CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION EXPRESSWAY CONSTRUCTION METHODS (Including construction method for Thruway, Ha Lam IC, Parking Area, Cross Frontage road and Miscellaneous Works) 1/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION TABLE OF CONTENTS A GENERAL CONSTRUCTION PLAN B METHOD STATEMENT DETAIL CHAPTER I: METHOD STATEMENT FOR ROAD I SITE CLEARING, GRUBBING, EXCAVATION TOP SOIL II EXCAVATION III ROCK BLASTING IV EMBANKMENT V CONSTRUCTION SUB - BASE AND BASE COURSE VI CONSTRUCTION ASPHALT CONCRETE PAVEMENT, ASPHALT TREATED BASE COURSE VII PORTLAND CEMENT CONCRETE PAVEMENT VIII BITUMINOUS SURFACE TREATMENT CHAPTER II: CONSTRUCTION METHOD FOR DRAINAGE SYSTEM I DETAIL CONSTRUCTION METHOD FOR PILE CULVERT, BOX CULVERT AND UNDERPASS BOX CULVERT II DETAIL CONSTRUCTION METHOD FOR SIDE DRAINAGE AND SLOPE DRAINAGE III DETAIL CONSTRUCTION METHOD FOR IMPROVEMENT AND RELOCATION OF EXISTING IRRIGATION CHANNELS IV DETAIL CONSTRUCTION METHOD FOR CATCH BASINS, MANHOLES, INLETS, AND OUTLETS CHAPTER III METHOD STATEMENT FOR OTHER ITEMS 2/ 10 I CONSTRUCTION MSE WALL II SODDING AND PLANTING III OTHER MISCELLANEOUS PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION A.GENERAL CONSTRUCTION PLAN I General Requirements Having studying the Bidding Documents issued, prevail regulation on quality control and construction supervision of construction works, our Bidder will propose the proper plan for construction and completion of Work of this Package in compliance with the conditions of contract II Construction organization plan The section from KM32+600 - KM42+000 with 9.4 km in length, The Bidder will arrange temporary road for construction Construction progress will be construction simultaneously over all section of line Construction arrangement For ensuring the construction progress schedule and construction quality required by the Employer and basing on the quantities of works to be completed and site conditions, the construction lines are proposed to arrange as follows: Constructions Line 01: From Km32+600 to Km35+447 Constructions Line 02: From Km35+447 to Km38+000 included parking area Constructions Line 03: From Km38+000 to Km40+300; Constructions Line 04: From Km40+300 to Km42+000 included Ha Lam interchange The Works will be constructed and completed mainly by construction equipment and machinery in combination of use of common labor All construction lines shall be almost developed at the same time over the site upon receiving the commencement order from Employer A The Project Management Board shall be located at the site for overall management and direction of construction and completion of works of construction lines during construction period, that will mobilize construction units from this construction section to other, distribute and arrange properly the construction equipment, machinery, manpower so that they will be used effectively Primary construction method for road Sequences of construction for road construction lines: 3/ 10 Excavation Construction embankment K95 Construction embankment K98 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION Construction of Sub-base, base aggregate course, asphalt treated base Construction cement concrete pavement Construction of asphalt concrete pavement Bituminous Surface Treatment Construction of Completed works Primary construction method for bridge Construction of bored piles Construction of Foundation pit Construction of Abutment Construction of Pier Construction of I beam Installation Construction of Completed works III PLAN FOR CONSTRUCTION EQUIPMENT AND MACHINERY AND MANPOWER MOBILIZATION General This is the most important factor in execution of works, because the quality and construction progress to be depended on this factor The construction equipment and machinery : Bidder shall provide the construction equipment and machinery, testing instrument and measurement instruments in enough number and type with high productivity in good operation conditions, responding the advantaged construction line and technology for construction and completion of works as required by the Employer One workshop shall be arranged by the Bidder for maintaining construction equipment and machinery in good conditions time by time during construction period The Key personnel The key personnel consisting the experience skill management staffs and professional engineers, they have been trained with the professional education and success experience from previous similar construction work, which they have participated in They are able to manage and direct construction and completion of works success The Technicians, Machinery Operators, Driver and Skill Labor etc Bidder shall mobilize the experience Technicians, Machinery Operators, Driver and Skill Labor, they have been trained at the professional training schools and have the professional acknowledge and skill They are able to operate machinery and carry their work effectively The Common Labor Firstly Bidder shall use maximally their available resource, if still not enough, the local labor shall be employed in place 4/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION Arrange manpower and equipment for road 2.1 Excavation For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Number of team: 01 team - The construction equipment and manpower: 5/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION Intended Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpowe r Quantity Excavator 1.6 m3 01 Driver 01 Bulldozer 110CV 01 Driver 01 Dump Truck ≥10 T 05 Driver 05 Compress air 01 Operator 01 Rock hammer 01 Drilling machine 02 Operator 02 Foreman 01 Unskilled Labor 05 2.2 Construction embankment K95, K98 For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Number of team: 04 teams - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity 01 Driver 01 Bulldozer Steel Wheel Roller 10T 01 Driver 01 Vibrating Roller 25T 01 Driver 01 Dump Truck ≥10T 05 Driver 05 Water Truck 01 Driver 01 Tired Roller 16T 01 Driver 01 Water Pump 3.7Kw 02 Operator 02 Foreman 01 Unskilled Labor 05 2.3 Construction sub base, base aggregate course 6/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Number of team: 04 teams - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity Steel Wheel Roller 10T 01 Driver 01 Steel Wheel Roller 6T-8T 01 Driver 01 Tired Roller 16T 01 Driver 01 Vibrating Roller 25T 01 Driver 01 Dump Truck ≥10 T 05 Driver 05 Water Truck 01 Driver 01 Aggregate Spreader 01 Operator 01 Motor Grader 01 Operator 01 Air Compressor 01 Operator 01 10 Foreman 01 11 Unskilled Labor 05 2.4 Construction asphalt pavement, asphalt treated base For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Number of team: 02 teams - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity Steel Wheel Roller 10T 01 Driver 01 Steel Wheel Roller 6T-8T 01 Driver 01 Tired Roller 16T 01 Driver 01 Vibrating Roller 25T 01 Driver 01 7/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION Dump Truck ≥10 T 05 Driver 05 Water Truck 01 Driver 01 Asphalt Spreader 01 Operator 01 Air Compressor 01 Operator 01 Bitumen distribution 01 Operator 01 10 Foreman 01 11 Unskilled Labor 05 2.5 Construction Bituminous Surface Treatment For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Number of team: 01 team - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity Steel Wheel Roller 10T 01 Driver 01 Tired Roller 16T 01 Driver 01 Steel Wheel Roller 6T-8T 01 Driver 01 Dump Truck ≥10 T 03 Driver 03 Water Truck 01 Driver 01 Chip Spreader 01 Operator 01 Bitumen distribution 01 Operator 01 Air Compressor 01 Operator 01 Brooms 01 Operator 01 10 Foreman 01 11 Unskilled Labor 04 2.6 Construction treated base Portland cement concrete pavement or cement For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: 8/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION - Number of team: 01 team - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity ≥10 T 01 Driver 01 200KVA 01 Driver 01 Truck Stand- by generator Portland cement concrete spreader 01 Milling machine 01 Driver 01 Steel well 03 Operator 03 Reedle vibrator 04 Operator 04 Water truck 01 Operator 01 Mixer Concrete mixer 23kw Driver 02 6~10m3 06 06 ≥250L 01 01 01 01 10 Crane 11 Foreman 01 12 Unskilled Labor 05 2.7 MSE retaining wall For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Construction direction: 01 civil engineer - Number of team: 01 team - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity Excavator 1.2 m3 01 Driver 01 Crane ≥10 T 01 Driver 01 Dump Truck 12T 03 Driver 03 9/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV CIVIL WORKS CONTRACT PACKAGE (KM 32+600-KM42+000)- DA NANG – QUANG NGAI SECTION TT Equipment Capacity Quantit y Manpow er Quantity Mixer 350l 01 Driver 01 Steel Wheel Roller 6T-8T 01 Driver 01 Steel Wheel Roller 10T 01 Driver 01 Handle Tamper 60kg Operator 04 Foreman 01 Unskilled Labor 10 2.8 Finish items construction as planting grass, tree For the construction of this item, the Bidder shall arrange Intended Manpower and equipment of team as follows: - Construction direction: 01 civil engineer - Number of team: 04 teams - The construction equipment and manpower: Intended Manpower and equipment of team TT Equipment Capacity Quantit y Manpow er Quantity 0.7 m3 01 Driver 01 Back Excavator Truck Crane ≥10T 02 Driver 02 Dump Truck 12T 02 Driver 02 Mixer 250l 01 Driver 01 Handle Tamper 60kg 10 Operator 10 Foreman Unskilled Labor 01 Arrange manpower and equipment for bridge As shown on bridge section and “Workforce Mobilization Plan” 10/ 10 PHUONG THANH TRANCONSIN – CIENCO6 – CIENCO8 – THANH PHAT JV ... Operator 04 Water truck 01 Operator 01 Mixer Concrete mixer 23kw Driver 02 6 ~10 m3 06 06 ≥250L 01 01 01 01 10 Crane 11 Foreman 01 12 Unskilled Labor 05 2.7 MSE retaining wall For the construction of this... Truck ? ?10 T 05 Driver 05 Water Truck 01 Driver 01 Asphalt Spreader 01 Operator 01 Air Compressor 01 Operator 01 Bitumen distribution 01 Operator 01 10 Foreman 01 11 Unskilled Labor 05 2.5 Construction. .. Wheel Roller 10 T 01 Driver 01 Steel Wheel Roller 6T-8T 01 Driver 01 Tired Roller 16 T 01 Driver 01 Vibrating Roller 25T 01 Driver 01 Dump Truck ? ?10 T 05 Driver 05 Water Truck 01 Driver 01 Aggregate