Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống
1
/ 45 trang
THÔNG TIN TÀI LIỆU
Thông tin cơ bản
Định dạng
Số trang
45
Dung lượng
1,66 MB
Nội dung
26
Cash flow forecasting
It has been stated in Chapter 25 that it is very
easy to convert a network into a bar chart,
especially if the durations and week (or day)
numbers have been inserted. Indeed, the graph-
ical method of analysis actually generates the bar
chart as it is developed.
If we now divide this bar chart into a number
of time periods (say, weeks or months) it is
possible to see, by adding up vertically, what
work has to be carried out in any time period. For
example, if the time period is in months, then in
any particular month we can see that one section
is being excavated, another is being concreted
and another is being scaffolded and shuttered,
etc.
From the description we can identify the work
and can then find the appropriate rate (or total
cost) from the bills of quantities. If the total
period of that work takes six weeks and we have
used up four weeks in the time period under
consideration, then approximately two-thirds of
the value of that operation has been performed
and could be certificated.
By this process it is possible to build up a fairly
accurate picture of anticipated expenditure at the
Project Planningand Control
beginning of the job, which in itself might well affect the whole tendering
policy. Provided the job is on programme, the cash flow can be calculated,
but, naturally, due allowance must be made for the different methods and
periods of retentions, billing and reimbursement. The cost of the operation
must therefore be broken down into six main constituents:
Labour;
Plant;
Materials and equipment;
Subcontracts;
Site establishment;
Overheads and profit.
By drawing up a table of the main operations as shown on the network, and
splitting up the cost of these operations (or activities) into the six constituents,
it is possible to calculate the average percentage that each constituent contains
in relation to the value. It is very important, however, to deduct the values of
the subcontracts from any operation and treat these subcontracts separately.
The reason for this is, of course, that a subcontract is self-contained and is
often of a specialized nature. To break up a subcontract into labour, plant,
materials, etc. would not only be very difficult (since this is the prerogative of
the subcontractor) but would also seriously distort the true distribution of the
remainder of the project.
Example of cash flow forecasting
The simplest way to explain the method is to work through the example
described in Figures 26.1 to 26.6. This is a hypothetical construction project
of three identical simple unheated warehouses with a steel framework on
independent foundation blocks, profiled steel roof and side cladding, and a
reinforced-concrete ground slab. It has been assumed that as an area of site has
been cleared, excavation work can start, and the sequences of each warehouse
are identical. The layout is shown in Figure 26.1 and the network for the three
warehouses is shown in Figure 26.2.
Figure 26.3 shows the graphical analysis of the network separated for each
building. The floats can be easily seen by inspection, e.g. there is a two-week
float in the first paint activity (58–59) since there is a gap between the
212
Cash flow forecasting
213
Figure 26.1
Figure 26.2 Construction network
Cash flow forecasting
215
Figure 26.3
following dummy 59–68 and activity 68–69. The speed and ease of this
method soon becomes apparent after a little practice.
The bar chart in Figure 26.5 has been drawn straight from the network
(Figure 26.2) and the costs in £100 units added from Figure 26.4. For
example, in Figure 26.4 the value of foundation excavation for any one
building is £9400 per four-week activity. Since there are two four-week
activities, the total is £18 800. To enable the activity to be costed in the
corresponding measurement period, it is convenient to split this up into
Figure 26.4
0
4
8
12
16
20
24
28
1
2
3
4
5
6
7
8
Site clear
Found exc.
""
""
Found conc.
""
""
Harden
Steel erect
""
""
Re-bay lay
""
""
Slab conc.
""
""
Roof sheet
""
""
Side sheet
""
""
Paint
"
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
"
C
Period
Weeks
62 62
62
47 47 47 47
47 47 47 47
47 47 47 47
71
71
71
71
71
71
220
220
147
147 73
73
220
220
79
7927
27
79
79
27
27
79
7927
27
35
35
36
36
35
35
36
36
71
71
66
66
66
66
44
44
22
22
80
20 60
40
44
44
22
44
66
44
66
80
80
20
20
60
60
40
40
Units in£x100
Sub-contr.
36
40
9
10
32
Figure 26.5
Total S/C
–
–
–
367
660
381
318
438
%
91
9
%
34
19
32
7
8
0
2
2
1
1
0
0
1
Delay
334
33
216
74
41
69
15
17
74
70
118
31
17
33
583
343
403
60
448
153
85
143
31
36
153
33
55
26
36
448
303
331
28
368
125
70
118
26
29
125
12
29
368
166
154
(12)
171
58
33
55
12
13
58
13
171
71
(71)
600
60
247
84
47
79
17
20
84
85
143
334
15
20
60
907
741
525
(216)
347
34
368
159
89
150
33
37
159
41
69
600
17
37
34
849
957
816
(141)
289
29
284
97
54
91
20
22
97
47
79
347
33
22
29
602
654
764
110
399
39
36
12
7
11
3
3
12
89
150
289
20
3
39
474
602
542
(60)
S/C
OH&P
In 90%
Net flow
Direct
Labour
Plant
Material
Site est.
OH&P
Outflow
Labour
Plant
Material
S/C
Site est.
OH&P
S/C OH&P
Total value
Out
0
4
8
12
16
20
24
28
Period
Week
1
2
3
4
5
6
7
8
354
128
322
32
54
91
399
3
32
354
579
427
(152)
116
12
7
11
322
12
116
128
352
319
(33)
116
115
(1)
32
36
40
4
4
9
10
11
Figure 26.6
Cash flow forecasting
two-weekly periods of £4700. Hence in Figure 26.5, foundation excavation
for building A is shown as
47 in period 1
47 + 47 = 94 in period 2
47 in period 3
The summation of all the costs in any period is shown in Figure 26.6.
The table in Figure 26.6 clearly shows the effect of the anticipated delays
in payment of certificates and settlement of contractor’s accounts. For
example, material valued at 118 in period 2 is paid to the contractor after one
month in period 3 (part of the 331, which is 90% of 368, the total value of
period 2), and is paid to the supplier by the contractor in period 4 after the
two-month delay period.
From Figure 26.6 it can be seen that it has been decided to extract overhead
and profit monthly as the job proceeds, but this is a policy that is not followed
by every company. Similarly, the payment delays may differ in practice, but
the principle would be the same.
It will be noted that there is a positive cash flow in only three of the eleven
measurement periods, and suitable finance charges must, therefore, be added
to the contract value. Another method, of course, would be to ask for a
mobilization fee at the beginning of the contract.
219
27
Cost controland EVA
Apart from ensuring that their project is com-
pleted on time, all managers, whether in the
office, workshop, factory or on-site, are con-
cerned with cost. There is little consolation in
finishing on time, when, from a cost point of
view, one wished the job had never started!
Cost control has been a vital function of
management since the days of the pyramids, but
only too frequently is the term confused with mere
cost reporting. The cost report is usually part of
every manager’s monthly report to his superiors,
but an account of the past month’s expenditure is
only stating historical facts. What the manager
needs is a regular and up-to-date monitoring
system which enables him to identify the expendi-
ture with specific operations or stages, determine
whether the expenditure was cost-effective, plot or
calculate the trend, and then take immediate action
if the trend is unacceptable.
Network analysis forms an excellent base for
any cost-control system, since the activities can
each be identified and costed, so that the
percentage completion of an activity can also give
the proportion of expenditure, if that expenditure
is time related. The system is ideal, therefore, for
construction sites, drawing offices or factories
where the basic unit of control is the man hour.
[...]... 0% 0% 0% 0% 0% 60 % 100% 0% 60 % 0% 60 % 0% 0% 0% 100% 100% 100% 100% Value hours 5029 0 0 0 0 500 80 164 100 950 5 46 131 148 0 66 77 0 0 0 0 0 0 0 0 0 0 510 70 0 150 0 158 0 0 0 240 110 180 850 Estimate comp 69 77 61 8 0 0 0 0 0 97 0 0 1773 83 520 50 180 53 400 10 0 700 145 203 240 270 60 0 280 0 200 61 500 133 200 200 0 0 0 0 0 Forecast hours 11819 61 8 0 0 0 460 80 242 105 865 2533 208 65 0 50 225 118... 64 .4 3238 2770 85.5 5028 VAL 50 2493 2150 86. 2 49 86 ACT 100 1140 1000 80 810 64 0 80 590 480 70 914 840 85 304 255 80 2 96 320 % 100 1140 1000 50 585 400 60 410 360 40 545 480 70 262 210 80 2 96 320 VAL 800 320 210 360 180 280 ACT % 6 ACT VAL % 9 VAL 1140 1000 1020 800 1045 540 1082 960 335 285 322 360 ACT 91.7 4544 3945 87 4955 100 100 90 80 95 90 % Cost controland EVA efficiency when the value hours diverged... PlanningandControl 16 000 14 000 Budget 12 000 11 758 Final Manhours 10 000 8 000 Value Actual 6 000 Historical Projections 4 000 2 000 13,275 14, 468 12,589 11,019 11,548 11, 260 11,141 11,277 560 1 461 2 468 3152 5030 66 28 8513 1 561 2314 3118 4824 62 39 8120 11 12 13 14 15 16 9477 10 10,095 11,095 68 0 6 342 5 385 4 Final 3 Value 2 Act 1 Week No 7 8 9 Figure 27.9 Boiler No 1 Manhour – time curves Once work has... 1.000 100 50 60 40 70 80 23.2 9.3 8.4 11.2 4.9 7.4 64 .4 1,400 60 0 300 850 250 60 0 4,000 Overall % complete = 64 .4% Predicted final hours Efficiency = 222 4000 0 .64 4 4300 × 0 .64 4 4000 = 62 11 × 100 hours = 69 .25% Cost controland EVA Table 27.2 Value hours (Earned Value) system 1 Activity no 2 Activity 3 Budget × 100 4 % Complete 5 Value hours × 100 6 Actual hours × 100 A B C D E F 1000 800 60 0 1200 300... 0 0 850 70 108 125 0 263 0 0 0 240 110 180 850 Budget hours 11758 61 8 0 0 0 500 80 273 100 950 1819 218 741 50 328 140 400 10 0 700 145 203 240 270 60 0 850 70 200 250 500 263 200 200 0 240 110 180 850 Actual hours 4842 0 0 0 0 460 80 145 105 865 760 125 130 0 45 65 0 0 0 0 0 0 0 0 0 0 420 65 0 92 0 200 0 0 0 230 90 155 810 % Complete 43% 0% 0% 0% 0% 100% 100% 60 % 100% 100% 30% 60 % 20% 0% 20% 55% 0%... 67 20 10 10 5 15 20 % 63 93 780 255 250 100 50 50 45 ACT 3 525 200 80 60 60 45 80 VAL 4 310 310 100 195 92 50 ACT 19.4 1057 79 5448 30 15 10 15 25 25 % 835 300 120 60 180 75 100 VAL 5 380 390 188 280 166 185 ACT 450 160 150 240 120 200 VAL 30.7 1589 1320 83.1 51 76 45 20 25 20 40 50 % Months (all hours x 100) 7 8 950 425 250 395 212 261 82.2 4054 3535 87.2 4932 80 40 35 30 60 70 64 .4 3238 2770 85.5 5028... 6 Actual hours × 100 A B C D E F 1000 800 60 0 1200 300 400 4300 100 50 60 40 70 80 1000 400 360 480 210 320 2770 1400 60 0 300 850 250 60 0 4000 1 2 3 4 5 6 Total Overall % complete = Predicted final hours Efficiency = 2770 4000 2770 = 64 .4% 4300 4000 0 .64 4 = 62 11 × 100 hours = 69 .25% Summary of advantages Comparing the weighting and value hour systems, the following advantages of the value hour system... 3 4 5 6 4300 VAL/ACT ACT/% x 100 1000 800 60 0 1200 300 400 Budget hours Figure 27.4 Total Effic Est final Activity Acti No MAN HOURS x 100 VAL 3 16 4.4 60 1000 800 60 0 400 200 2000 3000 4000 5000 60 00 7182 190 120 140 0 0 32 24 10 5 0 0 10 5 7000 100 40 0 0 30 20 ACT % 1 69 49 542 212 140 100 0 50 40 ACT 335 150 40 60 0 45 40 VAL Actual Budget Estimated final 7.8 62 5 5 0 0 15 10 % 2 Value 12.2 67 20... cooler 2 6 Erect duck-stack J 15 16 2 2 2 5 Erect gas duct 2 H 10 Weld duct-stack G 9 Weld duct F 31 Erect gallery ½ 1 Set up boiler C 17 Erect floor 17 18 A N Figure 27 .6 Boiler No 1 Precedence diagram Figure 27.7 Boiler No 1 Bar chart and manhour loadings Figure 27.8 Completion date week 11 ProjectPlanningandControl 16 000 14 000 Budget 12 000 11 758 Final Manhours 10 000 8 000 Value Actual 6 000... / / / / / / / / / / / / / / / / / 10/APR/91 14/APR/91 / / 13/MAR/91 3/APR/91 / / / / / / / / / / / / / / / / / / 6/ APR/91 / / / / / / / / / / 6/ MAR/91 9/MAR/91 23/MAR/91 6/ APR/91 27:5 -3:8 2:8 23:8 0:0 0:0 27:0 0:0 0:0 2:8 29:8 6: 0 51:5 38:2 6: 7 6: 7 6: 7 6: 7 24:2 24:2 20:7 20:7 10:2 6: 0 6: 0 24:2 0:0 20:0 3:2 -3:8 –3:8 3:8 3:8 3:8 0:0 0:0 0:0 0:0 Float remain day day day day (s) (s) (s) (s) slippage . 73
73
220
220
79
7927
27
79
79
27
27
79
7927
27
35
35
36
36
35
35
36
36
71
71
66
66
66
66
44
44
22
22
80
20 60
40
44
44
22
44
66
44
66
80
80
20
20
60
60
40
40
Units in£x100
Sub-contr.
36
40
9
10
32
Figure 26. 5
Total S/C
–
–
–
367
66 0
381
318
438
%
91
9
%
34
19
32
7
8
0
2
2
1
1
0
0
1
Delay
334
33
2 16
74
41
69
15
17
74
70
118
31
17
33
583
343
403
60
448
153
85
143
31
36
153
33
55
26
36
448
303
331
28
368
125
70
118
26
29
125
12
29
368
166
154
(12)
171
58
33
55
12
13
58
13
171
71
(71)
60 0
60
247
84
47
79
17
20
84
85
143
334
15
20
60
907
741
525
(2 16)
347
34
368
159
89
150
33
37
159
41
69
60 0
17
37
34
849
957
8 16
(141)
289
29
284
97
54
91
20
22
97
47
79
347
33
22
29
60 2
65 4
764
110
399
39
36
12
7
11
3
3
12
89
150
289
20
3
39
474
60 2
542
(60 )
S/C
OH&P
In. S/C
–
–
–
367
66 0
381
318
438
%
91
9
%
34
19
32
7
8
0
2
2
1
1
0
0
1
Delay
334
33
2 16
74
41
69
15
17
74
70
118
31
17
33
583
343
403
60
448
153
85
143
31
36
153
33
55
26
36
448
303
331
28
368
125
70
118
26
29
125
12
29
368
166
154
(12)
171
58
33
55
12
13
58
13
171
71
(71)
60 0
60
247
84
47
79
17
20
84
85
143
334
15
20
60
907
741
525
(2 16)
347
34
368
159
89
150
33
37
159
41
69
60 0
17
37
34
849
957
8 16
(141)
289
29
284
97
54
91
20
22
97
47
79
347
33
22
29
60 2
65 4
764
110
399
39
36
12
7
11
3
3
12
89
150
289
20
3
39
474
60 2
542
(60 )
S/C
OH&P
In