0
  1. Trang chủ >
  2. Kinh Tế - Quản Lý >
  3. Quản lý dự án >

Tài liệu Project Planning and Control Part 7 pptx

Tài liệu Project Planning and Control Part 7 pptx

Tài liệu Project Planning and Control Part 7 pptx

... 521 77 7 70 588 62 77 7 70 588 62 77 7Erect vessel 11 1 11 92 138 12 101 11 138 12 101 11 138Erect bridge sect. A 12 4 62 521 77 7 60 504 62 77 7 60 504 62 77 7Erect bridge sect. B 13 4 62 521 77 7 ... suction pipe 1 36 7 – – – 8 100 7 8 100 7 Weld suction pipe 1 37 7 – – – 5 100 7 5 100 7 Support suction pipe 1 38 4 – – – 4 80 3 5 100 5Erect discharge pipe 1 39 6 5 70 4 7 100 6 7 100 6Weld discharge ... 5Erect suction pipe 2 56 7 5 60 4 8 100 7 8 100 7 Weld suction pipe 2 57 7 – – – 5 100 7 5 100 7 Support suction pipe 2 58 4 – – – 2 40 2 4 100 4Erect discharge pipe 2 59 6 6 70 4 8 100 6 8 100 6Weld...
  • 33
  • 475
  • 0
Tài liệu Project Planning and Control Part 1 pptx

Tài liệu Project Planning and Control Part 1 pptx

... 0.895 0. 877 0. 870 0.862 0.8 47 0.833 0.820 0.806 0.800 0 .79 4 0 .78 1 0 .76 9 0 .74 1 0 .71 4 0.690 0.6 67 2 0.980 0.961 0.925 0.890 0.8 57 0.826 0 .79 7 0 .76 9 0 .75 6 0 .74 3 0 .71 8 0.694 0. 672 0.650 0.640 0.630 0.610 ... 0.650 0.5 27 0.429 0.350 0.2 87 0.2 37 0.215 0.195 0.162 0.135 0.112 0.094 0.086 0. 079 0.066 0.056 0.0 37 0.025 0.0 17 0.01212 0.8 87 0 .78 8 0.625 0.4 97 0.3 97 0.319 0.2 57 0.208 0.1 87 0.168 0.1 37 0.112 ... 0 .79 0 0 .70 5 0.630 0.564 0.5 07 0.456 0.432 0.410 0. 370 0.335 0.303 0. 275 0.262 0.250 0.2 27 0.2 07 0.165 0.133 0.108 0.088 7 0.933 0. 871 0 .76 0 0.665 0.583 0.513 0.452 0.400 0. 376 0.354 0.314 0. 279 ...
  • 63
  • 443
  • 1
Tài liệu Project Planning and Control Part 2 pptx

Tài liệu Project Planning and Control Part 2 pptx

... and thus does not affect the logic or overall time ofthe project. It can be seen that activity A still starts at 1 and takes 7 units 67 Figure 11.2Figure 11.3Figure 11.4 Project Planning and ... applied and incorporated in the organization. The output of thisstage is the audit report.63 Project Planning and Control In all these stages resources and facilities must always be considered and arrangements ... monitored and controlled.To this end a Configuration Control Committee is appointed to head up specialInterface Control Groups and Configuration Control Boards which inves-tigate and, where...
  • 39
  • 503
  • 0
Tài liệu Project Planning and Control Part 3 pptx

Tài liệu Project Planning and Control Part 3 pptx

... dummies, an accurate prediction is obtainedimmediately and the float of any particular activity can be seen almost by 97 Project Planning and Control inspection. It will be noted that each activity ... GgAhEgEfGhAj21915103183 7 26162424 7 2 7 526144104291210 7 8 7 62858246434365331234000000002191510318581121119312 7 12182311 3616814141319 27 112012 17 211923303024Duration ... a109 Project Planning and Control Analysis and float calculation (see Chapter 15) is identical to the methodsemployed for arrow diagrams and, if the box is large enough, the earliest and latest...
  • 46
  • 464
  • 0
Tài liệu Project Planning and Control Part 8 pptx

Tài liệu Project Planning and Control Part 8 pptx

... Project Planning and Control Apart from the start and finish, there are four milestones (days 8, 16, 24 and 30). These are described and plotted on the Milestone ... tens, hundreds and thousands. An example of this is shownin Figure 30.5.315Figure 30.4 Toolbar display Project Planning and Control If the original project has been drafted by hand on a large ... through time, and the timescale contracted or expanded to show a larger or smaller slice of the project duration.313Figure 30.1 Hornet Windmill title screen Project Planning and Control 314Figure...
  • 50
  • 435
  • 0
Tài liệu Project Planning and Control Part 4 pdf

Tài liệu Project Planning and Control Part 4 pdf

... 48136816610158 170 13160 170 5166 178 179 16 28 16012406 7 243212 7 7111220000000000001000 0 112012816036816610158 170 13158 171 178 15 16 28012816036816610158 170 13159 171 ... to station 8.0U queue and buy ticket 3.0V board train 1.0 27. 15The total time taken to perform these activities is 27. 15 minutes.1 37 Figure 18.1 Project Planning and Control The first question ... 28012816036816610158 170 13159 171 178 15 16140R 178 178 7 0 171 171 DurationEarlystartEarlyfinishActivityLatestartLatefinishKeyFloatSimple examplesThe network for this project is shown in...
  • 38
  • 549
  • 0
Tài liệu Project Planning and Control Part 5 ppt

Tài liệu Project Planning and Control Part 5 ppt

... always be clarity and ease ofunderstanding. Complex networks only confuse clients, and reflect a lack ofappreciation of the advantages of method statements. 177 Project Planning and Control Integrated ... a project manager to ensure that this faith exists. Where small cracks doappear in this vital bridge of understanding between the planning depart-ment and the operational departments, the project ... Project Planning and Control movements and the crescendos of activities and combine these into aharmonious flow until the grand finale is reached.To facilitate...
  • 46
  • 508
  • 0
Tài liệu Project Planning and Control Part 6 docx

Tài liệu Project Planning and Control Part 6 docx

... 4.4 7. 812.219.430 .7 50316542 78 010 57 15891903355258351320950425250395212261498610010010011401140114080010001000100050801005858101020320400640800608090410590104521036048054040 70 805459141082360480840960 70 859526230433518021025528580809029629632228032032036050284932495585.5 87. 2 87 64.482.291 .7 24933238405445442150 277 035353945 70 00Figure 27. 4Cost control and ... 2Erect frame 31Erect frame 1 7 73344424Erectduct AErectduct B13Erect frames 1, 2& beams AErect frame 3& beams B 7 711 7 Project Planning and Control Any competent supervisor ... 10151525406032505092166304545 75 1206F400 510202550 70 24404550185204080100200Est. final ACT/% 71 826949639354485 176 Effic. VAL/ACT 6062 67 7983.186.2Total4300 4.4 7. 812.219.430 .7 50316542 78 010 57 15891903355258351320950425250395212261498610010010011401140114080010001000100050801005858101020320400640800608090410590104521036048054040 70 805459141082360480840960 70 859526230433518021025528580809029629632228032032036050284932495585.5 87. 2 87 64.482.291 .7 24933238405445442150 277 035353945 70 00Figure...
  • 45
  • 409
  • 0
Tài liệu Project Planning and Control 4E doc

Tài liệu Project Planning and Control 4E doc

... 12.60001121636132611111120 27 04015218 7 6 17 2611241221 27 0362538541102950START ADGMKB50% = 4EHNLCFJFINISH036132691111 17 272 1132025 27 0 074 60 174 2601122110110214 270 2102613211261 270 ActivityDurationEarlystart(ES)Earlyfinish(EF)Latestart(LS)Latefinish(LF)CriticalCriticalCritical ... configurationmanagement and quality management.2 Hard skills such as project organization, project evaluation, project planning, cost control, monitoring, risk management and changemanagement. Project Planning and ... 11.25. Project Planning and Control Analysis and float calculation (see Chapter 15) is identical to the methodsemployed for arrow diagrams and, if the box is large enough, the earliest and latest...
  • 406
  • 1,702
  • 0
Project Planning and Control Part 9

Project Planning and Control Part 9

... curves (budget, planned, actual, value, anticipated final)3 57 Project Planning and Control 340Figure 31.1Figure 31.2 Project Planning and Control Table 32.1 ContinuedDraw time/% curves (% planned, ... projectsvary enormously in scope, size and complexity. Project Planning and Control The sequences and techniques given may therefore have to be changed to suitany particular project. Indeed certain techniques ... Summary table348MS Project 98349Figure 31.10Figure 31.11 Project Planning and Control which shows the status of the project can be obtained from View – Table –Summary and is shown in Figure...
  • 24
  • 352
  • 0

Xem thêm

Từ khóa: kaplan toefl paper and pencil part 7tài liệu dạy và học vật lý 7tài liệu bồi dưỡng hsg toán lớp 7tài liệu thiết kế website với drupal 7tài liệu hướng dẫn sử dụng windows 7 toàn tậptài liệu ôn học sinh giỏi toán 7Nghiên cứu tổ hợp chất chỉ điểm sinh học vWF, VCAM 1, MCP 1, d dimer trong chẩn đoán và tiên lượng nhồi máu não cấpNghiên cứu vật liệu biến hóa (metamaterials) hấp thụ sóng điện tử ở vùng tần số THzGiáo án Sinh học 11 bài 13: Thực hành phát hiện diệp lục và carôtenôitGiáo án Sinh học 11 bài 13: Thực hành phát hiện diệp lục và carôtenôitGiáo án Sinh học 11 bài 13: Thực hành phát hiện diệp lục và carôtenôitNghiên cứu về mô hình thống kê học sâu và ứng dụng trong nhận dạng chữ viết tay hạn chếNghiên cứu tổng hợp các oxit hỗn hợp kích thƣớc nanomet ce 0 75 zr0 25o2 , ce 0 5 zr0 5o2 và khảo sát hoạt tính quang xúc tác của chúngĐịnh tội danh từ thực tiễn huyện Cần Giuộc, tỉnh Long An (Luận văn thạc sĩ)Tìm hiểu công cụ đánh giá hệ thống đảm bảo an toàn hệ thống thông tinSở hữu ruộng đất và kinh tế nông nghiệp châu ôn (lạng sơn) nửa đầu thế kỷ XIXChuong 2 nhận dạng rui roBT Tieng anh 6 UNIT 2Giáo án Sinh học 11 bài 15: Tiêu hóa ở động vậtGiáo án Sinh học 11 bài 15: Tiêu hóa ở động vậtNguyên tắc phân hóa trách nhiệm hình sự đối với người dưới 18 tuổi phạm tội trong pháp luật hình sự Việt Nam (Luận văn thạc sĩ)Giáo án Sinh học 11 bài 14: Thực hành phát hiện hô hấp ở thực vậtBÀI HOÀN CHỈNH TỔNG QUAN VỀ MẠNG XÃ HỘIChiến lược marketing tại ngân hàng Agribank chi nhánh Sài Gòn từ 2013-2015TÁI CHẾ NHỰA VÀ QUẢN LÝ CHẤT THẢI Ở HOA KỲQUẢN LÝ VÀ TÁI CHẾ NHỰA Ở HOA KỲ