1. Trang chủ
  2. » Ngoại Ngữ

Risks-Involved-in-Using-Alternative-Project-Delivery-APD-Methods-in-Water-and-Wastewater-Projects

5 1 0

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Nội dung

Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 145 (2016) 219 – 223 International Conference on Sustainable Design, Engineering and Construction Risks Involved in Using Alternative Project Delivery (APD) Methods in Water and Wastewater Projects Pramen P Shresthaa*, Ph.D., P.E., Jacimaria Batistab, Ph.D., and Ruiko Maharajanc, P.E a Associate Professor, Department of Civil and Environmental Engineering and Construction, Howard R Hughes College of Engineering, University of Nevada, Las Vegas, 4505 S Maryland parkway, Las Vegas, NV 89154, USA b Professor, Department of Civil and Environmental Engineering and Construction, Howard R Hughes College of Engineering, University of Nevada, Las Vegas, 4505 S Maryland parkway, Las Vegas, NV 89154, USA c Ph.D Student, Department of Civil and Environmental Engineering and Construction, Howard R Hughes College of Engineering, University of Nevada, Las Vegas, 4505 S Maryland Parkway, Las Vegas, NV 89154, USA Abstract There are risks involved in the design and construction of projects, and several studies have been conducted in identifying the risks involved in using traditional delivery method (Design Bid Build) in the design and construction of the projects However, little research has been done in identifying the risks involved in using Alternative Project Delivery (APD) methods in the design and construction of water and wastewater projects The identification of these risks could assist in improving project performance of future projects that use APD methods A survey was conducted to identify the risks involved in using APD methods for the design and construction of water and wastewater projects The respondents of the survey were owners, policy makers, utility managers and project managers who had used APD methods for their water and wastewater projects The survey results showed that the top three risks in using APD methods were 'discomfort with change from traditional delivery method', 'lack of qualified personnel within the organization', and 'loss of control of the design process' One of the recommended approaches provided by the respondents to address these risks was to educate the owners’ policy makers and project staffs regarding the APD methods Keywords: Risk; Alternative Project Delivery method; Design Build; Construction Management-at-Risk; Risks Introduction People have different perceptions on the use of Alternative Project Delivery (APD) methods Out of many APD * Corresponding author Tel.: 702-895-3841; fax: 702-895-3936 E-mail address: pramen.shrestha@unlv.edu 1877-7058 © 2016 The Authors Published by Elsevier Ltd This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/) Peer-review under responsibility of the organizing committee of ICSDEC 2016 doi:10.1016/j.proeng.2016.04.064 220 Pramen P Shrestha et al / Procedia Engineering 145 (2016) 219 – 223 methods existing, this study focused on Design Build (DB) and Construction Management-at-Risk (CMAR) project delivery methods The identification of perceptions about use of these non-traditional methods will help to improve their use in future projects These perceptions may be a result of a paradigm or an individual’s experience on these delivery methods, and were analysed based on such factors as cost growth, schedule growth, and the quality of the project Previously, some studies have been conducted on projects that used DB and CMAR as delivery method Shrestha et al (2014) has conducted a survey with water and wastewater infrastructures’ owners to measure the satisfaction rating with the use of DB and CMAR in the design and construction of the projects The survey found that owners were satisfied with the level of owner’s involvement in the design process, the quality of the completed project, and the owner’s communication process [1] Based on an analysis of 351 general building projects build in U.S from year 1990 to 1996, Strange [2] found that DB projects had significantly less design and construction cost growth when compared to projects using traditional delivery methods (Design Bid Build) In addition, the DB projects were better in terms of quality performance With CMAR as the APD method used for construction projects, some portion of cost risk is transferred to construction manager [3] In a study by Knise [4], when using a DB method, the engineers involved as designers were less liable for risk compared to contractors; mostly, when the lines of responsibility are unclear, DB project delivery method may lead to more risk to the engineer Finally, various additional risks associated with APD methods should be taken in account by reviewing their existing insurance policy, determining if there are any gaps in the coverage, and if required considering additional insurance coverage [4] Research Methodology A questionnaire was prepared using Qualtrics software in a joint effort of Research Task Force of the Water Design Build Council (WDBC) and Principal Investigators at the Department of Civil & Environmental Engineering and Construction at the University of Nevada, Las Vegas (UNLV) This questionnaire was sent online to such individuals as policy makers, utility managers, and project managers who used APD methods in water and wastewater projects between October 1, 2013 and November 15, 2013 Out of 14 questions prepared, three were related to risk issues that exist within their organizations and solicited suggestions on the mitigation methods for these issues Out of 124 responses, 104 complete responses were received; only completed responses were used for data analysis Results The respondents were asked to identify their perception(s) about risk issues that may exist within their organization, and which are or could become an impediment to using DB or CMAR delivery methods for water or wastewater projects As shown in Figure 1, the top three issues that the respondents identified were 'discomfort with change from traditional delivery method', 'lack of qualified personnel with DB or CMAR project', and 'loss of control of the design process' This was a multiple choice question, so the total percentage did not add up 100% Pramen P Shrestha et al / Procedia Engineering 145 (2016) 219 – 223 Figure Risk issues that could become impediments in using DB or CMAR delivery methods (total number of respondents = 95) In addition, the respondents identified various other risk issues that exist within their organization, and which are or could become impediments to using DB or CMAR delivery methods in water and wastewater projects Table shows the other risk issues stated by the respondents Table Identified Risk Issues that Exist Within Organizations S No Risk Issues in DB & CMAR Delivery Methods Influence of state regulations Procurement policies and methods Education Selection process issues Labor unions Unrealistic owner expectation of transferring all risk to the DB/CMAR firm, resulting in loss of profit by means of litigation Inability to award all work to single entity under professional contract Complexity of upgrade projects is difficult with DB Inability to create requirements documents in the early phase of design 10 High time commitment by internal staff is required 11 Concern that local contractor become excluded 221 222 Pramen P Shrestha et al / Procedia Engineering 145 (2016) 219 – 223 Then, the respondents were asked to rank all the risk issues that they have identified in the previous question As shown in Figure 2, the survey results showed that the risk issues mentioned in the category of 'others' were ranked as the top risk issue, followed by 'DBB is the preferred delivery method for delivering project in our organization' and then 'discomfort with change from traditional delivery method' Figure Ranking of risk perceptions that may exist within an organization (total number of respondents = 54) For the future improvements in these APD methods, the respondents were asked to provide suggestions or methods that have been successful previously in addressing impediments to using DB or CMAR delivery methods in water and wastewater projects The suggestions provided by the respondents are summarized in Table Table Recommended Approaches to Addressing Impediments to Using DB or CMAR Delivery Methods S No Risk Issues in DB & CMAR Delivery Methods Using successful projects as benchmarks Hiring a well-qualified DB or CMAR team Educating policy makers, owners, senior staff, municipal government, consulting firms, and clients about the risks in using APD methods via trusted professional organizations (e.g., ASCE, AWWA, APWA Flexible procurement in legislation to meet some local preferences Promote fair and open competition for opportunity to work on alternative delivery projects Integrated training for consultants, contractors, and owner staffs Use the Progressive Design-Build method Prepare a detailed scope of work, request a turnkey proposal, and provide applicable drawings and operating data Focus on schedule reduction by fast tracking 10 Allow alternate delivery methods all across the U.S 11 More input from all staff, and knowledge of 'chain of approvals' Pramen P Shrestha et al / Procedia Engineering 145 (2016) 219 – 223 Conclusion The majority of respondents were experienced decision makers in either DB or CMAR or both delivery methods in their water and wastewater projects The major risk issue that could become an impediment to using DB or CMAR delivery methods, according to most respondents, was 'discomfort with change from traditional delivery method' Except for the risk issues listed in the questionnaire, many respondents perceived other risk issues They ranked the top perceived risk issues as 'others', followed by 'design-bid-build is the preferred delivery method for their organization' The major suggestions in addressing impediments to using DB or CMAR delivery methods included educating and training the decision makers (policy officials, project staff, and procurement and legal staff) regarding these delivery methods and changing the state procurement rules Acknowledgements We would like to thank the Water Design Build Council for providing funding and support for this research References [1] Shrestha, P.P., Maharjan, R., Shakya, B., and Batista, J (2014) Alternative Project Delivery Methods for Water and Wastewater Projects: The Satisfaction Level of Owners Proceedings of Construction Research Congress, American Society of Civil Engineers, Atlanta, Georgia, May 19-21, 2014 [2] W Strange The Risk in CM-At-Risk CM eJournal, (2015) (Access 12/15/2015) [3] Construction Industry Institute Research (2015) Project Delivery Systems: CM-at-Risk, Design-Build, DesignBid-Build; Summary 133-1 https://store.construction-institute.org/detail.aspx?id=RS133_1> (Access 12/20/2015) [4] Knise, D (2015) Alternate Project Delivery Brings Risk with Rewards Civil + Structural Engineer ENews (Access 12/22/5015) [5] Smith Currie & Hancock LLP (2015) Alternative Project Delivery Methods – Risks and Challenges Common Sense Contracting (Access 12/24/2015) 223

Ngày đăng: 30/10/2022, 17:42

w