calibration certificate shall not be reproduced except in full, without wrinen approval of Metrology.,Jsc) ý bằng văn bản của Công ty cổ phần Tư Vấn Đo lường
Trang 40
CONG HOA XA HOI CHU NGHIA VIET NAM Doc lap - Tu do - Hanh Phuc
CÔNG TY CỔ PHAN TU VAN DO LUONG
(Metrology Advisory Joint Stock Company)
Add: 22A Ngõ 294 Km Mö - Bơ Đình - Hị Nội
Tel: 024 384ó 132ó - Email: Tuvandoluong294@gmail.com
GIAY CHUNG NHAN HIEU CHUAN
(Calibration Certificate)
Số @): CN4.M.573.23
Tên phương tiện đo (0ð/eci): Đồng hồ đo bién dang (Dial ee ——
Kiểu (Type): Mitutoyo S6 (Serial We): 90 293 | 9
„ SS /
Co s& san xuat (Manufacturer): Japan ` “ Dac trung k¥ thuat (Technical Specification): Pham vi do (Range): (0 + 50) mm
Độ phân giải (Resolution): d = 0,01mm
Co sé sit dung (Customer): Céng ty cé phan Thi nghiém Khao sat va Xay dung Bach Dang Phuong phap thuc hién (/n accordance with): M.08 - 2011
Đồng hỗ đo biến đạng — Quy trình hiệu chuẩn (Methods and means of calibration)
Chuan due st dung (Standards used): M.TB3.11 Cari mau, may kiém déng hd so
Độ không đảm bảo đo 0,1x10”
Nhiệt độ hiệu chuẩn (Caiibration 1emperaitire): 28 °C
Sai số thành phan: + 28 um D6 hồi sai: 6 um
Với độ không đảm bao do (With the uncertainty of):
U = (5,8 + 6,2 L) pm L tinh bằng (m)
Kết qua (Results):
Ngày hiệu chuẩn đề nghị (Recalibration recommended): 12 - 06 - 2024
Ngày 13 tháng 06 năm 2023
> (Date of Calibration)
Trưởng phịng thí nghiệm Giám đốc
(Head of the calibration Laboratory) (Director)
GIÁM ĐỐC
Nog Vick Humg
Ngô Hung Phong
? > —
Trang: Không được sao chép rời khi giấy chứng nhận hiệu chuẩn có nhiều trang nếu không (Ng of pages! t được sự đồng ý bằng văn bản của Công ty cổ phần Tư Vấn Đo lường
(This calibration certificate shall not be reproduced except in full, without written approval of Metrolo, gy.,JSC)