02 iok a1 TRAFFIC CONTROL

12 3 0
02  iok a1  TRAFFIC CONTROL

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION TRAFFIC CONTROL 1/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION TABLE OF CONTENTS I GENERAL, CONTENTS AND ORGANIZATION CHART II PROPOSED FOR GENERAL TRAFFIC CONTROL III SUBMISSION, APPROVAL AND CHANGE OF TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION IV TRAFFIC CONTROL PLAN (TCP) 2/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION I GENERAL, CONTENTS AND ORGANIZATION CHART General and Contents This General Traffic Control Plan shall be read in order to describe clearer Contractor’s planning of traffic control during construction period and shall be read in conjunction with all the relevant tender documents It shall be revised to allow for modifications based on actual physical site conditions during construction stage This plan is prepared for the treatment of public traffic on existing road that shall be affected by the construction of the project and in order to maintain traffic safety as well as avoiding excessive delay of public traffic on existing road The Contractor shall be responsible for carrying out any necessary investigations and obtaining approvals, licenses, escorts and any other necessary facilities in order to enable extraordinary traffic to be moved on the roads in the Project area Before the application of the measures for traffic maintenance and protection contained in the “General Traffic Control Plan” described below, the Contractor shall investigate and clarify sufficiently the details and regulations established by local authorities and pertinent divisions of the Vietnam Road and Railroad Traffic Police Department The technical requirements specified in the Vietnamese Standards 22-TCN-237-01 “Road Signs and Signaling Regulations” or National Specifications QCKT / 01/2008/ BGTVT shall be applied as the specifications for the work items contained in this Specification Section Traffic control devices and services shall be provided and maintained both inside and outside the project limits as needed to facilitate traffic guidance should this be necessary such as temporary bridges, temporary roads and diversions All traffic temporary control devices and facilities shall be removed upon completion of the Contract Line communication shall be regular updating between all relation subdivision by mobile phone and daily report system Moreover, the intent of site meeting for traffic coordination shall be clarified when necessary All Sub-contractor shall follow Project’s General Traffic Control Plan Inventory of the affected traffic are road section near site work area The detailed inventory of the affected traffic shall be mention in the specific traffic control plan for each section in this project Main contents of General Traffic Control Plan shall include followings: 3/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION 1) Works for Traffic Control 2) Materials for Traffic Control Devices 3) Maintenance of Equipment and Devices for Traffic Control 4) Traffic Control during Non-Working Hours 5) Traffic Control during Nighttime 6) Traffic Control Conserving Existing Traffic 7) Number of Lanes for Traffic Control 8) Vertical Clearance 4/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION Organization Chart The Organization Chart for General Traffic Control Plan will be as follows: Project Manager Vice-Project Manager Head of Safety / Traffic Vice Head of Safety / Traffic Leader of Construction Team SITE ENGINEER SAFETY INSPECTION TEAM SUB-CONTRACTOR (B) Worker Worker Worker 5/ 12 SUB-CONTRACTOR (A) Worker PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION Traffic control works are responsibilities of all relation subdivisions Head of Safety / Traffic who will be main responsible for all traffic control issues in the site Head of Safety / Traffic have experience in traffic management and safety management II PROPOSED FOR GENERAL TRAFFIC CONTROL Work for Traffic Control Prior to the start of construction operations, based on his approved Traffic Control Plan, the Contractor shall furnish, erect and maintain (at prescribed points) warning and guide signs, barricades or barriers, temporary fences (2.0 m height), and other traffic control devices as established in the approved Traffic Control Plan, the Vietnamese Standards, these specifications were directed by the Engineer As necessary for proper control of traffic, or when/where directed by the Engineer, the Contractor will furnish and station competent flagmen whose sole duties will consist of directing the movement of traffic through or around the Works Materials for Traffic Control Devices Retro-reflective Material: Sign panels, barricades, cones, vertical panels, and flagged paddles shall have retro-reflective sheeting meeting the minimum requirements for retro-reflective material noted in Specification “Road Signs” of the Technical Specifications Sign Panels: Sign panels shall conform to Specification “Road Signs” of the Technical Specifications and shall be in orange color with black legend (or white with blue) Sign Posts: Sign posts shall be fabricated from untreated softwood Signs shall be capable of remaining in position during normal traffic flow and wind conditions Barricades: Barricades shall be constructed of wood Cones: Cones shall be in accordance with the Vietnamese Standards for “Roads Sign and Signaling Regulations” (Article 91) with a minimum of 60 cm in height and a broadened base and shall be capable of withstanding impact without damage to the cones or vehicles All cones shall be orange/white colored and highly visible both in daylight and darkness Cones will be capable of remaining bright and in position during normal traffic flow and wind conditions in the area where they are used Lamps for cones shall be suitable for the purpose Temporary Fence: Temporary fence shall be fabricated in panels with timber framework and galvanized metal panels The panel face towards the traffic shall be painted Vertical Panels: Vertical panels shall be constructed of wood Maintenance of Equipment and Devices for General Traffic Control The equipment and devices provided to satisfy the requirements of this Specification Section will be maintained and kept in good condition of operation all the time Any equipment or devices that are lost, stolen, destroyed, or deemed unacceptable while their use is required on the Project, shall be replaced by at 6/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION the Contractor expense Devices for traffic control shall be operated only when necessary Traffic Control during Non-Working Hours During non-working hours and following the completion of a particular construction operation, all warning signs, except those necessary for the safety of the public, shall be removed or entirely covered with either metal or plywood sheeting so that the sign panel will not be visible Traffic Control during Night Time Nighttime operation shall be illuminated by a lighting system approved by the Engineer The lighting system shall be positioned and operated to preclude glare Incandescent lights will not be permitted Retro-reflective sheeting on signs, barricades, and other devices shall be kept clean and in good condition The Contractor shall promptly correct stretches, rips, and tears in the sheeting Retro-reflective sheeting shall have a maintained retroreflection When applicable, street lighting shall be relocated as necessary to maintain the same standards of lighting in the course of the Works until new lighting facilities are put into operation Traffic Control Conserving Existing Traffic When the construction is going to affect an existing road (feeder roads or others) where traffic closing is not permissible, the Contractor shall keep that open to traffic during the execution of the Works, provided that when approved by the Engineer the Contractor may bypass traffic over a detour The Contractor shall at all times keep roads and footpaths, affected by his operations, free from soil and material spillage and properly repaired at his expense if the road is damaged by those operations The Contractor keeps the length of the Project construction areas in such condition that traffic will be accommodated safely Traffic control devices and services shall be provided and maintained both inside and outside the Project limits as needed to facilitate traffic guidance should this be necessary Number of lanes for Traffic Control The existing number of traffic lanes of the roads that may be affected by the Project must be maintained at all times during the work execution and if diversions are provided these must be of the same traffic capacity as the original road The detailed of Temporary road for each section shall be design and submit to the Engineer Vertical Clearance In general any temporary works placed over roads or diversions used by public traffic should have a vertical clearance specified by the Vietnamese Standards TCVN5729-97, TCVN4054-85, 22TCN210-92, TCVN5729-97 and 22TCN210-92, as follows: 7/ 12 Expressways and Highways Class I, II and III at least 4.75 m PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION - Highways Class IV, V and VI at least 4.50 m - Rural Roads Class A at least 3.20 m - Rural Roads Class B at least 2.70 m Where required by the Engineer, the Contractor shall erect and maintain suitable approved check-gates, fitted with warning signs indicating the vertical clearance III SUBMISSION, APPROVAL AND CHANGE OF TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION: All the activities related to the Traffic Control shall comply with approved TCP and Engineer’s instruction on traffic control If the Contractor proposes to change the approved TCP or TS, the Contractor will notify the Consultant in writing at least seven (7) calendar days prior to any proposed change Proposed changes are subject to the Engineer’s approval In case the Engineer makes any subsequent recommendation or instructions on the TCP in writing, the Contractor will revise the TCP accordingly IV TRAFFIC CONTROL PLAN (TCP) Before Construction Before carrying out the construction, the Contractor shall implement procedures to ask for construction permission of Relating Authorities and procedure for handing over Construction site for Construction since date of receiving site plan, the organization, construction individual shall be responsible for managing, ensuring the smooth and safe traffic and orderly implement all measures for ensuring traffic safety during duty implementation period; At latest 28 days from the construction commencement, the Contractor shall submit a plan for traffic control including facilities, measures which are planned by the Contractor for reasonable and orderly traffic control during the time of project implementation During Construction Process During construction stage, the Contractor shall fulfill all agreed options, measures, working schedule; ensure smooth and safe traffic according to regulations and avoid causing damages to existing road constructions, not level, deposit soil, if not for purpose of Construction, within road corridor The Contractor shall regularly check the implementation of regulations for ensuring the safe traffic during construction stage according to the permission and law During construction time, there shall be an outguard for directing traffic, when construction halt, there shall be safe signal following regulations such as: guide sign, flags and red light in the night time The outguard for directing traffic will bear a red band on the left arm and will be equipped with signal flags, whistle, red light in the nighttime Name of Construction unit, construction station, address of the site office, telephone number and name of construction site leader will be note on both ends of Construction road sections The construction leader shall bear a badge The workers working on the road will wear on the job protection clothing according to the regulation 8/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION Construction machines on the road shall be installed sufficiently safe equipments and painted with colors according to the regulation Out of construction time, construction machines shall be gathered in the parking lot In the case of having no parking lot, they shall be parked on the road shoulder where is easily detected and equipped with warning signal For broken down machines, the Contractor shall at any ways bring them to the road shoulders and there shall be signal according to the regulation While construction on the roadbed, road pavement, bridge surface, we will reserve a part of road base, pavement or bridge surface for passing of vehicles, pedestrians, as the following: - Reserve at least one traffic lane if the pavement with less than lanes - Reserve at least lanes if the pavement with more than lanes - In the event that one lane is not wide enough, it may be cause traffic jam, we will first enlarge one side to the level as high as the exiting road and traffic can travel on a part of existing pavement and newly built pavement to support the construction of the remained part - In the case of excavating for enlarging road base, where is cut there shall be immediately backfilled In the case of construction on the soft soil, excavating for lowering the road base, or filing up the pavement higher than m, special measures will be done for ensuring traffic, approved by the Engineer and the Employer Solution when raining will be prepared - In the case of culvert construction without by pass, it is allowed to construct on 1/2 pavement and leave the remained part for traffic If one lane width could not attain, enlarging embankment will be carry out to reach one traffic lane We will erect fencing around excavating hole and firm barricades away from each side 30m Construction materials will be delivered to the Site only sufficiently for construction sections and depositing length does not large than 300m for each of construction section The material will be placed only on one road shoulder side, not parallel deposited on both road sides to make narrowness of road surface Materials disorderly deposited is strictly prohibited to avoid hindering and loosing traffic safety While chopping down trees on road sides, warning signs and guard on both sides will be performed; Do not let trees falling down on road surface to cause traffic jam In the unavoidable situation that trees shall be fell down on road surface, it shall be quickly move down trees to the road sides When chopping trees in any part of road, roots of trees shall be taken away and recover the original conditions Activities to plunge any object from the high to road bed, road pavement is severely banned At the bridge repair positions keeping on traffic, traffic signs will be set up, including: narrow road, speed deceleration, roadwork, etc; establishing guard barrier, appointing traffic controller all day; materials, construction equipments shall be tidily put behind barrier separating the part for construction and the part for traffic; Electric and water supply systems for construction shall be controlled regularly for avoiding any accident In the circumstance that the implementation of both construction and traffic maintenance is unable , the detour shall be built 9/ 12 Completion of Construction PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION After completion of a road section not longer than 1km or a bridge or a culvert, the Contractor shall clear all obstacles for ensuring smooth and safe traffic Before hand-over, the Contractor shall clear all unnecessary materials, displace all machines, remove all obstructions and repair all defects of road caused by construction process Characters of the Construction Alignment The Contract Package passes through dense inhabitant region with high traffic volume, hence, traffic safety on the whole projected line will be specially taken care The Contractor shall tightly observe regulations No 2525/2003/QD BGVT dated 23/3/2003 issued by Ministry of Transport Due to encountering difficulties in traffic maintenance during construction process, the construction instruction shall be tightly and implement in details, have the close combination of units participated in construction to suitably organize by daily or even by hourly so that vehicle may travel on each section and the entire alignment Traffic Safety Assurance Regulations During construction process, the Contractor shall severely comply with required regulations of the Employer and the Engineer about traffic maintenance on the whole projected alignment as well as assurance of labor safety, closely incorporate with pertinent authorities to effectively coordinate the traveling on the entire alignment, detailed as following: - The Contractor shall conform to requirements in the Bidding documents; - Road signs and prohibited signs, etc will be setup in compliance with the Standard in order to guide vehicle moving in the right lane, avoid jamming and blocking traffic; - The Contractor shall consecutively clean up the plan to permit vehicle moving; - Since executing roadbed, the Contractor shall tightly cooperate and discuss with the Engineer and relative units to ensure absolute safety for people and vehicles working on the alignment section as well as inhabitants around working position; - At two ends of the working section, the Contractor shall appoint flagmen to guide, protect people and vehicle passing by Therefore, traffic maintenance to be uninterrupted and safety during construction process will be taken special care right after receiving the construction plan to call vehicles moving on this alignment section for their attention Traffic Maintenance Assurance Solution - Prohibitory signs, informatory signs etc will be placed in conformity with current regulations; - During construction process, flagmen dressing in reflective cloths will be arranged to ensure traffic at two ends of the section being constructed; - 10/ 12 At night, warning lamp will be installed; The existing pavement will be maintained to ensure traffic during construction process, the adjoining side between the new road and the PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION existing road will be laid barricades, etc applied reflective paint and tied reflective papers so that at night vehicles will run safely; For Existing pavement sections The Contractor shall arrange each construction section less than 300 m long to construct on a half of pavement apart The Contractor shall submit plan to Engineer for approval before construction commencement as follows: - Contractor shall arrange a picket line separating construction area and area for public traffic Besides, we will use cone pickets if necessary; - At both sides of construction section, site signs, speed limit signs, sign of narrow road, signal light etc will be set up; arranging qualified flagmen with signal flag for directing traffic; - All machines, equipments, materials for construction, the Contractor shall gather within construction area neatly, reasonably by reasonable and scientific organization After completion of a haft of section (L < 300 m) and the structure reaches load bearing capacity and there is space large enough for traffic, the Contractor shall channelize traffic flow for shifting construction lane and execute the remained side as mentioned above TYPICAL TRAFFIC ORGANIZATION DIAGRAM 11/ 12 PHUONG THANH TRANCONSIN – GRBCC JV CIVIL WORKS CONTRACT PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION 150m SLOW! ROADWORKS AHEAD RIGHT 150m TURNING SECTION UNDER CONSTRUCTION SECTION UNDER CONSTRUCTION Warning light Marker cone 150m SLOW! ROADWORKS AHEAD 150m LEFT TURNING WORKS 300M AHEAD AHEAD 1KM WORKS 12/ 12 PHUONG THANH TRANCONSIN – GRBCC JV ... PACKAGE A1 (KM 65+000-KM81+150)- DA NANG – QUANG NGAI SECTION 1) Works for Traffic Control 2) Materials for Traffic Control Devices 3) Maintenance of Equipment and Devices for Traffic Control 4) Traffic. .. Traffic Control 4) Traffic Control during Non-Working Hours 5) Traffic Control during Nighttime 6) Traffic Control Conserving Existing Traffic 7) Number of Lanes for Traffic Control 8) Vertical Clearance... all traffic control issues in the site Head of Safety / Traffic have experience in traffic management and safety management II PROPOSED FOR GENERAL TRAFFIC CONTROL Work for Traffic Control Prior

Ngày đăng: 03/06/2021, 00:41

Mục lục

    I. GENERAL, CONTENTS AND ORGANIZATION CHART

    I. GENERAL, CONTENTS AND ORGANIZATION CHART

    II. PROPOSED FOR GENERAL TRAFFIC CONTROL

    III. SUBMISSION, APPROVAL AND CHANGE OF TRAFFIC CONTROL PLAN (TCP) FOR EACH STATION:

    IV. TRAFFIC CONTROL PLAN (TCP)

    4. Characters of the Construction Alignment

    5. Traffic Safety Assurance Regulations

    6. Traffic Maintenance Assurance Solution

    For Existing pavement sections

    7. TYPICAL TRAFFIC ORGANIZATION DIAGRAM

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan