Visio 20210911 ELEVATION CONSTRUCTION SEQUENCE CHART Rev 00 vsdx PROJECT COMMERCIAL PROJECT OF SAI GON – BASON COMPLEX ELEVATION CONSTRUCTION SEQUENCE CHART STRUCTURE WORK (F10) WP 105 12 days STRUCTURE WORK (F13) WP 105 7 days STRUCTURE WORK (F14) WP 105 6 days STRUCTURE WORK (F6 F8) WP 105 36 days STRUCTURE WORK (F11) WP 105 24 days STRUCTURE WORK (F12) WP 105 7 days BMU WP 105 B 45 days STRUCTURE WORK (F1 F5) WP 105 244 days JUMP FORM (F4 F7) WP 105 5 days MEP (F4) WP 106 151 days (F5) FS STR.