Tài liệu Project Planning and Control Part 6 docx

45 409 0
Tài liệu Project Planning and Control Part 6 docx

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

26 Cash flow forecasting It has been stated in Chapter 25 that it is very easy to convert a network into a bar chart, especially if the durations and week (or day) numbers have been inserted. Indeed, the graph- ical method of analysis actually generates the bar chart as it is developed. If we now divide this bar chart into a number of time periods (say, weeks or months) it is possible to see, by adding up vertically, what work has to be carried out in any time period. For example, if the time period is in months, then in any particular month we can see that one section is being excavated, another is being concreted and another is being scaffolded and shuttered, etc. From the description we can identify the work and can then find the appropriate rate (or total cost) from the bills of quantities. If the total period of that work takes six weeks and we have used up four weeks in the time period under consideration, then approximately two-thirds of the value of that operation has been performed and could be certificated. By this process it is possible to build up a fairly accurate picture of anticipated expenditure at the Project Planning and Control beginning of the job, which in itself might well affect the whole tendering policy. Provided the job is on programme, the cash flow can be calculated, but, naturally, due allowance must be made for the different methods and periods of retentions, billing and reimbursement. The cost of the operation must therefore be broken down into six main constituents: Labour; Plant; Materials and equipment; Subcontracts; Site establishment; Overheads and profit. By drawing up a table of the main operations as shown on the network, and splitting up the cost of these operations (or activities) into the six constituents, it is possible to calculate the average percentage that each constituent contains in relation to the value. It is very important, however, to deduct the values of the subcontracts from any operation and treat these subcontracts separately. The reason for this is, of course, that a subcontract is self-contained and is often of a specialized nature. To break up a subcontract into labour, plant, materials, etc. would not only be very difficult (since this is the prerogative of the subcontractor) but would also seriously distort the true distribution of the remainder of the project. Example of cash flow forecasting The simplest way to explain the method is to work through the example described in Figures 26.1 to 26.6. This is a hypothetical construction project of three identical simple unheated warehouses with a steel framework on independent foundation blocks, profiled steel roof and side cladding, and a reinforced-concrete ground slab. It has been assumed that as an area of site has been cleared, excavation work can start, and the sequences of each warehouse are identical. The layout is shown in Figure 26.1 and the network for the three warehouses is shown in Figure 26.2. Figure 26.3 shows the graphical analysis of the network separated for each building. The floats can be easily seen by inspection, e.g. there is a two-week float in the first paint activity (58–59) since there is a gap between the 212 Cash flow forecasting 213 Figure 26.1 Figure 26.2 Construction network Cash flow forecasting 215 Figure 26.3 following dummy 59–68 and activity 68–69. The speed and ease of this method soon becomes apparent after a little practice. The bar chart in Figure 26.5 has been drawn straight from the network (Figure 26.2) and the costs in £100 units added from Figure 26.4. For example, in Figure 26.4 the value of foundation excavation for any one building is £9400 per four-week activity. Since there are two four-week activities, the total is £18 800. To enable the activity to be costed in the corresponding measurement period, it is convenient to split this up into Figure 26.4 0 4 8 12 16 20 24 28 1 2 3 4 5 6 7 8 Site clear Found exc. "" "" Found conc. "" "" Harden Steel erect "" "" Re-bay lay "" "" Slab conc. "" "" Roof sheet "" "" Side sheet "" "" Paint " A B C A B C A B C A B C A B C A B C A B C A B " C Period Weeks 62 62 62 47 47 47 47 47 47 47 47 47 47 47 47 71 71 71 71 71 71 220 220 147 147 73 73 220 220 79 7927 27 79 79 27 27 79 7927 27 35 35 36 36 35 35 36 36 71 71 66 66 66 66 44 44 22 22 80 20 60 40 44 44 22 44 66 44 66 80 80 20 20 60 60 40 40 Units in£x100 Sub-contr. 36 40 9 10 32 Figure 26.5 Total S/C – – – 367 660 381 318 438 % 91 9 % 34 19 32 7 8 0 2 2 1 1 0 0 1 Delay 334 33 216 74 41 69 15 17 74 70 118 31 17 33 583 343 403 60 448 153 85 143 31 36 153 33 55 26 36 448 303 331 28 368 125 70 118 26 29 125 12 29 368 166 154 (12) 171 58 33 55 12 13 58 13 171 71 (71) 600 60 247 84 47 79 17 20 84 85 143 334 15 20 60 907 741 525 (216) 347 34 368 159 89 150 33 37 159 41 69 600 17 37 34 849 957 816 (141) 289 29 284 97 54 91 20 22 97 47 79 347 33 22 29 602 654 764 110 399 39 36 12 7 11 3 3 12 89 150 289 20 3 39 474 602 542 (60) S/C OH&P In 90% Net flow Direct Labour Plant Material Site est. OH&P Outflow Labour Plant Material S/C Site est. OH&P S/C OH&P Total value Out 0 4 8 12 16 20 24 28 Period Week 1 2 3 4 5 6 7 8 354 128 322 32 54 91 399 3 32 354 579 427 (152) 116 12 7 11 322 12 116 128 352 319 (33) 116 115 (1) 32 36 40 4 4 9 10 11 Figure 26.6 Cash flow forecasting two-weekly periods of £4700. Hence in Figure 26.5, foundation excavation for building A is shown as 47 in period 1 47 + 47 = 94 in period 2 47 in period 3 The summation of all the costs in any period is shown in Figure 26.6. The table in Figure 26.6 clearly shows the effect of the anticipated delays in payment of certificates and settlement of contractor’s accounts. For example, material valued at 118 in period 2 is paid to the contractor after one month in period 3 (part of the 331, which is 90% of 368, the total value of period 2), and is paid to the supplier by the contractor in period 4 after the two-month delay period. From Figure 26.6 it can be seen that it has been decided to extract overhead and profit monthly as the job proceeds, but this is a policy that is not followed by every company. Similarly, the payment delays may differ in practice, but the principle would be the same. It will be noted that there is a positive cash flow in only three of the eleven measurement periods, and suitable finance charges must, therefore, be added to the contract value. Another method, of course, would be to ask for a mobilization fee at the beginning of the contract. 219 27 Cost control and EVA Apart from ensuring that their project is com- pleted on time, all managers, whether in the office, workshop, factory or on-site, are con- cerned with cost. There is little consolation in finishing on time, when, from a cost point of view, one wished the job had never started! Cost control has been a vital function of management since the days of the pyramids, but only too frequently is the term confused with mere cost reporting. The cost report is usually part of every manager’s monthly report to his superiors, but an account of the past month’s expenditure is only stating historical facts. What the manager needs is a regular and up-to-date monitoring system which enables him to identify the expendi- ture with specific operations or stages, determine whether the expenditure was cost-effective, plot or calculate the trend, and then take immediate action if the trend is unacceptable. Network analysis forms an excellent base for any cost-control system, since the activities can each be identified and costed, so that the percentage completion of an activity can also give the proportion of expenditure, if that expenditure is time related. The system is ideal, therefore, for construction sites, drawing offices or factories where the basic unit of control is the man hour. [...]... 0% 0% 0% 0% 0% 60 % 100% 0% 60 % 0% 60 % 0% 0% 0% 100% 100% 100% 100% Value hours 5029 0 0 0 0 500 80 164 100 950 5 46 131 148 0 66 77 0 0 0 0 0 0 0 0 0 0 510 70 0 150 0 158 0 0 0 240 110 180 850 Estimate comp 69 77 61 8 0 0 0 0 0 97 0 0 1773 83 520 50 180 53 400 10 0 700 145 203 240 270 60 0 280 0 200 61 500 133 200 200 0 0 0 0 0 Forecast hours 11819 61 8 0 0 0 460 80 242 105 865 2533 208 65 0 50 225 118... 64 .4 3238 2770 85.5 5028 VAL 50 2493 2150 86. 2 49 86 ACT 100 1140 1000 80 810 64 0 80 590 480 70 914 840 85 304 255 80 2 96 320 % 100 1140 1000 50 585 400 60 410 360 40 545 480 70 262 210 80 2 96 320 VAL 800 320 210 360 180 280 ACT % 6 ACT VAL % 9 VAL 1140 1000 1020 800 1045 540 1082 960 335 285 322 360 ACT 91.7 4544 3945 87 4955 100 100 90 80 95 90 % Cost control and EVA efficiency when the value hours diverged... Planning and Control 16 000 14 000 Budget 12 000 11 758 Final Manhours 10 000 8 000 Value Actual 6 000 Historical Projections 4 000 2 000 13,275 14, 468 12,589 11,019 11,548 11, 260 11,141 11,277 560 1 461 2 468 3152 5030 66 28 8513 1 561 2314 3118 4824 62 39 8120 11 12 13 14 15 16 9477 10 10,095 11,095 68 0 6 342 5 385 4 Final 3 Value 2 Act 1 Week No 7 8 9 Figure 27.9 Boiler No 1 Manhour – time curves Once work has... 1.000 100 50 60 40 70 80 23.2 9.3 8.4 11.2 4.9 7.4 64 .4 1,400 60 0 300 850 250 60 0 4,000 Overall % complete = 64 .4% Predicted final hours Efficiency = 222 4000 0 .64 4 4300 × 0 .64 4 4000 = 62 11 × 100 hours = 69 .25% Cost control and EVA Table 27.2 Value hours (Earned Value) system 1 Activity no 2 Activity 3 Budget × 100 4 % Complete 5 Value hours × 100 6 Actual hours × 100 A B C D E F 1000 800 60 0 1200 300... 0 0 850 70 108 125 0 263 0 0 0 240 110 180 850 Budget hours 11758 61 8 0 0 0 500 80 273 100 950 1819 218 741 50 328 140 400 10 0 700 145 203 240 270 60 0 850 70 200 250 500 263 200 200 0 240 110 180 850 Actual hours 4842 0 0 0 0 460 80 145 105 865 760 125 130 0 45 65 0 0 0 0 0 0 0 0 0 0 420 65 0 92 0 200 0 0 0 230 90 155 810 % Complete 43% 0% 0% 0% 0% 100% 100% 60 % 100% 100% 30% 60 % 20% 0% 20% 55% 0%... 67 20 10 10 5 15 20 % 63 93 780 255 250 100 50 50 45 ACT 3 525 200 80 60 60 45 80 VAL 4 310 310 100 195 92 50 ACT 19.4 1057 79 5448 30 15 10 15 25 25 % 835 300 120 60 180 75 100 VAL 5 380 390 188 280 166 185 ACT 450 160 150 240 120 200 VAL 30.7 1589 1320 83.1 51 76 45 20 25 20 40 50 % Months (all hours x 100) 7 8 950 425 250 395 212 261 82.2 4054 3535 87.2 4932 80 40 35 30 60 70 64 .4 3238 2770 85.5 5028... 6 Actual hours × 100 A B C D E F 1000 800 60 0 1200 300 400 4300 100 50 60 40 70 80 1000 400 360 480 210 320 2770 1400 60 0 300 850 250 60 0 4000 1 2 3 4 5 6 Total Overall % complete = Predicted final hours Efficiency = 2770 4000 2770 = 64 .4% 4300 4000 0 .64 4 = 62 11 × 100 hours = 69 .25% Summary of advantages Comparing the weighting and value hour systems, the following advantages of the value hour system... 3 4 5 6 4300 VAL/ACT ACT/% x 100 1000 800 60 0 1200 300 400 Budget hours Figure 27.4 Total Effic Est final Activity Acti No MAN HOURS x 100 VAL 3 16 4.4 60 1000 800 60 0 400 200 2000 3000 4000 5000 60 00 7182 190 120 140 0 0 32 24 10 5 0 0 10 5 7000 100 40 0 0 30 20 ACT % 1 69 49 542 212 140 100 0 50 40 ACT 335 150 40 60 0 45 40 VAL Actual Budget Estimated final 7.8 62 5 5 0 0 15 10 % 2 Value 12.2 67 20... cooler 2 6 Erect duck-stack J 15 16 2 2 2 5 Erect gas duct 2 H 10 Weld duct-stack G 9 Weld duct F 31 Erect gallery ½ 1 Set up boiler C 17 Erect floor 17 18 A N Figure 27 .6 Boiler No 1 Precedence diagram Figure 27.7 Boiler No 1 Bar chart and manhour loadings Figure 27.8 Completion date week 11 Project Planning and Control 16 000 14 000 Budget 12 000 11 758 Final Manhours 10 000 8 000 Value Actual 6 000... / / / / / / / / / / / / / / / / / 10/APR/91 14/APR/91 / / 13/MAR/91 3/APR/91 / / / / / / / / / / / / / / / / / / 6/ APR/91 / / / / / / / / / / 6/ MAR/91 9/MAR/91 23/MAR/91 6/ APR/91 27:5 -3:8 2:8 23:8 0:0 0:0 27:0 0:0 0:0 2:8 29:8 6: 0 51:5 38:2 6: 7 6: 7 6: 7 6: 7 24:2 24:2 20:7 20:7 10:2 6: 0 6: 0 24:2 0:0 20:0 3:2 -3:8 –3:8 3:8 3:8 3:8 0:0 0:0 0:0 0:0 Float remain day day day day (s) (s) (s) (s) slippage . 73 73 220 220 79 7927 27 79 79 27 27 79 7927 27 35 35 36 36 35 35 36 36 71 71 66 66 66 66 44 44 22 22 80 20 60 40 44 44 22 44 66 44 66 80 80 20 20 60 60 40 40 Units in£x100 Sub-contr. 36 40 9 10 32 Figure 26. 5 Total S/C – – – 367 66 0 381 318 438 % 91 9 % 34 19 32 7 8 0 2 2 1 1 0 0 1 Delay 334 33 2 16 74 41 69 15 17 74 70 118 31 17 33 583 343 403 60 448 153 85 143 31 36 153 33 55 26 36 448 303 331 28 368 125 70 118 26 29 125 12 29 368 166 154 (12) 171 58 33 55 12 13 58 13 171 71 (71) 60 0 60 247 84 47 79 17 20 84 85 143 334 15 20 60 907 741 525 (2 16) 347 34 368 159 89 150 33 37 159 41 69 60 0 17 37 34 849 957 8 16 (141) 289 29 284 97 54 91 20 22 97 47 79 347 33 22 29 60 2 65 4 764 110 399 39 36 12 7 11 3 3 12 89 150 289 20 3 39 474 60 2 542 (60 ) S/C OH&P In. S/C – – – 367 66 0 381 318 438 % 91 9 % 34 19 32 7 8 0 2 2 1 1 0 0 1 Delay 334 33 2 16 74 41 69 15 17 74 70 118 31 17 33 583 343 403 60 448 153 85 143 31 36 153 33 55 26 36 448 303 331 28 368 125 70 118 26 29 125 12 29 368 166 154 (12) 171 58 33 55 12 13 58 13 171 71 (71) 60 0 60 247 84 47 79 17 20 84 85 143 334 15 20 60 907 741 525 (2 16) 347 34 368 159 89 150 33 37 159 41 69 60 0 17 37 34 849 957 8 16 (141) 289 29 284 97 54 91 20 22 97 47 79 347 33 22 29 60 2 65 4 764 110 399 39 36 12 7 11 3 3 12 89 150 289 20 3 39 474 60 2 542 (60 ) S/C OH&P In

Ngày đăng: 26/01/2014, 11:20

Từ khóa liên quan

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan