Cellular composite beams with composite slab

Một phần của tài liệu Steel Building Design Medium rise braced frames (Trang 51 - 55)

Description Cellular beams are beams with openings at short regular intervals along their length. The beams are either fabricated from 3 plates or made from rolled sections. Openings, or ‘cells’, are normally circular, which are ideally suited to circular ducts, but can be elongated, rectangular or hexagonal. Cells may have to be filled in to create a solid web at positions of high shear, such as at supports or either side of point loads along the beam. The size and spacing of the openings can be restricted by the fabrication method, as well as by the required strength of the beams.

The main two companies specialising in design and supplying these beams are:

Westok Ltd, supply cut and re-welded rolled sections, which can be of different weights or serial size, and can incorporate a camber when re-welded.

These cellular beams generally have circular openings at regular centres.

Fabsec Limited, supply beams fabricated from three plates with openings cut in the web. These beams can have a wide range of opening types and spacings, and can be supplied with a camber.

Cellular beams can be arranged as long-span secondary beams, supporting the floor slab directly, or as long-span primary beams which are aligned parallel to the span of the slab supporting other cellular beams or conventional rolled section secondary beams.

Typical beam

span range 10 – 18 m

Figure 5.6 Long-span secondary cellular beams with regular circular openings

6.0 m7.5 m

6.0 m

130

2 No. 19ỉ x 100lg studs @ 300ctrs

3.0 m 3.0 m

660

450

Decking

1.0 thk A193 mesh

20 No. holes @ 650ctrs.575

650

PART PLAN Side bracing

Wall bracing

203 UC 46 (3

&4) 203 UC46 (3&4)

203 UC 46 (1&

2)

S275 203x133 UB25

S275 203x133 UB25

S275

Stairs

Side bracing

A A

Slab

203 UC 46 (3

&4) 254 UC7

3 (1&

2)

457 x 152 UB52 S275

203 UC60 (1&2) 203 UC46 (3&4) 356 x 171 UB51

S275

Slab

254 x 146 UB31 S275 254 x 146 UB31 S275

457 x 152 UB52 S275 254 UC73 (1&2)

B

B

254 UC73 (1&2) 203 UC52 (3&4) 203 UC46 (1&2)

203 UC46 (3&4)

254 UC 73 (1&

2)

203 UC52 (3&4) S355

S355 S355

203 UC 60 (1

&2)

203 UC46 (3&4) S355

S355

S355

S355

SECTION A-A

457 x 191 UB67 S275 406 x 178 UB60 S275

254 x 146 UB31 S275

356 x 127 UB33 S275 356 x 171 UB45 S275

457 x 191 UB74 S275 + 457 x 191 UB82 S275 Cellular beam

406 x 178 UB60 S275

= 150 mm raised floor + 130 mm slab + 660 mm beam

+ 150 mm ceiling & lighting Lift

Overall floor zone

=1090 mm 1100 mm

Figure 5.7 Cellular beams (long-span secondary beams) and composite slabs – example of floor steelwork arrangement for a 4 storey rectangular plan building

Main design considerations for the floor layout

Secondary beams should be spaced close enough to avoid propping the decking during construction. (3 – 4 m).

Large (elongated or rectangular) openings should be located in areas of low shear, e.g. in the middle third of span for uniformly loaded beams.

Consider integration of the services within the beam depth to minimise the overall floor zone.

Advantages Long, column-free floor spans.

Relatively lightweight beams compared with other long-span systems.

Economic long-span solution.

Precamber can be accommodated during the fabrication of the members.

Disadvantages Increased fabrication costs compared with plain sections.

Services

integration Regular openings in the web allow ducts to pass through the beams. Larger items of equipment are located between the beams. Openings need to allow for any insulation around the services. Ensure web openings align through beams.

Governing design criteria for beams

Critical check may be elements within the beam – for example, the web posts between openings, particularly near high point loads or adjacent to elongated openings.

The dynamic response of the floor may be critical in some circumstances.

Opening size is ideally within 80% of the finished beam depth, and with a maximum opening length/depth ratio of 2.5. Stiffeners may be required for large openings.

Governing design criteria for decking/slab

Strength or deflection of the decking in the construction condition.

Fire resistance (affects the concrete cover to the decking and mesh reinforcement size).

Strength or deflection of the slab in the composite condition.

Design approach 1. Assume long-span secondary beams at 3 – 4 m spacing, supported by primary beams on a 6 m, 7.5 m or 9 m column grid

2. Choose the decking and slab, using decking manufacturer’s design tables or software. Use lightweight concrete unless there is a directly-bonded floor covering. Assume LC35/38 concrete, and unpropped decking during construction. Ensure the chosen slab and reinforcement meet the fire resistance required.

3. Design the beams using manufacturer’s software. If stud spacing is not automatic within the software, try shear studs at approximately 300 mm spacing on secondary beams (to suit trough spacing), and at 150 mm spacing on primary beams (The development of moment resistance will often be more severe on a primary beam, demanding closer spacing of studs.) Note that the orientation of the decking will differ between secondary and primary beams. As the services are likely to be integrated, ensure cell sizes and positions are agreed with the services engineer.

Typical section

sizes 700 mm deep steelwork for 15 m span at 3.75 m centres.

(Beam + slab depth)  span/16-19.

Grade of steel S275 and S355.

Lighting Ceiling

Raised floor 150

140

100 50 Ducting + insulation

400 dia.

 760

1200

Figure 5.8 Cellular beam - Typical cross section Type of

concrete Either normal concrete, 2400 kg/m3, or lightweight aggregate concrete (LWAC), typically density class D1,8 to BS EN 206-1 (1600-1800 kg/m3) can be used.

Normal concrete has better sound reduction, so is better for residential buildings, hospitals, etc.

LWAC is better for overall building weight/foundation design, better span capability of slab, and has better fire insulating properties, enabling slightly thinner slabs (10 mm less) to be used. It is not available in all parts of the UK. LWAC is not considered suitable for directly-bonded floor coverings.

Overall floor zone 1200 mm for 15 m span with 400 mm opening.

Fire protection Intumescent paint, often off-site. Consult fire protection manufacturer; References 23 and 24 give background information on fire protection of beams with web openings.

Connections End plate, in shear only.

Design guidance For choice of decking and composite slab design (including fire resistance);

manufacturer’s design tables.

For best practice advice in design and construction, refer to P300[17]

For design charts and worked example for decking and beams, refer to P055[18]

For the basic design of orthodox cellular beams, refer to P100[25]

Software Cellbeam software from www.westok.steel-sci.org Fabsec software from www.fabsec.co.uk

Figure 5.9 Fabricated beam with off-site fire protection

Một phần của tài liệu Steel Building Design Medium rise braced frames (Trang 51 - 55)

Tải bản đầy đủ (PDF)

(127 trang)