Resettlement Monitoring Report Quarterly Report October–December 2013 VIE: Mong Duong Thermal Power Plant Prepared by Viet Nam Electricity (EVN) GENCO Thermal Power Projects Management Board EVN GENCO Thermal Power Projects Management Board (TPMB1) MONG DUONG (2 x 500MW) THERMAL POWER PLANT PROJECT INTERNAL RESETLEMENT MONITORING QUARTERLY REPORT Period 1st January to 31st March 2014 Contract No: TPMB1-EVN/ADB-2610L2MFF-Consulting-002 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Table of Contents ABBREVIATIONS GENERAL INFORMATION OF THE PROJECT 1.1 Mong duong Thermal Power Plant Project 1.2 The Fresh Water Component 1.3 The Scope of Land Acquisition and Resettlement DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS 2.1 Information Disclosure and Community Participation 2.2 Detailed Measurement Survey 2.3 Compensation payment, assistance and resettlement 2.4 Process of resettlement and site clearance 2.5 Restoration of APs’ livelihoods and rehabilitation of APs’ lives 10 2.6 Assess degree of APs’ satisfaction of compensation and resettlement 10 2.7 Conformity of resettlement implementation progress with civil works progress and next plan 10 2.8 Issues concerning gender and ethnic minority 11 PENDING ISSUES 11 3.1 Outstanding problems 11 3.2 Solutions for pending issues and responsibility of relevant agencies 11 CONCLUSIONS AND RECOMMENDATIONS 11 4.1 Conclusions 11 4.2 Recommendations 12 APPENDIX 14 Appendix1 List of the affected Households 14 Appendix Situation of Compensation Payment 22 TABLE Table 1: Affected Land Area Categorized by Communes til 31/3/2014 Table Number of HHs and Persons whose land affected in each Commune til 31/3/2014 Table Summary of consultations undertaken Table Status of affected household until 31 March, 2014 Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project ABBREVIATIONS DCARB District compensation, Assistance, and Resettlement Board DMS Detailed Measurement Survey EVN Electricity of Viet Nam FWC Freshwater Component LFDC Land Fund Development Center PAP Project Affected Person PMU Project Management Unit PPC Provincial People's Committee RAP Resettlement Action Plan TPP Thermal Power Plant TPMB1 Thermal Power Plant Project Management Unit No TRC Town Resettlement Committee PC People’s Committee RC Resettlement Committee Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project GENERAL INFORMATION OF THE PROJECT 1.1 Mong duong Thermal Power Plant Project Mong Duong Thermal Power Plant complex with a total combined capacity of 2’200 MW, is located in the Mong Duong Ward (Cam Pha town, Quang Ninh province) It is situated along Highway 18, 300 km northeast of Hanoi and 18 km from the Center of Cam Pha town The Project site is located at the mouth of the Mong Duong River and includes one ward (Mong Duong) and one commune (Cam Hai) The objective of building this Plant is to increase the capacity of the thermal electric power source and contribute to the stable supply of electricity throughout the year and especially in the dry season when the hydro plants not generate much of their maximum capacity 1.2 The Fresh Water Component The Mong Duong Thermal Generation Plant complex needs a large amount of fresh water from Quarter Four, 2013 It is calculated that, the combined Plant needs 15.000 m3 of fresh water per day A fresh water supply system therefore must be constructed to serve the project The system consists of the reservoir, the pumping station, the 10 KV power supply to serve for the pumping station, the water pipe line, and the access road Of which, only the Reservoir area and the Water Pineline area relates to land acquisition and resettlement 1.3 The Scope of Land Acquisition and Resettlement Based on the detailed design, a total area of 1,849,411.39m2 with 192 households will be permanently affected Among the permanently affected land, 1,366,399.76m2 is affected by the reservoir in Mong Duong Ward and 483,011.63m2 by the pipe-line and other works (access road, powerhouse, etc) in Cong Hoa Commune and Cam Hai Commune (Cam Pha City) 34% of affected area is productive forest land which is currently used for planting Acacia of 71 households (385 persons) in three communes/wards FWC will also affect 8000.0m2 of residential land of 37 households (182 persons) in Village 10, Mong Duong Ward Cong Hoa and Cam Hai communes will not have residential land affected by the FWCt Area, number of households and persons of affected land are shown detailed in Table and Table Beside, 17,756.5m2 temporary land is also acquired for the Project during construction phase and the compensation was paid for the temporarily affected households In the pipeline, DMS also conducted in August to analyze the road widening According to the original design, pipeline will crossed over on road number 18, thus, the change in in alignment should be done due to the wider road Because of this change, more households will be affected by this project The categories of permanently affected lands are as below: Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Table 1: Affected Land Area Categorized by Communes til 31/3/2014 Reservoir Categories of affected land No Pipe line Mong Duong Ward (m ) Cong Hoa Commune (m ) Cam Hai Commune (m ) Total (m ) Sub-total (m ) Residential land 8,000.0 - - - 8,000.0 Agricultural land 225,309.5 - - - 225,309.5 Forest land 305,863.50 195,251.53 129,451.60 324,703.13 630,566.63 Aquaculture area 13,872.65 269.00 12,687.80 12,956.80 26,829.45 Public land 813,354.16 98,304.20 47,047.50 145,351.70 958,705.86 1,366,399.76 293,824.73 189,186.90 483,011.63 1,849,411.39 Total st (Source: TPMB1, Updated in March 31 , 2014) Table Number of HHs and Persons whose land affected in each Commune til 31/3/2014 Cong Hoa Commune Mong Duong Ward No Categories of affected land Cam Hai Commune Total No of AHs (HH) No of APs (person) No of AHs (HH) No of APs (person) No of AHs (HH) No of APs (person) No of AHs (HH) No of APs (person) Residential land 37 182 0 0 37 182 Agricultural land 127 508 42 168 23 95 192 768 Forest land (for acacia planting) 19 88 35 148 17 69 71 305 Aquaculture land 41 4 49 (Source: TPMB1, Updated in March 31st, 2014) DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS Detailed on the progress of Resettlement Plan Implementation is in the Appendix 2.1 2.1 Information Disclosure and Community Participation Information dissemination was conducted by Thermal Power Project Management Unit No.1 (TPMB1) and DCARB of Cam Pha city Orientation meetings have been conducted since 2009 with relevant parties and affected households Project information has been delivered to 100% affected households (such as introduction of detailed technical design, scope of impacts on land and asset upon on lands, entitlements for compensation, assistance and resettlement, implementation schedule of land acquisition, compensation, assistance and resettlement and grievance redress mechanism) The documents have also been placed in public places and in the house of village leaders and head of mass-organization Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project 11 consultations were conducted by the local authorities from January 1st to March 31st, 2014 and gathered representative of following groups: Project information disclosure activity was continuously and regularly implemented through the implementation progress This kind of activity is to enhance local awareness, reduce grievance or complaints from AHs as well as speed up the implementation of the project’s components The information disclosure was mainly carried out through: residential meetings, delivery of notices to each household, posting up notice at local government’s offices, delivery of project leaflets and posters, direct meetings with AHs by TPMB1’s, and local authorities During the project implementation, the information disclosure activity was implemented mainly in the affected areas to local people and the ones who have complaints, grievance The disclosed information included; (i) information about the compensation policy and the right of AHs; (ii) information about environmental impacts; (iii) issues arising from the construction execution affecting local people Besides, local people were also informed of project compensation implementation arrangements, responsibilities of relevant stakeholders and grievance redressal mechanism and results of grievance redressal as well as newly arising issues during the project implementation The results of the consultation show that dissemination of information to local authorities, agencies and organizations, especially local communities where the project has achieved certain results The public consultation has mobilized the full participation of stakeholders, information about projects, policies and projects that benefit from the project really helped raise awareness for community and contributing to the progress of clearance and construction projects The consultation and information dissemination is done in all communes and wards to implement the Project TPMB1 was in collaboration with the local government has organized a series of meetings, direct dialogue with those remaining claims, the displaced households The Advocacy, Dissemination and Implementation have been carried out the support policies of Cam Pha City Comittee to speed up the site clearance activities of projects thoroughly The Project has made sure to get the information to the PAPs fully and as fast as possible The Consultation and Information Dissemination has been implemented in accordance with the provisions of ADB, from the municipal level, communes, villages and received basic consensus of the community on the issues : land and resource products affected are compensated The project has the support appropriate policies for each object affected under the provisions of the Government of Vietnam, The Matrix Rights under the provisions of the projects using ODA Fund And especially those supporting policy priorities of provinces and cities dedicated to the project Both men and women from affected households are encouraged to attend, as well as other interested community members The list of public meetings for the Fresh Water Component is provided in the following Table Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Table Summary of consultations undertaken Ward/commune Mông Dương ward Time 14/1/2014 Contents Meeting at City PC to solve complaints of people related to site clearance Participants City PC, LFDC, Ward PC, Resident Area, TPMB1, affected households Comments from participants The affected household was satisfy with compensation policy 21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, head of Resident Area, TPMB1, affected households The affected household was satisfy with compensation policy 28/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money ; Cam Pha LFDC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 14/3/2014 To mobile people to receive compensation money and hand over their land and assets for the Investor To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy Cam Pha LFDC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 14/1/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 28/3/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 14/1/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 28/3/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households The affected household agreed with compensation policy 28/3/2014 Cộng Hoà commune Cẩm Hải commune Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Participants of public meetings include all affected households, local authorities, head of massorganizations and village leaders The total turns of participants are around 905 people, of whom 407 people are female (accounting for 45%) Consultations continue to be deployed in the project area through community meetings 100% of affected households were consulted times or more on the project’ policy of land acquisition, compensation, support, and resettlement Affected people have been consulted on the needs of participating in the income restoration program, however, many households are still not aware of the importance of the program, therefore, they are not ready to participate in the program Propaganda, information disseminating to these households will be continuously performed during the implementation of the income restoration program The consultation process has also paid its attention to the needs of women and vulnerable groups such as the poor, single women headed household, elderly or some other policy objects Due to the Consultants providing information adequately and transparently on compensation entitlements the complaints of affected people are not considerable in numbers 2.2 Detailed Measurement Survey Detailed Measurement Survey was completed before November 10th, 2012 However some added surveys are still continuing due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use left As of March 31st, 2014, the discrepancies and omissions in the loss inventory process or other damages arising due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use caused by land acquisition was timely inventory replenishment to ensure the entitlements of the affected people, ensuring compliance RP framework of the project Need assessment survey was conducted in July 2013 to design and implement the measures for income and livelihood restoration Participants chose the vocational training, Acacia’s Cultivating and the breeding’s model The Income Restoration Program has prepared since December and TPMB1 has sent unofficial updated IRP to ADB for comments before official submission, and ADB sent comments on 27th of January 2014, TPMB1 will responses to ADB comment and send official to ADB in early of April 2014 In the pipeline, DMS also conducted in August to analyze the road widening According to the original design, pipeline will crossed over on road number 18, thus, the change in alignment should be done due to the wider road Because of this change, more households will be affected by this project It is necessary to assess the impact of these households in next quarterly report 2.3 Compensation payment, assistance and resettlement As of March 31st, 2013, the total budget of approved compensation, assistance and resettlement is VND 97,405,207,100and VND 96,789,219,900 has been paid for the affected people (including budget for the DCARB), reached 98.8% The Progress of Site Clearance of the project was concerned properly, however, due to the unexpected issues happened during the implementation, the schedule of clearance process is carried out slowly in compare with The Resettlement Plan and Resettlement Plan proposed Compensation payment has implemented for the Pipeline component Total of unpaid budget is VND 615,987,200, this will be paid for the Reservoir and Pipeline Component before April 30th, Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project 2014 This unpaid amount belongs to Resevoir Component Pipeline Component was completed compensation payment In general, The Application Cost for the project was in compliance with the provisions of ADB about the Compensation and Assistance will be based on the principle of replacement cost (market value in normal conditions) at the time of The Compensation Implementation The TPMB1 has many solutions to make sure that all the displaced Households in the project without having any certificate of Land Use rights or any legal recognition of the acquired land are eligible to receive compensation and resettlement assistance, non-land assets to support the replacement cost of ABD and policies of Vietnam's Law Although the compensation paid almost finished, there are some household still complaint on misjudging of their assets The compensation team of TPMB1 is calculated to add the inventory for those households for next few months There are total 37 resettled households, concentrated in Reservoir Component and all of them agreed to resettle freely 12/37 of households returned their fatherland in another province such as Hai Phong, Lang Son, Bac Giang They are immigrant households those moved to this area during 15 -25 years ago 25 other households still stay inside the commune but move near to 329 road, and they buy a new land with basic infrastructure for a household and all of them completed construction their resettled houses These households have already connected to the electricity distribution system because the 35kv electric line completed and put into use in September, 2013 and they also have accessed to potable water supply because they buy their own pumpling machine to collect the water from streams Table Status of affected household until 31 March, 2014 No Affected Household situation HHs Remarks House Build a new house 25 House is under construction HHs has not build new house Sell the house and move to other place 12 hhs to Hai Phong, hhs to Lang son, and hhs move to other village in Quang ninh province (8 HHs are under construction and HHs have not built yet) Land Buy a new agriculture land 15 Buy a new resident land 25 Not buy any kind of land 12 They have their own land or they are too old Staying/Moving Move to other place 12 Staying in Mong Duong ward 25 2.4 Process of resettlement and site clearance As of March 31st, 2014, the land acquisition and resettlement has achieved good results in general for the Pipeline Component (Cong Hoà and Cam Hai communes) Site clearance rate for Page of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project APPENDIX Appendix1 List of the affected Households Cộng Hòa commune Family member No Name of household head Male Female Job situation of the hhs members Ethnic Under 18 years old Above 18 years old Under 18 years old Primary Income Secondary Income Above 18 years old Employment Worker Forestry planting Unemployment Bàng Phương Hùng Kinh 2 Bế Văn Mít Tày 1 1 Forestry planting Trader Bế Văn Viện Tày 1 2 Farmer Forestry planting Bùi Hữu Đài Kinh 1 Farmer Forestry planting Bùi Hữu Luân Kinh Farmer Forestry planting Bùi Đức Chinh Kinh 1 Trader Forestry planting Đào Xuân Tuy Kinh Trader Forestry planting Đỗ Thành Minh Kinh 1 Worker Trader Đỗ Thị Bảy Kinh Farmer Worker 10 Hà Thị Thuỷ Tày 1 Farmer Forestry planting 11 Hà Văn Chung Kinh 1 Farmer Forestry planting 12 Hà Văn Lường Tày 1 Forestry planting 13 Hà Văn Lưu Kinh 14 Hà Văn Mùi Kinh 15 Hà Văn Năm 16 1 1 Forestry planting 1 Trader Forestry planting Kinh 1 Farmer Forestry Planting Hà Văn Tần Kinh Farmer Forestry Planting 17 Hà Văn Thuỵ Kinh Farmer Forestry Planting 18 Hoàng Minh Thắng Kinh 1 Soldier Trader 19 Hoàng Thị Minh Tày Forestry planting Forestry Planting 20 Hoàng Văn Toàn Tày Farmer Forestry Planting 21 Lại Văn Tòng Kinh Worker Forestry Planting 1 Page 14 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Family member No Name of household head Male Female Job situation of the hhs members Ethnic Primary Income Secondary Income Under 18 years old Above 18 years old Under 18 years old Above 18 years old Employment 1 Farmer Forestry Planting Unemployment 22 Mã Văn Sáng Tày 23 Ngô Thị Vân Kinh 1 Trader Forestry Planting 24 Nguyễn Đức Nhuần Kinh Trader Forestry Planting 25 Nguyễn Đức Thành Kinh 1 Worker Forestry Planting 26 Nguyễn Đức Tốt Kinh 1 Soldier Forestry Planting 27 Nguyễn Hữu Nhuyên Kinh Farmer Forestry Planting 28 Nguyễn Ngọc Hiến Kinh 1 Soldier Forestry Planting 29 Nguyễn Thị Thuỷ Kinh 2 Forestry planting Forestry Planting 30 Nguyễn Thị Tình Kinh 1 Trader Forestry Planting 31 Nguyễn Văn Huế Kinh 1 Soldier Forestry Planting 32 Nguyễn Văn Phượng Kinh 2 Farmer Forestry Planting 33 Nguyễn Văn Thành Kinh 1 Farmer Forestry Planting 34 Nguyễn Văn Tới Kinh 1 Soldier Forestry Planting 35 Nông Văn Lan Tày Forestry planting Forestry Planting 36 Phạm Nam Hương Kinh 1 Soldier Forestry Planting 37 Phan Thị Nhật Kinh 1 1 Trader Forestry Planting 38 Tơ Văn Nà Sán Dìu 1 Forestry planting Forestry Planting 39 Bùi Quốc Duy Kinh 1 Trader Forestry Planting 40 Hà Mạnh Hùng Tày Farmer Forestry Planting 41 Trần Thị Châu Kinh Farmer Forestry Planting 42 Cong Hoa Commitee 1 Page 15 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Cam hai: Family member No Name of household head Male Ethnic Under 18 years old Job situation of the hhs members Female Above 18 years old Under 18 years old Above 18 years old Employment Forestry Planting Forestry Planting Bùi Văn Tay Kinh Đào Xuân Quang Kinh 1 Hà Văn Dương Kinh 1 Hà Văn Tình Kinh Hồng Văn Ngọc Kinh Lê Đức Tính Kinh Lưu Đức Oanh Kinh Đỗ Văn Lỳ Kinh Mai Thị Việt Kinh 10 Hoàng Văn Ngọc Kinh 11 Nguyễn Văn Việt Kinh 12 Nguyễn Văn Tần Kinh 13 Nông Thị Vấn Tày 14 Phạm Bá Quyết Kinh 1 15 Phạm Thị Gái Kinh 2 16 Trần Thị Thúy Nga Kinh 3 17 Phạm Thị Thu Ánh Kinh 1 18 Trương Thị Dịu Kinh 1 19 Trương Văn Trò Kinh Trần Thị Bùng Kinh Trần Thị Châu Kinh Từ Minh Ngọc Sán Dìu Hồng Văn Nghiên Kinh Secondary Income Unemployment 2 Primary Income Trader 1 Worker Forestry planting Farmer Forestry planting Trader 1 Worker 1 Forestry Planting Worker 1 Farmer Farmer Forestry planting Trader Worker Aquaculture Forestry planting Worker Forestry planting Worker Forestry planting Worker Aquaculture 20 Forestry planting Farmer Forestry planting 1 Aquaculture Forestry planting 21 22 23 1 1 1 Page 16 of 28 Trader 2 Farmer Aquaculture Forestry planting Forestry planting st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project No10.ward Sexual Name of household head No Male Ethnic Under 18 years old Above 18 years old 1 Bàn Văn Năm Dao Bùi Quang Chiến Kinh Bùi Quang Chính Kinh Bùi Quang Cường Kinh Đàm Văn Ắm Tày Đặng A Sắt Dao Đặng A Ửng Job situation of the hhs members Female Under 18 years old Above 18 years old Employment Primary income Unemployment Farmer Farmer Farmer 1 Farmer Farmer 1 2 Dao 3 Worker Đặng Phúc Tiến Dao 1 Farmer Đặng Thị Loan Kinh 1 Worker 10 Đặng Văn Ba Dao 2 Worker 11 Đặng Văn Nguyên Dao 1 1 Worker 12 Đặng Văn Tư Dao Farmer 13 Đặng Xuân Ba Dao 1 1 14 Đặng Xuân Cường Dao 1 Farmer 15 Đặng Xuân Lương Dao 1 Farmer 16 Đặng Xuân Minh Dao Farmer 17 Đào Đức Thọ Kinh 1 Farmer 18 Đào Văn Chuỳ Kinh 1 Worker 19 Đỗ Thị Hồng Kinh 20 Đỗ Văn Biên Kinh 1 21 Hà Văn Hầu Tày 1 22 Hồ Quay Phương Dao 1 1 23 Hồ Văn Đức Dao 2 Farmer 24 Hồ Văn Phúc Dao 1 1 Worker 25 Hồ Văn Thanh 2 Worker 26 Hoàng Thị Bé Tày 1 Farmer 27 Hoàng Thị Kim Dao 1 Farmer 28 Hoàng Thị Liên Tày 29 Hoàng Văn Anh 1 30 Hoàng Văn Khoa Kinh Tày, Dao 1 1 Page 17 of 28 Farmer Farmer 1 Retirement Farmer Forestry planting Farmer Forestry planting Forestry planting Farmer Secondary income st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Sexual No Name of household head Male Ethnic Under 18 years old Job situation of the hhs members Female Primary income Above 18 years old Under 18 years old Above 18 years old Employment 1 1 Forestry planting 1 Forestry planting Unemployment 31 Hoàng Xuân Đoàn Tày 32 La Văn Bộ Tày 33 La Văn Huấn Tày 34 Lê Văn Nam Kinh 35 Lê Văn Nhất Kinh 36 Loan Văn Phổ Tày 37 Loan Văn Quang Tày Forestry planting 38 Loan Văn Tô 1 Worker 39 Loan Văn Tường Tày Tày, Nùng Worker 40 Loan Văn Việt Tày 41 Lộc Văn Vương Tày, Kinh 42 Lục Văn Hùng 43 1 Farmer 2 Farmer Worker Forestry planting 2 Forestry planting 1 Forestry planting Tày 1 Forestry planting Lương Văn Cò Tày 1 Forestry planting 44 Lương Văn Yên Tày, Dao 1 Forestry planting 45 Lý Minh Trọng Dao 1 Farmer 46 Lý Minh Tuấn Dao 47 Lý Thị Hai Dao 48 Lý Thị Tư Dao 49 Lý Văn Hai Dao 50 Lý Văn Năm Dao 51 Lý Văn Phúc Dao 52 Lý Văn Sáu Dao 2 53 Lý Văn Tư Dao 2 1 54 Lý Văn Việt Dao 2 55 Lý Xuân Cảnh Dao 1 56 Lý Xuân Minh Dao 57 Lý Xuân Thắng (Lý Xuân Hồng) Dao 1 2 Secondary income 1 Farmer Farmer Farmer Farmer 2 Forestry planting Forestry planting Page 18 of 28 Farmer Forestry planting Farmer Forestry planting Farmer Forestry planting Farmer Forestry planting Farmer Forestry planting Forestry planting st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Sexual No Name of household head Male Ethnic Job situation of the hhs members Female Primary income Under 18 years old Above 18 years old Under 18 years old Above 18 years old Employment 1 1 Forestry planting 1 Forestry planting Unemployment 58 Ngọc Văn Bẩy Tày 59 Ngọc Văn Chiều Tày 60 Ngọc Văn Miêu Tày 1 61 Nguyễn Bảo Long Kinh, Dao 1 62 Nguyễn Đức Thức Kinh 1 63 Nguyễn Như Đạo Kinh 1 64 Nguyễn Quốc Đệ Kinh 65 Nguyễn Sỹ Nam Kinh Worker 66 Nguyễn Thanh Cảnh Tày Forestry planting 67 Nguyễn Thị Hoa Kinh 68 Nguyễn Thị Linh Kinh 69 Nguyễn Văn Long Kinh 70 Nguyễn Văn Luân Kinh 71 Nguyễn Văn Nức 72 Nguyễn Văn Sỹ Kinh Kinh, Tày 73 Tày 74 Nguyễn Văn Tá Nguyễn Văn Thanh 75 1 1 Farmer Forestry planting Farmer Forestry planting Farmer Forestry planting Retirement Forestry planting Retirement Forestry planting 1 Forestry planting Forestry planting 1 Worker Farmer Farmer Farmer 1 1 Farmer Kinh 1 1 Worker Nguyễn Văn Thụy Kinh 2 Worker 76 Nguyễn Xuân Qúy (Qúy Ngà) Kinh 1 1 Trader 77 Nông Quốc Khánh Tày Worker 78 Nông Văn Toản Tày 79 Phạm Huy Cường Kinh 80 Phạm Thị Giang Kinh 81 Phng Cắm Cơng Dao 82 Phng Cắm Tắc Dao 1 83 Phoòng Cắm Thành Dao 1 1 Forestry planting 84 Phng Đình Huy Dao 1 Farmer Forestry planting 1 Forestry planting Forestry planting 1 Page 19 of 28 Secondary income Forestry planting Forestry planting st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Sexual No Name of household head Male Ethnic Under 18 years old Job situation of the hhs members Female Above 18 years old Under 18 years old Above 18 years old Dao 86 Phng Đình Phú Phng Đình Thống Dao 1 87 Phng Đình Vinh Dao 2 85 1 Secondary income Unemployment Farmer Farmer Forestry planting Worker Forestry planting Worker 1 Forestry planting 88 Phoòng Tắc Qúy Dao 89 Phoòng Tài Múi 90 Phoòng Thị Mai Dao Dao, Kinh 1 1 91 Phoòng Văn Sinh Dao 1 Farmer Forestry planting 92 Phoòng Văn Tư Dao 2 Farmer Forestry planting 93 Phùn A Hải Dao 1 94 Phùn A Phúc Dao 95 Phùn A Sơn Dao 96 Phùn Văn Tư (Phoòng Thị Mai) Dao 1 97 Tạ Hữu Hợi Kinh 1 98 Triệu Chăn Thống Dao 1 99 Triệu Kim Tề Dao 100 Triệu Quý Bình Dao 101 Triệu Quý Dếnh 102 Employment Primary income 1 Farmer Forestry planting Forestry planting 1 Farmer Farmer 1 Worker Trader Worker Forestry planting Worker Worker 1 Forestry planting Dao 2 Forestry planting Triệu Quý Quân Dao 1 Forestry planting 103 Triệu Qúy Sáng 1 Worker 104 Triệu Xuân Lợi Dao Dao, Chiêm Worker 105 Vi Văn Đăng Tày, kinh 106 Vi Xuân Lộc 107 1 Farmer Farmer Forestry planting Farmer Forestry planting Trader Forestry planting 1 Tày 1 Vũ Văn Tơn Kinh 108 Phùn Thị Minh Dao 109 Vi Thị Hồng Tày 110 Vi Thị Huệ Tày Farmer 111 Vi Văn Muội Tày Farmer 1 Page 20 of 28 Aquaculture Farmer Forestry planting st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Sexual No Name of household head Male Ethnic 112 Triệu Quang Sáu 113 Vi Văn Đăng Tày, kinh 114 Vi Xuân Lộc 115 Under 18 years old Job situation of the hhs members Female Above 18 years old Under 18 years old Above 18 years old Employment Primary income Unemployment Farmer 1 Tày 1 Vũ Văn Tơn Kinh 116 Đỗ Thị Hồng Kinh Trader 117 Đỗ Văn Biên Kinh 1 Trader 118 Triệu Chăn Thống Dao 1 Worker 119 Lý Văn Việt Dao 2 1 Farmer 120 Triệu Kim Tề Dao Farmer 121 Lã Văn Nàng Dao 1 Farmer 122 Vi Thị Liều Tày 1 1 123 Phùng Văn Tơn Dao 2 124 Phạm Thị Luyến Đong Mo High School Mong duong Committee Dong Mo Medecine Center Kinh 1 126 127 Page 21 of 28 Forestry planting Forestry planting 125 Secondary income Forestry planting Forestry planting Farmer Farmer Trader Trader Forestry planting Forestry planting Forestry planting st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix Situation of Compensation Payment Appendix 2.1: Situation of Compensation Payment until 31/3/2014 Date of project information dissemination No Making compensation plan Verify and approve the compensation plan Situation of Compensation payment Situation of Site Clearance Component Starting date Detailed Measurement Survey Finishing date Starting date Finishing date Starting date Finishing date Submitting date Approval Starting date Finishing date Continue Continue Pineline 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 24/12/12 Cộng Hòa 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 24/12/12 Starting date 14/1/13 Cẩm Hải 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 Resevoir 24/8/11 31/11/13 10/10/11 31/11/13 13/11/11 31/11/13 12/11/12 31/11/13 24/12/12 24/12/12 24/8/11 31/11/13 10/10/11 31/11/13 13/11/11 31/11/13 Page 22 of 28 12/11/12 31/11/13 24/12/12 6/12/13 6/12/13 14/1/13 6/12/13 Continue 14/1/13 Continue Mông Dương Continue Continue Continue Continue Finishing date 14/1/13 Continue Contract award Continue 31/3/14 5/4/14 5/4/14 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 2.2: Number of Affected Households until 31/3/2014 Total Affected HHs (both long term and short term Affected HHs Long term affected households HHs with Vulnerable People No Of Severe HHs No Component Total Lost from 10% or more of agricultural land Number of resettled HHs No Of Nonesevere HHs Affected Business HHs Poor HHs Ethic Minorities HHs Single Woman headed HHs Social Policy HHs Pineline 53 53 12 5 65 Cộng Hòa 36 36 42 Cẩm Hải 17 17 1 23 Resevoir 101 101 37 26 93 127 Mông Dương 101 101 37 26 93 127 154 154 37 38 11 98 10 192 Total Page 23 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 2.3: Area of the acquired land until 31/3/2014 No Components/ Packages Permanently Acquired Land Area (m2) Agricultural Land Residential Land Aquacultural Area Forest Land Temporarily Acquired Land Area (m2) Other Land Total Forest Land Other Land Total Pineline 0.0 0.0 12,956.80 324,703.13 145,351.70 483011.63 11460.7 6295.8 17756.5 Cộng Hòa 0.0 0.0 269.00 195,251.53 98,304.20 293824.73 0.0 1667.0 1667.0 Cẩm Hải 0.0 0.0 12,687.80 129,451.60 47,047.50 189186.90 11460.7 4628.8 16089.5 Resevoir 225,309.5 8,000.0 13,872.65 305,863.50 813,354.16 1366399.76 0.0 0.0 0.0 Mông Dương 225,309.5 8,000 13,872.65 305,863.50 813,354.16 1366399.76 0.0 0.0 0.0 Total 225,309.5 8,000.0 26,829.45 630,566.63 958,705.86 1849411.39 11460.7 6295.8 17756.5 Page 24 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 2.4: Housing and other assets affected until 31/3/2014 No Components/ Packages Affected Housing Area (m2) Affected Rice and crops area (m2) Affected Factory Area (m2) Affected Shop Area (m2) Affected Tree (tree) Relocated Graves (pcs) Affect Objects/ Architect Works Pipeline 2,004.8 0.0 288.0 528.0 73,512.0 Cộng Hòa 1,198.0 0.0 288.0 310.0 46,232 Cẩm Hải 806.8 0.0 0.0 218.0 27,280 Resevoir Mông Dương 2,813.0 0.0 0.0 169,765.0 99,893 2,813 0.0 0.0 169,765.0 96,791 Total 4,817.8 0.0 288.0 170,293.0 173,405.0 Affected Other Assets Appendix 4.1 Appendix 4.1 0.0 - Appendix 2.4.1: Affected Other Assets until 31/3/2014 No Components/ Packages Pineline Toilet Kitchen Bathroom Well Barns Cement roof Fence Water Tank Electric Line (m2) (m2)/ (m2) (pcs) (m2) (m2) (m2) (m3) (m) 16.92 144.27 2.79 1.00 329.20 130.56 8.40 372.76 4490.00 Cộng Hòa 0.00 10.63 2.79 1.00 35.60 0.00 0.00 50.19 1695.00 Cẩm Hải 16.92 133.64 0.00 0.00 293.60 130.56 8.40 322.57 2795.00 Resevoir 89.36 419.86 87.20 8.00 1,758.30 127.80 32.60 851.60 18537.70 Mông Dương 89.36 419.86 87.20 8.00 1758.30 127.80 32.60 851.60 18537.70 106.28 564.13 89.99 9.00 2087.50 258.36 41.00 1224.36 23027.70 Total Page 25 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 5: Situation of Compensation Payment until 31/3/2014 Compensation Cost (VND) No Component Pineline Total of cost estimation approved by 31/3/2014 Total of cost according to the compensation plan Paid and None-paid yet (VND) Paid until 31/3/2014 Situation of Compensation No of HHs received compensation None-paid Situation of Site Clearance No of HHs nonereceived compensation No of HHs handed over the sites No of HHs have not been handed over the sites 17,074,100,200 17,074,100,200 17,074,100,200 65 65 Cộng Hòa 7,670,930,200 7,670,930,200 7,670,930,200 40 42 Cẩm Hải Pipeline (addition Recovery) 7,365,028,400 7,365,028,400 7,365,028,400 20 23 2,038,141,600 2,038,141,600 2,038,141,600 0 Resevoir 80,401,106,900 80,401,106,900 79,715,119,700 615,987,200 126 127 Mông Dương 80,401,106,900 80,401,106,900 79,715,119,700 615,987,200 126 127 97,405,207,100 97,405,207,100 96,789,219,900 615,987,200 191 191 Total Page 26 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 2.6: Situation of Compensation Payment until 31/3/2014 No of HHs are satisfactorily resolved No of Complained HHS No of HHs are satisfactorily resolved No of Complained HHS No of HHs are satisfactorily resolved No of Complained HHS No of HHs are satisfactorily resolved Court No of Complained HHS Provincial Level No of HHs are satisfactorily resolved Provincial PMU No of Complained HHS Compensation Committee No of HHs are satisfactorily resolved District Level No of Complained HHS Communal Level Resevoir 17 14 0 0 0 0 0 Pipeline 8 0 0 0 0 0 Total 25 23 0 0 0 0 0 Components/ Packages Page 27 of 28 st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project Appendix 2.7: Progress on compensation and resettlement implementation till 31/3/2014 Component Activities on compensation and resettlement Information Dissemination and Community Participation Detailed Measure Survey (DMS) Setting Compensation Plan Consulting and Counseling with the APs on compensation plan Update the RP and approve by ADB Finalized the compensation plan and submit for approval Verify and approve the compensation plan Consultate the APs on the approved compensation plan (to the agricultural land) Compensation Payment Resettlement and Site Clearance Independent Monitoring and Reporting Compensation Progress by component Compensation Progress of the Project Resevoir Component Pipeline Component Cộng Hòa Complete situation Cẩm Hải Mông Dương Complete situation Complete situation 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 99.37% 100.0% 100.0% 99.37% 100.0% 100.0% 99.37% 100.0% 100.0% 99.37% 100.0% 100.0% 99.37% Page 28 of 28

Ngày đăng: 12/05/2021, 00:47

w