Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống
1
/ 38 trang
THÔNG TIN TÀI LIỆU
Thông tin cơ bản
Định dạng
Số trang
38
Dung lượng
121,31 KB
Nội dung
ConceptualIssuesinFinancialRisk Analysis:
A Reviewfor Practitioners
Joseph Tham and Lora Sabin
February, 2001
Lora Sabin is Senior Program Officer at the Center for Business and
Government, John F. Kennedy School of Government, Harvard University, where
she is involved in developing and managing training programs in various
developing countries, including Vietnam and China. From 1998-2000, she was
the Academic Director of the Fulbright Economics Teaching Program (FETP) in
Vietnam, a teaching center funded by the U.S. State Department and managed by
Harvard University.
Joseph Tham is a Project Associate at the Center for Business and
Government, John F. Kennedy School of Government, Harvard University.
Currently, he is teaching at the Fulbright Economics Teaching Program in Ho Chi
Minh City, Vietnam. Before moving to Vietnam, he taught in the Program on
Investment Appraisal and Management at the Harvard Institute for International
Development for many years. He has also served as a consultant on various
development projects, including working with the government of Indonesia on
educational reform in 1995-96.
The authors would like to thank the following individuals for their helpful
feedback: Tran Duyen Dinh, Le Thi Thanh Loan, Brian Quinn, Nguyen Bang
Tam, Cao Hao Thi, Bui Van, Nguyen Ngoc Ho, Graham Glenday and Baher El-
Hifnawi. Responsibility for all remaining errors lies with the authors. Critical
comments and constructive feedback may be addressed to the authors by email at
lora_sabin@ksg.harvard.edu and ThamJx@yahoo.com.
2
Conceptual IssuesinFinancialRisk Analysis:
A Reviewfor Practitioners
Abstract: This paper presents a critical review of the conceptualissues involved
in accounting forfinancialriskin project appraisal. It begins by examining three
of the main approaches to assessing risk: the use of the probability distributions of
project outcomes, such as the NPV, the use of a single risk-adjusted discount rate
for the life of the project, and the use of certainty equivalents. The first two
approaches are very common, while the third is used less often. Next, it proposes
an approach based on annual “certainty equivalents” that is conceptually similar to
using multiple risk-adjusted discount rates and which involves specifying the risk
profile of a project over its lifetime. Finally, this approach is illustrated with a
simple numerical example.
The certainty equivalent approach is compelling because it clearly
separates the time value of money from the issue of risk valuation. While the
authors point out the analytical challenges of the certainty equivalent approach,
they note that its informational requirements are no greater than those posed by
the older, more traditional approaches, while avoiding the numerous inadequacies
of the latter.
JEL codes
D61: Cost-Benefit Analysis D81: Criteria for Decision-Making
Under Risk and Uncertainty
G31: Capital Budgeting H43: Project evaluation
Key words or phrases
Risk Analysis, Monte Carlo Simulation, Cash Flow Valuation, Project
Appraisal.
Available for free download from the Social Science Research Network on
the internet at: papers.SSRN.com
3
INTRODUCTION
It would not be exaggerating to argue that financialrisk analysis is one of
the most important and most difficult components of project appraisal. Such
analysis is especially important because the financial viability of a project may be
critical for its long-term sustainability and survivability. Its particular difficulty is
due to the inherent challenge of pricing risk with market indicators, an exercise
which even in developed countries, where capital markets are mature and function
well, is far from simple. In such countries, capital markets can play an invaluable
role in providing general market-based assessments of risk and bounds to the price
of riskfor given projects. In developing countries, where inadequate and
immature capital markets predominate, lack of reliable market-based information
about the price of risk makes financialrisk analysis a truly daunting undertaking.
1
At the same time, the rapid decline in the cost of computing power has
made it increasingly easy and fashionable to conduct certain types of analysis,
such as Monte Carlo simulation, in the financialrisk analysis of project
evaluations.
2
The popularization of (Monte Carlo) simulation analysis, however,
should be viewed as a mixed blessing. On the one hand, the ability to perform
sophisticated computer simulations is clearly helpful in providing valuable
1
Some project analysts may not appreciate that fact that in many developing countries, especially
transitional economies, the application of risk-pricing models, such as the Capital Asset Pricing
Model (CAPM) and the Arbitrage Pricing Theory (APT) is particularly difficult due to unreliable
or nonexistent data.
2
Fora recent example, see Dailami et al. (1999). Also see, Jayawardena, et al. (1999) and Jenkins
and Lim (1998). For an early discussion of Monte Carlo simulation in the context of project
appraisal, see Savvides (1988). For references to earlier literature, see the citations in Dailami et
al. (1999). At a practical level, in many developing countries, more advanced techniques, such as
contingent claims analysis, would simply be out of the question. In addition, one cannot simply
specify the cash flows as Brownian motion with certain values for the key parameters and solve
the stochastic differential equation with Ito calculus or numerical methods.
4
information about the character of a project and in understanding the effect of
certain variables - contractual arrangements, for example - on important project
outcomes.
3
On the other hand, analysts have increasingly relied upon the use of
computer simulations to carry out financialrisk evaluations without a
corresponding appreciation of the serious limitations of such analysis.
4
In
practical project appraisal, there is a tough balancing act to maintain between
rigorous techniques and user-friendly applied techniques.
Computer simulation analysis is fundamentally limited by the nature of its
final output – typically a probability distribution of the project outcome in
question, such as the financial Net Present Value or Internal Rate of Return - and
the difficulty of its interpretation. Although the probability distribution suggests
to the analyst the likelihood that the project will have an undesirable outcome, the
true relationship between this probability and the inherent risk of the project is far
more complicated. The current danger of the popularity of Monte Carlo
simulation analysis is precisely this temptation to confuse the rather simple use of
an output produced by a powerful and sophisticated computer technique with a
meaningful understanding of project risk.
5
Ironically, the limitations of computer
simulation analysis, and the problems in interpreting the probability distributions
that it yields, are well understood in the theoretical literature. Many practitioners
3
See Glenday (1996).
4
For instance, at the click of a mouse, an analyst selects the probability distributions for the
relevant risk variables. The computer will then conduct a comprehensive Monte Carlo simulation
and produce a mountain of outputs, most typically probability distributions of desired outcomes.
5
For example, as Savvides writes, “Project risk is thus portrayed in the position and shape of the
cumulative probability distribution.” See Savvides (1988), pp. 12-13. For more recent practical
applications inrisk analysis, see Dailami, et al., (1999), p. 5; Jayawardena, et al., (1999), p. 46; and
Jenkins and Lim (1998), p. 57.
5
of project evaluation, however, have failed to recognize the inadequacies of this
type of analysis when it comes to assessing and modeling the level of financial
risk associated with a given project.
6
It is also common practice to make use of a single, risk-adjusted discount
rate when analyzing the long-term financialrisk of a project. In this case, there
would appear to be a misunderstanding of one of the key issuesinrisk analysis,
the specification of risk over a broad time horizon, and its year-by-year resolution,
or the “intertemporal resolution of uncertainty.”
7
Here, the main problem is that it
is impossible to capture two independent dimensions – the time value of money
and the valuation of risk – ina single parameter. Again, this is an issue that has
been raised by theoreticians, but apparently without leading to significant progress
in assessing and modeling long-term riskin practical project appraisal.
8
In view of these trends, this paper seeks to present a critical review of the
conceptual issues involved in accounting forfinancialrisk analysis in project
appraisal. Part One discusses three of the main approaches to accounting for the
potential financialrisk of an investment project: the use of probability
6
Fora critical assessment of economic risk analysis, as contrasted with financialrisk analysis, see
Anderson (1989) and Dixit and Williamson (1989). In this paper, we do not address the equally
important and relevant issue of economic risk analysis and the determination of the economic
opportunity cost of capital. For general textbook discussions of risk analysis, see Brealey and
Myers (1996, Chapter 9), Haley & Schall (1980, Chapter 9), Levy and Sarnat (1994, Chapter 10),
Zerbe & Dively (1994, Chapter 16), Eeckhoudt & Gollier (1995), Benninga and Sarig (1997, p.
11), and Vose (1996).
7
Of course, if there is a known and constant beta for an all-equity claim on cash flow (together
with a known, constant market risk premium and a known, constant Treasure bill rate), then it is
appropriate to use a constant risk-adjusted discount rate. See Myers and Ruback (1987) or Zerbe
and Dively (1994) fora fuller explanation of these conditions.
8
See, for example, Myers and Turnbill (1977) and Bhattacharya (1978). As Dailami, et al. (1999),
p. 5, point out, “Specification of uncertainty through time may affect a project’s cash flow and is
also an important issue in project valuation.”
6
distributions of project outcomes, the use of a single, risk-adjusted discount rate,
and the use of certainty equivalents. As an alternative to the first two approaches,
we argue that the most conceptually appropriate technique begins by specifying
the risk profile of a project over its lifetime.
9
This necessarily involves making
use of multiple, risk-adjusted discount rates, or, correspondingly, the annual
“certainty equivalents” with which they are mathematically linked. In Part Two,
we illustrate our preferred approach in dealing with the “intertemporal resolution
of uncertainty” infinancialrisk analysis ina way that may be understood and
adopted in carrying out project appraisals.
10
PART ONE
In carrying out risk analysis, the question naturally arises, how do we take
into account the annual risk of the project over its entire lifetime? The main
approaches to date of dealing with this issue have made use of the following three
analytical tools: 1) probability distributions of the NPV and/or IRR of a project; 2)
a single risk-adjusted discount rate; and 3) annual certainty equivalents.
11
Each of
these approaches will be examined in more detail below.
To help focus the discussion, let us first specify a simple investment
project, the three-period “Project Risquey” shown in Table 1. At the end of year
0, Project Risquey has a required investment K and will enjoy expected benefits at
9
The idea of certainty equivalents is not new. However, it is not widely used in practice.
10
To a large extent, our analysis is inspired by Myers and Robichek (1966), Chapter 5.
11
We do not explicitly discuss the Capital Asset Pricing Model (CAPM), although this model is
closely related to the main ideas presented in this paper. For example, if the data were available,
the required returns could be estimated with the CAPM.
7
the end of years 1, 2, and 3 of B
1
, B
2
, and B
3
, respectively (there is no salvage
value at the end of year 3).
12
Table 1: Cash Flow Statement of Project Risquey.
(an all-equity project)
Year: 0 1 2 3
Expected Benefits B
1
B
2
B
3
Investment -K
Net Cash Flow -K B
1
B
2
B
3
Discounted NCF -K B
1
*γ B
2
*γ
2
B
3
*γ
3
Annual CF less
Discounted CF B
1
*(1 - γ) B
2
*(1 - γ
2
) B
3
*(1 - γ
3
)
For now we do not consider the impact of financing and assume that
Project Risquey is fully financed with equity (i.e., there is no debt financing).
13
We assume that ρ, the required risk-adjusted return on an investment with all-
equity financing, is 10%.
14
In addition, we assume that there are no taxes and no
foreign exchange risks associated with the project. Letting γ = 1/(1+ρ), the Net
Present Value (NPV) for the equity investor of Project Risquey is as follows:
NPV
PR
@ρ
= -K + B
1
+ B
2
+ B
3
(1 + ρ) (1 + ρ)
2
(1 + ρ)
3
= -K + B
1
*γ + B
2
*γ
2
+ B
3
*γ
3
12
For simplicity, we assume that the expected values of the annual benefits are constant over the
life of the project, even though in reality, the profile of a project’s annual benefits may be
nonlinear.
13
With debt financing, the cash flows to the recipients, namely the debt- and equity-holders, would
be censored and this would complicate the analysis. Furthermore, with debt financing, we would
have to specify the impact of leverage on the value of the levered cash flows.
13
If there was no risk, and the benefits were to occur with certainty, then the required return would
be the risk-free rate.
8
= -K + Σ
t=1
3
B
t
*γ
t
(1)
If, for example, B
t
= $402.11 for 1 ≤ t ≤ 3, and K = $1,000, the project’s NPV
would be equal to zero. Equivalently, its Internal Rate of Return (IRR) would be
10%.
15
How should we think of the factor γ? Basically, it is the adjustment factor
for the time value of money and the cost of risk.
16
Since we have assumed that the
required return on equity is constant for the life of the project, the discounted
benefits decrease year-by-year at the rate of (1-γ). In this case, γ = 90.91%, so
discounted benefits decrease by 9.1% from year to year. Another way to think
about this is to calculate the ratio of the discounted annual benefits in year t+1
with the discounted annual benefits in year t, which yields a result equal to γ.
Thus, ina simple deterministic analysis, the above project would be acceptable
because the NPV at the required risk-adjusted return to unlevered equity is zero
(or equivalently the IRR is equal to the required rate of return).
17
There would be
no need to take into account the variances of the annual benefits.
However, suppose we consider instead a stochastic analysis and specify
constant expected values and variances for the annual benefits.
18
That is,
15
The IRR is obtained by finding the discount rate at which the NPV is zero.
16
Later in the paper, we will show how we can use certain equivalent to separate the compensation
for the time value of money and the risk.
17
We recognize that in the presence of options, the simple NPV rule for capital budgeting and
project selection may be inadequate. See Dixit & Pindyck 91994) and McDonald (1998). In
this paper we will assume that the simple NPV rule is appropriate and will not address these
additional complications.
9
µ
B1
= µ
B2
= µ
B3
= µ
B
(2a)
(σ
B1
2
) = (σ
B2
2
) = (σ
B3
2
) = (σ
B
2
) (2b)
We also assume zero serial correlation between the annual benefits, meaning that
benefits in any year s are independent of benefits in year t, or Cov(B
s
, B
t
) = 0 for
all s and t, s ≠ t. There is no uncertainty about the cost of the initial investment;
the only uncertainty concerns the annual benefits as indicated by the annual
variances (see Table 2).
Table 2: Expected Values and Variances for the Annual Benefits.
Year: 0 1 2 3
Variance (σ
B1
2
) (σ
B2
2
)(σ
B3
2
)
Expected Benefits E(B
1
)E(B
2
)E(B
3
)
For simplicity, we assume that the annual variances are constant over the
life of the project, although, in reality, it is more likely that they would vary.
19
We
may also specify that the probability distributions for the annual benefits are
normal (Gaussian), though this assumption is not a necessary one. Ina more
complex cash flow statement with many different line items, it may be a practical
impossibility to specify the functional form of the annual cash flow since it will be
dependent on many line items in the cash flow statement.
18
We assume that these expected values were obtained from a Monte Carlo simulation conducted
with sufficient runs to obtain estimates within the desired level of accuracy.
19
In other words, we are assuming that the stochastic process for the benefits is stationary in the
mean, variance, and covariance.
10
(1) Probability distribution of Project NPVs and IRRs
This approach involves producing and analyzing probability distributions
of a desired project outcome, typically the NPV or the IRR. These distributions
are obtained by running computer simulations of possible future cash flows, based
on specifications of the probability distributions of the risk variables previously
identified as having an impact on the project’s cash flow, and then discounting the
resulting cash flows by the risk-free discount rate.
20
The final step requires the
analyst to examine the probability distributions and, most typically, to determine
the likelihood that a particular project outcome will be a certain value, for
example, the probability that the NPV will be negative.
21
The use of these probability distributions inrisk analysis is appealing
because they appear to be easy to explain and interpret, while containing a lot of
information. After all, what could be more useful than a range of possible project
outcomes? On closer examination, however, this apparent attractiveness is
misleading. First and foremost is the difficulty of interpreting the “probability
distribution” of the NPV. In short, what does such a probability distribution really
mean?
22
With capital markets, we would expect a single risk-adjusted price for
20
A particularly difficult issue that we will ignore is the determination of the appropriate
intermporal probability distributions for the key risk parameters that have been identified through
sensitivity or scenario analyses, especially in the presence of sparse or no historical data.
21
In the case of our simple Project Risquey, we would not need to carry out simulation analysis to
determine the expected value and the variance of the NPV. In this case, the Expected NPV
Proj
or
µ
NPV
Proj
= - E(K) + Σ
t=1
3
E(B
t
)*γ
t
and the Variance NPV
@ρ
Proj
= [σ
NPV
Proj
]
2
= Σ
t=1
3
Var(B
t
)*[γ
t
]
2
=
{Σ
t=1
3
[γ
t
]
2
}*(σ
B
2
). If we were to specify particular probability distributions for the annual benefits,
however, then simulation analysis would help us determine the probability that the project’s NPV
would be negative, just as with more complex projects.
22
Using rather harsh language, Brealey & Myers (1996), p. 255, suggest: “The only interpretation
we can put on these bastard NPVs is the following. Suppose all uncertainty about the project’s
ultimate cash flows were resolved the day after the project was undertaken. On that day the
[...]... the case that α32 must be equal to α31 The adjustment factor α31 is based on the information available at the end of year 1, while the adjustment factor α32 takes into account any relevant new information available at the end of year 2 Similarly, α21 and α31 may not be equal to α20 and α30, respectively, after the passage of the first year of the project Thus in each year, any available information about... Table 3 shows the present values of the annual cash flows discounted at both the unadjusted rate of 10% and the risk- adjusted rate of 15% As can be seen in Line 2, the former values are declining at a constant annual rate of 9.1% In year 1, the adjustment as a percentage of the annual benefits is 9.09% (see line 4); in year 2, the percentage rises to 17.4%; and in year 3, it is 24.9% In contrast, as... below in Table 6, however, the annual adjustment factors will now vary, indicating an increasing adjustment forrisk over time This once again illustrates the difference between a constant adjustment forrisk and a constant risk- adjusted discount rate Table 6: Certainty Equivalents using Varying Adjustment Factors Year: Expected Benefits Certainty Equivalent Adjustment Factor Discounted NCF NPV IRR 0 -1,000.00... certainty equivalent method makes separate adjustments forrisk and time The relevant question one asks using this technique is, “what is the smallest payoff for which the investor would exchange the risky cash flow?” Since that amount is the value equivalent of a safe cash flow, it may be safely discounted at the risk- free rate This approach is clearly closely linked conceptually and mathematically... By making use of certainty equivalent adjustment factors, or their corresponding multiple risk- adjusted discount rates, we are nudged away from the earlier easier techniques that rely on a single summary measure, such as the probability distribution of the NPV or a single risk- adjusted discount rate Rather than staring at the probability distributions of NPVs fora project, and waiting in vain for inspiration... shown in Line 5 of Table 3, the risk- adjusted discounted benefits are declining at an annual rate of 13.0% In absolute terms, the adjustment in year 1 as a percentage of the annual benefits is 13.0% (see line 7); in year 2, the percentage increases to 24.4%; and in year 3, it is 34.2% Thus the constant risk- adjusted discount rate does not imply a constant deduction forrisk Rather, it implies a larger... annual compensation forrisk is constant in each year, due to our initial assumption that the adjustment factors for calculating the certainty equivalents remain unchanged over the life of the project Thus in each year, the compensation forrisk is equal to the difference between the unadjusted and adjusted annual benefit, or (1- α)*Bt = (10%)*446.79 = 44.68 (3) Revisions in the annual valuations For. .. each of the first two years of the project, there is a gradual resolution in the uncertainty of the values of future benefits and a belief that future risk has declined Accordingly, the adjustment factors are increased from 90% to 93% at the end of year 1 and again to 95% at the end of year 2.30 The results of this analysis are summarized below in Table 10 Appendix B contains more detailed calculations... the case of a single risk- adjusted discount rate, the adjustment forrisk is conveniently and implicitly embodied ina single measure that also includes compensation for the time value of money In the absence of common marketbased data and measures of the price of risk, there are no truly reliable assessments forrisk and any analysis will be largely based on the best “educated guesses” of experts in. .. Substituting line 15b into 1 5a, we obtain that: 1 = (1 + ρt+1) and: ρt+1 = αt αt+1 αt +1_ αj -1 (1 6a) (16b) In words, the risk- adjusted discount rate in year t+1 is equal to the ratio of the certainty equivalent in year t to the certainty equivalent in year t+1, minus one 21 PART TWO In view of the discussion in Part One, the question naturally arises: how should we handle the valuation of risk in practical . ThamJx@yahoo.com.
2
Conceptual Issues in Financial Risk Analysis:
A Review for Practitioners
Abstract: This paper presents a critical review of the conceptual issues involved
in accounting. Conceptual Issues in Financial Risk Analysis:
A Review for Practitioners
Joseph Tham and Lora Sabin
February, 2001
Lora Sabin is Senior Program Officer